M+W Singapore Pte Ltd v Anstee-Brook

Link copied
Case Copied 25 min read

JURISDICTION     :   SUPREME COURT OF WESTERN AUSTRALIA

IN CHAMBERS

CITATION:   M+W SINGAPORE PTE LTD -v- ANSTEE-BROOK [2016] WASC 310

CORAM:   PRITCHARD J

HEARD:   ON THE PAPERS

DELIVERED          :   27 SEPTEMBER 2016

FILE NO/S:   CIV 2881 of 2015

BETWEEN:   M+W SINGAPORE PTE LTD

Applicant

AND

GRAHAM  ANSTEE-BROOK
Respondent

BROOKFIELD MULTIPLEX CONSTRUCTIONS PTY LTD
Other Party

Catchwords:

Practice and procedure - Consent orders - O 43 r 16 Rules of the Supreme Court 1971 (WA) - Consent orders in judicial review proceedings - Consent order for grant of prerogative relief - Requirement that Court be satisfied of grounds for and appropriateness of orders - Requirement that orders be within power - Where parties agree that decision-maker did not have jurisdiction to make the decision

Practice and procedure - Order for the issue of a writ of certiorari - Form of order - O 56 r 2(2) Rules of the Supreme Court 1971 (WA) - Court's power to make an order having the same effect as a prerogative writ - Whether necessary for order requiring decision-maker to deliver up decision to Court for purpose of being quashed - Whether sufficient to order that decision be quashed

Legislation:

Construction Contracts Act 2004 (WA)
Rules of the Supreme Court 1971 (WA)

Result:

Consent orders made

Category:    B

Representation:

Counsel:

Applicant:     No appearance

Respondent:     No appearance

Other Party  :     No appearance

Solicitors:

Applicant:     Tottle Partners

Respondent:     No appearance

Other Party  :     King & Wood Mallesons

Cases referred to in judgment:

Australian Competition and Consumer Commission v Energy Australia Pty Ltd [2015] FCA 274

Deans v Anangu Pitjantjatjara Yankunytjatjara (No 2) [2015] SASC 57

Director of Public Prosecutions (Cth) v Ede [2014] NSWCA 282; (2014) 289 FLR 82

Kovalev v Minister for Immigration and Multicultural Affairs [1999] FCA 557; (1999) 100 FCR 323

Laing O’Rourke Australia Construction Pty Ltd v Samsung C & T Corporation [2015] WASC 237

Laing O'Rourke Australia Construction Pty Ltd v Samsung C & T Corporation [2016] WASCA 130

  1. PRITCHARD J:  In this application for judicial review, the Applicant seeks a writ of certiorari to quash a determination made by Mr Anstee‑Brook (the Respondent), an adjudicator under the Construction Contracts Act 2004 (WA) (the CC Act), on 20 October 2015 (the Determination). The Determination required that M+W Singapore Pte Ltd pay Brookfield Multiplex Constructions Pty Ltd $800,397.00 plus GST, interest and costs.[1]

    [1] Affidavit of Mary Jane Walker sworn 16 November 2015, Annexure MJW1.

  2. The application for judicial review was heard on 24 May 2016, but counsel agreed that further submissions might be required once the Court of Appeal delivered its decision in Laing O'Rourke Australia Construction Pty Ltd v Samsung C & T Corporation.[2] Following the delivery of that decision, the parties reached an agreement to resolve the application for judicial review by consent. They submitted a minute of proposed consent orders pursuant to O 43 r 16 of the Rules of the Supreme Court 1971 (WA) (the Minute). The orders sought by the parties in the Minute…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read M+W Singapore Pte Ltd v Anstee-Brook and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2016] WASC 310
Decision Date

CaseChat Overview and Summary

The case of M+W Singapore Pte Ltd v Anstee-Brook involved a dispute between M+W Singapore Pte Ltd and Brookfield, with Anstee-Brook acting as the respondent. The dispute centred around a payment claim made under the Construction Contracts Act 2004 (WA) and the subsequent adjudication of this claim. The matter was brought before the court as an application for judicial review, seeking to quash the decision of the adjudicator, Mr Anstee-Brook. The court was required to determine whether the adjudicator had jurisdiction to make the decision in question and whether the decision was appropriate.

The primary legal issue before the court was whether the adjudicator had jurisdiction to make the decision in question. The court had to consider whether the application for adjudication was made within the required 28-day period as stipulated in section 26 of the Construction Contracts Act 2004 (WA). The parties agreed that the application for adjudication was not made within the required timeframe, and therefore, the adjudicator did not have jurisdiction to make the decision. The court also had to determine the appropriate form of relief to grant in the circumstances. Specifically, the court had to decide whether it was necessary to order the adjudicator to deliver up the decision for the purpose of being quashed or whether it was sufficient to simply order that the decision be quashed.

The court found that the adjudicator did not have jurisdiction to make the decision in question because the application for adjudication was not made within the required 28-day period. The court was satisfied that the parties had agreed that the adjudicator's decision should be quashed, and that the order sought by the applicant was appropriate. The court also found that it was not necessary to order the adjudicator to deliver up the decision for the purpose of being quashed, as it was sufficient to simply order that the decision be quashed. The court made an order quashing the adjudicator's decision and ordered that the applicant pay the respondent's costs of the action. The court made no order as to the costs of the action between the applicant and the other party or between the respondent and the other party.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

The factual background[2] Laing O'Rourke Australia Construction Pty Ltd v Samsung C & T Corporation [2016] WASCA 130. The following facts were disclosed in the affidavits filed by the parties. In 2012, Brookfield entered into a 'Letter of Intent Agreement' with M+W for mechanical services at the Midland Health Campus in Perth. In January 2013, Brookfield and M+W entered into a subcontract by which M+W would design, supply, install, test and commission mechanical services (the subcontract). On 22 May 2015, 22 June 2015 and 22 July 2015, M+W submitted payment claims to Brookfield (numbered Payment Schedules 27, 28 and 29, respectively). The total amount said to be owing in respect of those payment claims was just under $4.3 million. In response, Brookfield issued Payment Schedules numbered 27, 28 and 29 to M+W on 4 June 2015, 3 July 2015 and 4 August 2015, respectively. In each of those Payment Schedules, Brookfield disputed parts of each payment claim made by M+W, and determined that in fact an amount was due and payable by M+W to Brookfield, in the form of liquidated damages, or other amounts arising from delay and disruption, or by way of back charges. On 7 June 2015, M+W sent Brookfield a letter (dated 5 June 2015) in which it disputed that it was liable to pay the amounts claimed in Payment Schedule 27. On 17 July 2015, M+W sent Brookfield a letter in which it disputed the amounts claimed in Payment Schedule 28. Prior to 19 August 2015, M+W wrote to Brookfield disputing many of the claims made by Brookfield. On 16 September 2015, Brookfield made an application for the adjudication of a payment dispute which it claimed had arisen by virtue of M+W's failure to pay the amount due under Payment Schedules 27, 28 and 29 (which it was accepted constituted payment claims under the CC Act) by the time it said those amounts became due and payable, namely 26 August 2015 (the Adjudication Application). The Determination The parties raised numerous arguments in the course of the adjudication. For present purposes, it is necessary only to focus on one of those arguments, namely whether the Respondent was required to dismiss the Adjudication Application under s 31(2) of the CC Act, on the basis that there had not been compliance with the requirements of s 26 of the CC Act. The way in which the Respondent dealt with this argument in his Determination was as follows:[3] [3] Affidavit of Mary Jane Walker sworn 16 November 2015, Annexure MJW1, 13.12.3In response to each of the progress claims submitted by M+W, [Brookfield] determined that an amount was due and payable by M+W to [Brookfield].Section 26 of the CC Act12.4If an application for adjudication is not made within 28 days of a payment dispute the adjudication application must pursuant to s 31(2)(a)(ii) of the [CC Act] be summarily dismissed.12.5There is no issue between the parties that [Brookfield] can make a payment claim given the definition in s 3 of the [CC Act].…In respect of each of M+W's progress claims the payment schedules issued by [Brookfield] determined that there were amounts payable by M+W to [Brookfield] and that these payment schedules comprised payment claims pursuant to the [CC Act].12.6M+W contend that pursuant to clause 42.1 of the Subcontract as a payment schedule was issued M+W were required to make payment within 5 days of the issue of a certificate. The certificates were respectively issued on 4 June 2015 (Payment Schedule 27), 3 July 2015 (Payment Schedule 28) and 4 August 2015 (Payment Schedule 29) and as the Application was made on 16 September 2015, the Application was not made within the 28 days of any of the payment disputes arising.12.7On the contentions of M+W the last Payment Schedule having been issued on 4 August 2015, the Application should have been lodged no later than 8 September 2015.12.8Each of the three Payment Schedules issued by [Brookfield] require consideration to ascertain whether the Application has been made within 28 days after a payment dispute has arisen.Section 6 of the [CC Act] relevantly provides:...12.9[Brookfield] contend that clause 42.1 of the Subcontract provides that payment in relation to a payment schedule issued by [Brookfield] which reflects a payment by M+W to [Brookfield] ... must be made within 5 days of the issue of the certificate. That would mean that in respect of payment schedules 27, 28 and 29 payment was due respectively on 9 June 2015, 8 July 2015 and 9 August 2015. Extension of time for payment12.10It is apparent that unless there was some agreement or other mechanism pursuant to which the due dates for payment of Payment Schedules 27, 28 and 29 were extended then the Application was not brought within 28 days of a payment dispute arising.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

The application for judicial review was heard on 24 May 2016, but counsel agreed that further submissions might be required once the Court of Appeal delivered its decision in Laing O'Rourke Australia Construction Pty Ltd v Samsung C & T Corporation.[2] Following the delivery of that decision, the parties reached an agreement to resolve the application for judicial review by consent. They submitted a minute of proposed consent orders pursuant to O 43 r 16 of the Rules of the Supreme Court 1971 (WA) (the Minute). The orders sought by the parties in the Minute are:1.A writ of certiorari is issued quashing the adjudication determination of the Respondent dated 20 October 2015 on the ground that the Respondent wrongly determined that the Other Party's application for adjudication dated 16 September 2015 was made in accordance with s 26(1) of the Construction Contracts Act 2004 (WA) and the Respondent thereby fell into jurisdictional error.2.Within 7 days of the date of this order, the Other Party pay the Applicant's costs of the action … .3.There be no order as to the costs of the action as between the Applicant and the Respondent or between the Other Party and the Respondent. For the reasons explained below at [15] ‑ [17], it is appropriate to indicate why I am persuaded that the Determination should be quashed, and the basis for granting that relief. The factual background[2] Laing O'Rourke Australia Construction Pty Ltd v Samsung C & T Corporation [2016] WASCA 130. The following facts were disclosed in the affidavits filed by the parties. In 2012, Brookfield entered into a 'Letter of Intent Agreement' with M+W for mechanical services at the Midland Health Campus in Perth. In January 2013, Brookfield and M+W entered into a subcontract by which M+W would design, supply, install, test and commission mechanical services (the subcontract). On 22 May 2015, 22 June 2015 and 22 July 2015, M+W submitted payment claims to Brookfield (numbered Payment Schedules 27, 28 and 29, respectively). The total amount said to be owing in respect of those payment claims was just under $4.3 million. In response, Brookfield issued Payment Schedules numbered 27, 28 and 29 to M+W on 4 June 2015, 3 July 2015 and 4 August 2015, respectively. In each of those Payment Schedules, Brookfield disputed parts of each payment claim made by M+W, and determined that in fact an amount was due and payable by M+W to Brookfield, in the form of liquidated damages, or other amounts arising from delay and disruption, or by way of back charges. On 7 June 2015, M+W sent Brookfield a letter (dated 5 June 2015) in which it disputed that it was liable to pay the amounts claimed in Payment Schedule 27. On 17 July 2015, M+W sent Brookfield a letter in which it disputed the amounts claimed in Payment Schedule 28. Prior to 19 August 2015, M+W wrote to Brookfield disputing many of the claims made by Brookfield. On 16 September 2015, Brookfield made an application for the adjudication of a payment dispute which it claimed had arisen by virtue of M+W's failure to pay the amount due under Payment Schedules 27, 28 and 29 (which it was accepted constituted payment claims under the CC Act) by the time it said those amounts became due and payable, namely 26 August 2015 (the Adjudication Application).