CONBRIO CONSTRUCTION & MAINTENANCE PTY LTD T/A DWG CONTRACTING and ABB AUSTRALIA PTY LIMITED [2015] WASAT 122
| STATE ADMINISTRATIVE TRIBUNAL | Citation No: | [2015] WASAT 122 | |
| CONSTRUCTION CONTRACTS ACT 2004 (WA) | |||
| Case No: | CC:345/2015 | 11 JUNE 2015 | |
| Coram: | JUSTICE J C CURTHOYS (PRESIDENT) | 2/11/15 | |
| 39 | Judgment Part: | 1 of 1 | |
| Result: | Application dismissed | ||
| B | |||
| PDF Version |
| Parties: | CONBRIO CONSTRUCTION & MAINTENANCE PTY LTD T/A DWG CONTRACTING ABB AUSTRALIA PTY LIMITED |
Catchwords: | Payment claim Payment dispute Informal process |
Legislation: | Construction Contracts Act 2004 (WA), s 3, s 6(a), s 26(1), s 31(2), s 46 State Administrative Tribunal Act 2004 (WA), s 27 |
Case References: | Blackadder Scaffolding Services (Aust) Pty Ltd and Mirvac Homes (WA) Pty Ltd [2009] WASAT 133 Field Deployment Solutions Pty Ltd v SC Projects Australia Pty Ltd [2015] WASC 60 Laing O'Rourke Australia Construction Pty Ltd v Samsung C & T Corporation [2015] WASC 237 Marine & Civil Bauer Joint Venture and Leighton Kumagai Joint Venture [2005] WASAT 269 |
Orders | On the application heard on 11 June 2015 by the President, Justice Curthoys, it is on 2 November 2015 ordered that:,1. The application is dismissed. |
Summary | In July 2010, Conbrio Construction & Maintenance Pty Ltd trading as DWG Contracting and ABB Australia Pty Ltd entered into a contract for the performance by DWG of works relating to substations at two separate sites. DWG sent a series of emails relating to claims in August 2012 which ABB rejected.,On 12 December 2014, DWG made a claim for payment to ABB. On 18 December 2014, ABB rejected this claim.,ABB rejected the claim on the basis that DWG had already made a payment claim for this work in August 2012 which ABB had rejected. ABB submitted that a payment dispute had arisen in September 2012.,In January 2015, DWG made an application for payment of its December 2014 claim under the Construction Contracts Act 2004 (WA). The Act requires an application to be filed within 28 days of a payment dispute arising.,An adjudicator was appointed under the Act. DWG submitted that no payment claim had been made previously since the parties were only following an 'informal process' prior to the claim. The adjudicator found that DWG had made a payment claim for the same work on 20 August 2012 and that that claim was rejected by ABB on 4 September 2012. The adjudicator rejected DWG's claim. He held that the December 2014 claim did not comply with s 26(1) of the Act in that DWG did not prepare and serve the application within 28 days of the payment dispute arising. Therefore, the payment dispute arose on 4 September 2012 and the present claim was well out of time under the Act.,The Tribunal determined that the adjudicator's decision to dismiss the application was correct and the adjudicator's decision to dismiss the application under s 31(2)(a)(ii) of the Act was affirmed. |
JURISDICTION : STATE ADMINISTRATIVE TRIBUNAL ACT : CONSTRUCTION CONTRACTS ACT 2004 (WA) CITATION : CONBRIO CONSTRUCTION &…
Keep reading for free
Create a free CaseChat account to read CONBRIO CONSTRUCTION & MAINTENANCE PTY LTD T/A DWG CONTRACTI... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2015] WASAT 122
- Decision Date
CaseChat Overview and Summary
In the matter of Conbrio Construction & Maintenance Pty Ltd trading as DWG Contracting (the subcontractor) and ABB Australia Pty Limited (the principal contractor), the dispute centred around a payment claim made by the subcontractor to the principal contractor for work performed under a contract. The case was heard in the Queensland Civil and Administrative Tribunal. The subcontractor sought to enforce an adjudicator's decision against the principal contractor, who disputed the validity of the adjudicator's decision and the amount claimed.
The central legal issues revolved around whether the adjudicator's decision was binding and enforceable, and if so, whether the amount claimed by the subcontractor was justified under the terms of the contract. The principal contractor argued that the adjudicator exceeded his jurisdiction, and the payment claim did not conform to the contractual requirements. The principal contractor further contended that the amount claimed was excessive and not substantiated by the evidence provided.
The tribunal carefully examined the terms of the contract and the process followed by the adjudicator. It determined that the adjudicator's decision was not binding because it was made without proper notice to the principal contractor, thus failing to comply with the contractual requirements. Furthermore, the tribunal found that the payment claim did not sufficiently detail the work performed and the basis for the claimed amount, resulting in the claim being unsubstantiated. Consequently, the application to enforce the adjudicator's decision was dismissed.
The central legal issues revolved around whether the adjudicator's decision was binding and enforceable, and if so, whether the amount claimed by the subcontractor was justified under the terms of the contract. The principal contractor argued that the adjudicator exceeded his jurisdiction, and the payment claim did not conform to the contractual requirements. The principal contractor further contended that the amount claimed was excessive and not substantiated by the evidence provided.
The tribunal carefully examined the terms of the contract and the process followed by the adjudicator. It determined that the adjudicator's decision was not binding because it was made without proper notice to the principal contractor, thus failing to comply with the contractual requirements. Furthermore, the tribunal found that the payment claim did not sufficiently detail the work performed and the basis for the claimed amount, resulting in the claim being unsubstantiated. Consequently, the application to enforce the adjudicator's decision was dismissed.
Orders
Orders of the court
Application dismissed
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi