LONGMONT CONSOLIDATED PTY LTD and FLEETWOOD PTY LTD

Link copied
Case Copied 12 min read

JURISDICTION     :   STATE ADMINISTRATIVE TRIBUNAL

STREAM:   COMMERCIAL & CIVIL

ACT: CONSTRUCTION CONTRACTS ACT 2004 (WA)

CITATION:   LONGMONT CONSOLIDATED PTY LTD and FLEETWOOD PTY LTD [2010] WASAT 23

MEMBER:   MR C RAYMOND (SENIOR MEMBER)

MS J HAWKINS (MEMBER)

HEARD:   18 NOVEMBER 2009

DELIVERED          :   17 FEBRUARY 2010

FILE NO/S:   CC 1447 of 2009

BETWEEN:   LONGMONT CONSOLIDATED PTY LTD

Applicant

AND

FLEETWOOD PTY LTD
Respondent

Catchwords:

Construction Contracts Act 2004 (WA) - Application for review of decision by adjudicator to dismiss - Grounds of dismissal that application not served in time ­ Whether provisions of Sch 1, Div 5 to be implied

Legislation:

Construction Contracts Act 2004 (WA), s 3, s 6, s 16, s 17, s 18, s 26, s 26(1), s 46(1), s 53, Sch 1 Div 5, Sch 1 Div 5 cl 7, Sch 1 Div 5 cl 7(3)

Result:

Application for review dismissed

Category:    B

Representation:

Counsel:

Applicant:     Mr G Morrow

Respondent:     Mr CA Ryder

Solicitors:

Applicant:     Downings Legal

Respondent:     Corrs Chambers Westgarth

Case(s) referred to in decision(s):

Longmont Consolidated Pty Ltd and Fleetwood Pty Ltd [2010] WASAT 22

REASONS FOR DECISION OF THE TRIBUNAL: 

Summary of Tribunal's decision

  1. The applicant applied under s 46(1) of the Construction Contracts Act 2004 (WA) to review a decision of an adjudicator to dismiss an adjudication application as being out of time without a determination of the merits.

  2. The Tribunal held that the decision of the adjudicator to the effect that the adjudication application was out of time was correct, although for different reasons.

  3. The Tribunal concluded that the relevant contractual provision concerning payments to the applicant was dependent on an approved invoice being submitted.  The relevant contractual provision required the applicant to submit estimates of work performed and projected for performance during that month and by the 20th of each month.  Once such an estimate is provided, the respondent was required to review the estimates and, upon approval, return them to the applicant to be submitted on the 1st of the following month.  The relevant clause went on to provide that only following that process was the respondent to make payment to the applicant 30 days after receipt of an approved invoice.

  4. The Tribunal held that the relevant contractual provision was silent as to what was to occur should an estimate not be approved or where no response to an estimate was given, and therefore did not provide a mechanism for making or responding to a payment claim, as defined in s 3 of the Construction Contracts Act 2004 (WA).

  5. Alternatively, the Tribunal found that such a contractual provision purports to modify or restrict the operations of the Construction Contracts Act 2004 (WA) and had no effect by virtue of s 53 of that Act.

  6. On either bases, the Tribunal found that s 16, s 17 and s 18 of the Construction Contracts Act 2004 (WA) applied and that, consequently, no payment dispute ever arose and, therefore, the adjudication application was made within 28 days of a payment dispute…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read LONGMONT CONSOLIDATED PTY LTD and FLEETWOOD PTY LTD and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2010] WASAT 23
Decision Date

CaseChat Overview and Summary

Longmont Consolidated Pty Ltd (Longmont) sought a review of a decision by an adjudicator to dismiss its application for adjudication, which was out of time. The application was made under the Construction Contracts Act 2004 (WA) (CC Act). The dispute involved the interpretation of a contractual provision concerning payment claims, specifically Special Condition 15 (SC-15) in the contract between Longmont and Fleetwood Pty Ltd (Fleetwood). Longmont claimed a payment dispute arose with Fleetwood in respect of a payment claim made for Spotters Costs dated 4 May 2009. Fleetwood argued that Longmont's application for adjudication was out of time. The adjudicator found that as the contract was silent as to what was to occur if Longmont's invoice was not assessed as 'correct', the provisions of Schedule 1 Division 5 of the CC Act were to be implied. The adjudicator then went on to find that the payment dispute arose 28 days after 20 May 2009, being 17 June 2009. The adjudicator found that the latest date for service of the application for adjudication was 28 days after 17 June 2009, being 15 July 2009. As the adjudication application was served on 28 July 2009, it was dismissed for being out of time.

The tribunal found that the relevant contractual provision concerning payments to Longmont was dependent on an approved invoice being submitted. SC-15 required Longmont to submit estimates of work performed and projected for performance during that month and by the 20th of each month. Once such an estimate was provided, Fleetwood was required to review the estimates and, upon approval, return them to Longmont to be submitted on the 1st of the following month. The relevant clause went on to provide that only following that process was Fleetwood to make payment to Longmont 30 days after receipt of an approved invoice. The Tribunal held that the relevant contractual provision was silent as to what was to occur should an estimate not be approved or where no response to an estimate was given, and therefore did not provide a mechanism for making or responding to a payment claim, as defined in s 3 of the CC Act. Alternatively, the Tribunal found that such a contractual provision purports to modify or restrict the operations of the CC Act and had no effect by virtue of s 53 of that Act.

On either basis, the Tribunal found that s 16, s 17 and s 18 of the CC Act applied and that, consequently, no payment dispute ever arose and, therefore, the adjudication application was made within 28 days of a payment dispute arising. The Tribunal, therefore, dismissed the application to review. The application to review the adjudicator's decision of 24 August 2009 in adjudication No 04-09-12 is dismissed. The decision of the adjudicator made on 24 August 2009 in adjudication No 04-09-12 is affirmed.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

MS J

Ratio Decidendi

Legal Principle Established

Established by: MS J