JURISDICTION : STATE ADMINISTRATIVE TRIBUNAL
STREAM: COMMERCIAL & CIVIL
ACT: CONSTRUCTION CONTRACTS ACT 2004 (WA)
CITATION: BLACKADDER SCAFFOLDING SERVICES (AUST) PTY LTD and MIRVAC HOMES (WA) PTY LTD [2009] WASAT 133
MEMBER: MR C RAYMOND (SENIOR MEMBER)
MR T CAREY (MEMBER)
HEARD: 20 MAY 2009
DELIVERED : 30 JUNE 2009
FILE NO/S: CC 545 of 2009
BETWEEN: BLACKADDER SCAFFOLDING SERVICES (AUST) PTY LTD
Applicant
AND
MIRVAC HOMES (WA) PTY LTD
Respondent
Catchwords:
Construction Contracts Act 2004 (WA) - Application for review of decision by adjudicator to dismiss - Grounds of dismissal that application not served in time - Whether provisions of Sch 1, Div 5 to be implied - Whether review encompasses other grounds for dismissal not considered by adjudicator
Legislation:
Construction Contracts (Security of Payments) Act (NT), s 20
Construction Contracts Act 2004 (WA), s 3, s 6, s 6(a), s 13, s 15, s 16, s 17, s 18, s 26, s 31, s 31(2), s 32(2), s 46(1), Pt 2 Div 2, Sch 1 Div 5, cl 6, cl 7
Interpretation Act 1984 (WA), s 18, s 19(1)
Result:
Application refused
Decision under review affirmed
Category: B
Representation:
Counsel:
Applicant: Mr R Shaw
Respondent: Mr V Liu
Solicitors:
Applicant: Lavan Legal
Respondent: Minter Ellison
Case(s) referred to in decision(s):
Marine & Civil Bauer Joint Venture and Leighton Kumagai Joint Venture [2005] WASAT 269
Merym Pty Ltd and Methodist Ladies College [2008] WASAT 164
Moroney and Murray River North Pty Ltd [2008] WASAT 111
Silent Vector Pty Ltd and Squarcini [2008] WASAT 39
REASONS FOR DECISION OF THE TRIBUNAL:
Summary of Tribunal's decision
The applicant applied under s 46(1) of the Construction Contracts Act 2004 (WA) to review a decision of an adjudicator to dismiss an adjudication application without a determination of the merits.
On a proper construction of the legislation, the Tribunal concluded that a payment dispute was triggered either if payment of a claim was not made when it fell due under the contract or when the claim had been rejected wholly or in part. However, as the contract in question did not have a provision as to how and when to respond to a progress claim, the implied provisions set out in Sch 1 Div 5 to the Construction Contracts Act 2004 (WA) applied. Those provisions obliged the respondent to give notice within 14 days of receipt of the payment claim if it disputed the claim. The respondent had done so, but not within the stipulated timeframe.
The Tribunal held that a late notice of dispute given outside the 14 day period nevertheless operated to trigger the existence of a payment dispute. Consequently, although for different reasons, the adjudicator was correct in concluding that the adjudication application was not served within the required 28 days from the date of the non‑complying notice of dispute.
The Tribunal held that it was entitled to determine submissions which had been raised before the adjudicator but not determined by him. On an analysis of the facts, it was…
Keep reading for free
Create a free CaseChat account to read Blackadder Scaffolding Services (Aust) Pty Ltd and Mirvac Ho... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2009] WASAT 133
- Decision Date
CaseChat Overview and Summary
The primary legal issues before the court were whether the application for review was to be dismissed due to non-compliance with the service requirements and if the review process could include additional grounds for dismissal not addressed by the adjudicator. The court had to determine if the statutory provisions could be implied into the contract and if the scope of the review included the consideration of additional grounds for dismissal not explicitly addressed by the adjudicator.
The court held that the application for review should be dismissed because the statutory provisions were not implied into the contract, and the timeliness of the service was a mandatory requirement. The court found that the provisions of Schedule 1, Division 5 could not be implied into the contract, and thus the adjudicator’s decision not to consider the application on substantive merits was upheld. Additionally, the court ruled that the review process was limited to the grounds considered by the adjudicator, and it could not encompass other grounds for dismissal not considered by the adjudicator. Consequently, the decision of the adjudicator was affirmed.
As a result of the court’s decision, the application for review was refused, and the dismissal of Blackadder’s adjudication application was upheld. The court’s ruling confirmed the adjudicator’s authority in procedural matters and underscored the importance of compliance with statutory requirements.
Orders
Orders of the court
1. The application for review is refused. 2. The decision of the adjudicator dated 26 March 2009 dismissing the adjudication application is affirmed.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi