JURISDICTION : SUPREME COURT OF WESTERN AUSTRALIA
IN CIVIL
CITATION: LAING O'ROURKE AUSTRALIA CONSTRUCTION PTY LTD -v- SAMSUNG C & T CORPORATION [2015] WASC 237
CORAM: MITCHELL J
HEARD: 10 - 11 JUNE 2015
DELIVERED : 3 JULY 2015
FILE NO/S: CIV 1644 of 2015
BETWEEN: LAING O'ROURKE AUSTRALIA CONSTRUCTION PTY LTD
Plaintiff
AND
SAMSUNG C & T CORPORATION
Defendant
FILE NO/S :CIV 1645 of 2015
BETWEEN :SAMSUNG C & T CORPORATION
Applicant
AND
GRAHAM IVAN ANSTEE-BROOK
RespondentLAING O'ROURKE AUSTRALIA CONSTRUCTION PTY LTD
Other Party
FILE NO/S :CIV 1733 of 2015
BETWEEN :SAMSUNG C & T CORPORATION
Applicant
AND
GRAHAM IVAN ANSTEE-BROOK
RespondentLAING O'ROURKE AUSTRALIA CONSTRUCTION PTY LTD
Other Party
FILE NO/S :CIV 1793 of 2015
BETWEEN :LAING O'ROURKE AUSTRALIA CONSTRUCTION PTY LTD
Plaintiff
AND
SAMSUNG C & T CORPORATION
Defendant
Catchwords:
Judicial review - Jurisdictional error - Unreasonableness - Inferred error - Construction contract adjudication - Failure to determine payment dispute by reference to the terms of the construction contract
Construction contracts - Leave to enforce adjudicator's determination - Whether leave should be refused because payment has already been made
Words and phrases - 'Payment claim' - 'Payment dispute' - Whether payment dispute can arise before the payment is due under the construction contract
Legislation:
Construction Contracts Act 2004 (WA), s 6, s 31, s 32, s 41, s 43, s 45
Result:
Certiorari issued
Leave to enforce determination refused
Category: A
Representation:
CIV 1644 of 2015
Counsel:
Plaintiff: Mr S K Dharmananda SC & Mr M R Collins
Defendant: Mr C G Colvin SC & Mr B Millar
Solicitors:
Plaintiff: Clyde & Co Australia
Defendant: Herbert Smith Freehills
CIV 1645 of 2015
Counsel:
Applicant: Mr C G Colvin SC & Mr B Millar
Respondent: No appearance
Other Party : Mr S K Dharmananda SC & Mr M R Collins
Solicitors:
Applicant: Herbert Smith Freehills
Respondent: No appearance
Other Party : Clyde & Co Australia
CIV 1733 of 2015
Counsel:
Applicant: Mr C G Colvin SC & Mr B Millar
Respondent: No appearance
Other Party : Mr S K Dharmananda SC & Mr M R Collins
Solicitors:
Applicant: Herbert Smith Freehills
Respondent: No appearance
Other Party : Clyde & Co Australia
CIV 1793 of 2015
Counsel:
Plaintiff: Mr S K Dharmananda SC & Mr M R Collins
Defendant: Mr C G Colvin SC & Mr B Millar
Solicitors:
Plaintiff: Clyde & Co Australia
Defendant: Herbert Smith Freehills
Case(s) referred to in judgment(s):
A v Corruption and Crime Commission [2013] WASCA 288; (2013) 306 ALR 491
Alcan (NT) Alumina Pty Ltd v Commissioner of Territory Revenue [2009] HCA 41; (2009) 239 CLR 27
Alliance Contracting Pty Ltd v James [2014] WASC 212
Australian Broadcasting Commission v Australasian Performing Right Association Ltd (1973) 129 CLR 99
Avon Downs Pty Ltd v Federal Commissioner of Taxation (1949) 78 CLR 353
Balog v Independent Commission Against Corruption (1990) 169 CLR 625
Barrett v Coroner's Court of South Australia [2010] SASCFC 70; (2010)…
Keep reading for free
Create a free CaseChat account to read Laing O'Rourke Australia Construction Pty Ltd v Samsung C &... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2015] WASC 237
- Decision Date
CaseChat Overview and Summary
The central legal issue was whether the adjudicator had the jurisdiction to determine a payment dispute when the payment in question had already been made. The court was also required to determine whether the existence of a payment dispute in relation to a payment claim under a construction contract was a jurisdictional fact. The interpretation of the relevant statutory provisions, including the definition of 'payment claim' and 'payment dispute', was crucial to resolving these issues.
The court examined the relevant statutory provisions and the context in which they appeared. It concluded that the adjudicator's power to determine a payment dispute was subject to certain conditions, and that the existence of a payment dispute was a jurisdictional fact. The court found that the adjudicator had failed to comply with the statutory requirements in making the First and Second Determinations, and that these decisions were therefore unauthorised. The court granted the applicant's application for judicial review and quashed the adjudicator's determinations.
The court also noted that the applicant's argument that the payment dispute could not arise before the payment was due under the construction contract was not relevant to the jurisdictional issue before the court. The court emphasised that the issues raised in the case were to be resolved by construing the Act to identify the limits on the adjudicator's power to determine a payment dispute, followed by a factual inquiry to see if he had transgressed those limits on his authority. The court's decision was based on a careful analysis of the statutory provisions and the context in which they appeared, and did not speculate on any other possible outcomes.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence before the court
Decision
Reasons for decision
Ratio Decidendi
Legal principle established
Other rules of statutory construction concern what are often referred to as grounds of judicial review. For example, common law rules of statutory construction will assume that the rules of procedural fairness condition the valid exercise of certain statutory powers.[43] Grounds of review such as taking irrelevant considerations into account, or failing to take relevant considerations into account, are based on a construction of legislation as either prohibiting or requiring that regard be had to those matters.[44] A ground of review which asserts improper purpose asserts that a power was exercised for a purpose not authorised by the relevant Act.[45] A ground which asserts misapprehension of the nature or limits of the relevant statutory power[46] reflects a requirement of the law that a decision‑maker understand his or her statutory powers and obligations.[47][43] Plaintiff S10/2011 v Minister for Immigration [2012] HCA 31; (2012) 246 CLR 636 [97].[44] Minister for Aboriginal Affairs v Peko‑Wallsend Ltd (1986) 162 CLR 24, 39 ‑ 40; A v Corruption and Crime Commission [2013] WASCA 288; (2013) 306 ALR 491 [88] - [90].[45] Thompson v Randwick Corporation (1950) 81 CLR 87; R v Toohey; Ex parte Northern Land Council (1981) 151 CLR 170, 186, 233; Hunter v Minister for Planning [2012] WASC 247 [24].[46] Kirk [72]; Craig v South Australia (1995) 184 CLR 163, 177 ‑ 178.[47] Li [71]. Where the alleged jurisdictional error arises out of a failure to comply with legislative requirements, it is necessary to ask whether it was a purpose of the legislation that an act done in breach of the provision should be invalid. Answering that question is also a matter of construction of the relevant legislation, having regard to the language of the relevant provision and the scope and object of the whole statute.[48][48] Project Blue Sky [91] - [93]. An assertion of jurisdictional error in relation to the exercise of a statutory power is therefore a contention that the holder has purported exercised his or her power other than in accordance with the conditions for the valid exercise of the relevant power. The identification of the conditions which mark the limits of the holder's authority to decide is purely a matter of statutory construction. Those limits are to be identified by the application of common law and statutory rules of construction to the language which Parliament has chosen understood in the context in which it appears. Therefore, the issues raised in the present case are to be resolved by construing the Act to identify the limits on the adjudicator's power to determine a payment dispute, followed by a factual inquiry to see if he has transgressed those limits on his authority. Put simply, the question is whether the First and Second Determinations were authorised by the Act. Submissions in this case were directed to the issue of whether the existence of a payment dispute in relation to a payment claim under a construction contract was a 'jurisdictional fact'.