JURISDICTION : STATE ADMINISTRATIVE TRIBUNAL
STREAM: COMMERCIAL & CIVIL
ACT: CONSTRUCTION CONTRACTS ACT 2004 (WA)
CITATION: LONGMONT CONSOLIDATED PTY LTD and FLEETWOOD PTY LTD [2010] WASAT 23
MEMBER: MR C RAYMOND (SENIOR MEMBER)
MS J HAWKINS (MEMBER)
HEARD: 18 NOVEMBER 2009
DELIVERED : 17 FEBRUARY 2010
FILE NO/S: CC 1447 of 2009
BETWEEN: LONGMONT CONSOLIDATED PTY LTD
Applicant
AND
FLEETWOOD PTY LTD
Respondent
Catchwords:
Construction Contracts Act 2004 (WA) - Application for review of decision by adjudicator to dismiss - Grounds of dismissal that application not served in time Whether provisions of Sch 1, Div 5 to be implied
Legislation:
Construction Contracts Act 2004 (WA), s 3, s 6, s 16, s 17, s 18, s 26, s 26(1), s 46(1), s 53, Sch 1 Div 5, Sch 1 Div 5 cl 7, Sch 1 Div 5 cl 7(3)
Result:
Application for review dismissed
Category: B
Representation:
Counsel:
Applicant: Mr G Morrow
Respondent: Mr CA Ryder
Solicitors:
Applicant: Downings Legal
Respondent: Corrs Chambers Westgarth
Case(s) referred to in decision(s):
Longmont Consolidated Pty Ltd and Fleetwood Pty Ltd [2010] WASAT 22
REASONS FOR DECISION OF THE TRIBUNAL:
Summary of Tribunal's decision
The applicant applied under s 46(1) of the Construction Contracts Act 2004 (WA) to review a decision of an adjudicator to dismiss an adjudication application as being out of time without a determination of the merits.
The Tribunal held that the decision of the adjudicator to the effect that the adjudication application was out of time was correct, although for different reasons.
The Tribunal concluded that the relevant contractual provision concerning payments to the applicant was dependent on an approved invoice being submitted. The relevant contractual provision required the applicant to submit estimates of work performed and projected for performance during that month and by the 20th of each month. Once such an estimate is provided, the respondent was required to review the estimates and, upon approval, return them to the applicant to be submitted on the 1st of the following month. The relevant clause went on to provide that only following that process was the respondent to make payment to the applicant 30 days after receipt of an approved invoice.
The Tribunal held that the relevant contractual provision was silent as to what was to occur should an estimate not be approved or where no response to an estimate was given, and therefore did not provide a mechanism for making or responding to a payment claim, as defined in s 3 of the Construction Contracts Act 2004 (WA).
Alternatively, the Tribunal found that such a contractual provision purports to modify or restrict the operations of the Construction Contracts Act 2004 (WA) and had no effect by virtue of s 53 of that Act.
On either bases, the Tribunal found that s 16, s 17 and s 18 of the Construction Contracts Act 2004 (WA) applied and that, consequently, no payment dispute ever arose and, therefore, the adjudication application was made within 28 days of a payment dispute…
Keep reading for free
Create a free CaseChat account to read LONGMONT CONSOLIDATED PTY LTD and FLEETWOOD PTY LTD and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2010] WASAT 23
- Decision Date
CaseChat Overview and Summary
The tribunal found that the relevant contractual provision concerning payments to Longmont was dependent on an approved invoice being submitted. SC-15 required Longmont to submit estimates of work performed and projected for performance during that month and by the 20th of each month. Once such an estimate was provided, Fleetwood was required to review the estimates and, upon approval, return them to Longmont to be submitted on the 1st of the following month. The relevant clause went on to provide that only following that process was Fleetwood to make payment to Longmont 30 days after receipt of an approved invoice. The Tribunal held that the relevant contractual provision was silent as to what was to occur should an estimate not be approved or where no response to an estimate was given, and therefore did not provide a mechanism for making or responding to a payment claim, as defined in s 3 of the CC Act. Alternatively, the Tribunal found that such a contractual provision purports to modify or restrict the operations of the CC Act and had no effect by virtue of s 53 of that Act.
On either basis, the Tribunal found that s 16, s 17 and s 18 of the CC Act applied and that, consequently, no payment dispute ever arose and, therefore, the adjudication application was made within 28 days of a payment dispute arising. The Tribunal, therefore, dismissed the application to review. The application to review the adjudicator's decision of 24 August 2009 in adjudication No 04-09-12 is dismissed. The decision of the adjudicator made on 24 August 2009 in adjudication No 04-09-12 is affirmed.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Established by: MS J