JURISDICTION : SUPREME COURT OF WESTERN AUSTRALIA
IN CHAMBERS
CITATION: M+W SINGAPORE PTE LTD -v- ANSTEE-BROOK [2016] WASC 310
CORAM: PRITCHARD J
HEARD: ON THE PAPERS
DELIVERED : 27 SEPTEMBER 2016
FILE NO/S: CIV 2881 of 2015
BETWEEN: M+W SINGAPORE PTE LTD
Applicant
AND
GRAHAM ANSTEE-BROOK
RespondentBROOKFIELD MULTIPLEX CONSTRUCTIONS PTY LTD
Other Party
Catchwords:
Practice and procedure - Consent orders - O 43 r 16 Rules of the Supreme Court 1971 (WA) - Consent orders in judicial review proceedings - Consent order for grant of prerogative relief - Requirement that Court be satisfied of grounds for and appropriateness of orders - Requirement that orders be within power - Where parties agree that decision-maker did not have jurisdiction to make the decision
Practice and procedure - Order for the issue of a writ of certiorari - Form of order - O 56 r 2(2) Rules of the Supreme Court 1971 (WA) - Court's power to make an order having the same effect as a prerogative writ - Whether necessary for order requiring decision-maker to deliver up decision to Court for purpose of being quashed - Whether sufficient to order that decision be quashed
Legislation:
Construction Contracts Act 2004 (WA)
Rules of the Supreme Court 1971 (WA)
Result:
Consent orders made
Category: B
Representation:
Counsel:
Applicant: No appearance
Respondent: No appearance
Other Party : No appearance
Solicitors:
Applicant: Tottle Partners
Respondent: No appearance
Other Party : King & Wood Mallesons
Cases referred to in judgment:
Australian Competition and Consumer Commission v Energy Australia Pty Ltd [2015] FCA 274
Deans v Anangu Pitjantjatjara Yankunytjatjara (No 2) [2015] SASC 57
Director of Public Prosecutions (Cth) v Ede [2014] NSWCA 282; (2014) 289 FLR 82
Kovalev v Minister for Immigration and Multicultural Affairs [1999] FCA 557; (1999) 100 FCR 323
Laing O’Rourke Australia Construction Pty Ltd v Samsung C & T Corporation [2015] WASC 237
Laing O'Rourke Australia Construction Pty Ltd v Samsung C & T Corporation [2016] WASCA 130
PRITCHARD J: In this application for judicial review, the Applicant seeks a writ of certiorari to quash a determination made by Mr Anstee‑Brook (the Respondent), an adjudicator under the Construction Contracts Act 2004 (WA) (the CC Act), on 20 October 2015 (the Determination). The Determination required that M+W Singapore Pte Ltd pay Brookfield Multiplex Constructions Pty Ltd $800,397.00 plus GST, interest and costs.[1]
[1] Affidavit of Mary Jane Walker sworn 16 November 2015, Annexure MJW1.
The application for judicial review was heard on 24 May 2016, but counsel agreed that further submissions might be required once the Court of Appeal delivered its decision in Laing O'Rourke Australia Construction Pty Ltd v Samsung C & T Corporation.[2] Following the delivery of that decision, the parties reached an agreement to resolve the application for judicial review by consent. They submitted a minute of proposed consent orders pursuant to O 43 r 16 of the Rules of the Supreme Court 1971 (WA) (the Minute). The orders sought by the parties in the Minute…
Keep reading for free
Create a free CaseChat account to read M+W Singapore Pte Ltd v Anstee-Brook and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2016] WASC 310
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the court was whether the adjudicator had jurisdiction to make the decision in question. The court had to consider whether the application for adjudication was made within the required 28-day period as stipulated in section 26 of the Construction Contracts Act 2004 (WA). The parties agreed that the application for adjudication was not made within the required timeframe, and therefore, the adjudicator did not have jurisdiction to make the decision. The court also had to determine the appropriate form of relief to grant in the circumstances. Specifically, the court had to decide whether it was necessary to order the adjudicator to deliver up the decision for the purpose of being quashed or whether it was sufficient to simply order that the decision be quashed.
The court found that the adjudicator did not have jurisdiction to make the decision in question because the application for adjudication was not made within the required 28-day period. The court was satisfied that the parties had agreed that the adjudicator's decision should be quashed, and that the order sought by the applicant was appropriate. The court also found that it was not necessary to order the adjudicator to deliver up the decision for the purpose of being quashed, as it was sufficient to simply order that the decision be quashed. The court made an order quashing the adjudicator's decision and ordered that the applicant pay the respondent's costs of the action. The court made no order as to the costs of the action between the applicant and the other party or between the respondent and the other party.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
The application for judicial review was heard on 24 May 2016, but counsel agreed that further submissions might be required once the Court of Appeal delivered its decision in Laing O'Rourke Australia Construction Pty Ltd v Samsung C & T Corporation.[2] Following the delivery of that decision, the parties reached an agreement to resolve the application for judicial review by consent. They submitted a minute of proposed consent orders pursuant to O 43 r 16 of the Rules of the Supreme Court 1971 (WA) (the Minute). The orders sought by the parties in the Minute are:1.A writ of certiorari is issued quashing the adjudication determination of the Respondent dated 20 October 2015 on the ground that the Respondent wrongly determined that the Other Party's application for adjudication dated 16 September 2015 was made in accordance with s 26(1) of the Construction Contracts Act 2004 (WA) and the Respondent thereby fell into jurisdictional error.2.Within 7 days of the date of this order, the Other Party pay the Applicant's costs of the action … .3.There be no order as to the costs of the action as between the Applicant and the Respondent or between the Other Party and the Respondent. For the reasons explained below at [15] ‑ [17], it is appropriate to indicate why I am persuaded that the Determination should be quashed, and the basis for granting that relief. The factual background[2] Laing O'Rourke Australia Construction Pty Ltd v Samsung C & T Corporation [2016] WASCA 130. The following facts were disclosed in the affidavits filed by the parties. In 2012, Brookfield entered into a 'Letter of Intent Agreement' with M+W for mechanical services at the Midland Health Campus in Perth. In January 2013, Brookfield and M+W entered into a subcontract by which M+W would design, supply, install, test and commission mechanical services (the subcontract). On 22 May 2015, 22 June 2015 and 22 July 2015, M+W submitted payment claims to Brookfield (numbered Payment Schedules 27, 28 and 29, respectively). The total amount said to be owing in respect of those payment claims was just under $4.3 million. In response, Brookfield issued Payment Schedules numbered 27, 28 and 29 to M+W on 4 June 2015, 3 July 2015 and 4 August 2015, respectively. In each of those Payment Schedules, Brookfield disputed parts of each payment claim made by M+W, and determined that in fact an amount was due and payable by M+W to Brookfield, in the form of liquidated damages, or other amounts arising from delay and disruption, or by way of back charges. On 7 June 2015, M+W sent Brookfield a letter (dated 5 June 2015) in which it disputed that it was liable to pay the amounts claimed in Payment Schedule 27. On 17 July 2015, M+W sent Brookfield a letter in which it disputed the amounts claimed in Payment Schedule 28. Prior to 19 August 2015, M+W wrote to Brookfield disputing many of the claims made by Brookfield. On 16 September 2015, Brookfield made an application for the adjudication of a payment dispute which it claimed had arisen by virtue of M+W's failure to pay the amount due under Payment Schedules 27, 28 and 29 (which it was accepted constituted payment claims under the CC Act) by the time it said those amounts became due and payable, namely 26 August 2015 (the Adjudication Application).