DISTRICT COURT OF QUEENSLAND
CITATION:
Thallon Mole Group Pty Ltd v Morton [2022] QDC 224
PARTIES:
THALLON MOLE GROUP PTY LTD
ACN 104 671 801
(plaintiff)
v
LOUISE MORTON
(defendant)FILE NO/S:
2695/19
DIVISION:
Civil - Commercial List
PROCEEDING:
Trial
ORIGINATING COURT:
Brisbane District Court
DELIVERED ON:
7 October 2022
DELIVERED AT:
Brisbane
HEARING DATE:
25 - 28 May 2021; 1 - 4 June 2021; 6 - 10 September 2021; 13 - 16 September 2021; 10 & 11 February 2022;
Final submissions in reply 14 February 2022
JUDGE:
Muir DCJ
ORDER:
By 4.00pm Thursday 27 October 2022, the parties are to:
(a) Bring in Final Orders including relevant interest calculations and provision for the release of the Retention Monies consistent with my findings; and
(b) Exchange and deliver written submissions as to costs (if necessary), no longer than four pages.
CATCHWORDS:
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION – STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS – PROGRESS PAYMENTS – where defendant entered into a contract with the plaintiff – where contract was for construction of a luxury residential property – where during the course of construction the contract was terminated by the defendant for breaches – where plaintiff claimed they were willing and able to continue performing the contract – where the defendant did not pay outstanding progress claims for works completed – where the plaintiff seeks payment for the works completed.
PROCEDURE – CIVIL PROCEDURE IN STATE AND TERRITORY COURTS – COSTS – ISSUES AND COUNTERCLAIMS – where works performed under the contract were defective – where the defendant counterclaims for the cost of rectifying defective works – where there is dispute as to defects and the cost of rectification.
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – THE CONTRACT – CONSTRUCTION OF PARTICULAR CONTRACTS AND IMPLIED CONDITIONS – OTHER MATTERS – where specifications of the contract were not able to be met – where the contract price must be reduced to account for failure to meet conditions of the contract.
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – PERFORMANCE OF WORK – TIME – where performance of the contract was delayed – where the plaintiff claimed entitlement to an extension of time – where the defendant claimed no entitlement to extension of time exists – where the defendant argued that delays were caused by the plaintiff, were foreseeable and no notice of an extension was given.
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – PERFORMANCE OF WORK – GENERAL – where the plaintiff claimed that works had reached practical completion – where the defendant argued that practical completion was not reached due to defective works.
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – THE CONTRACT –CONSTRUCTION OF PARTICULAR CONTRACTS AND IMPLIED CONDITIONS – SECURITY AND RETENTION FUNDS – where retention money was to be given to plaintiff after practical completion – where practical completion did not occur – where the contract stipulated that defendant had recourse to unpaid retention money if notice…
Keep reading for free
Create a free CaseChat account to read Thallon Mole Group Pty Ltd v Morton and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2022] QDC 224
- Decision Date
CaseChat Overview and Summary
The court examined the terms of the contract, the nature of the defects, and the cost of rectifying them. The court found that the plaintiff had not met certain specifications and that the contract price should be reduced accordingly. The court also considered whether the plaintiff was entitled to an extension of time for delays in performance and whether practical completion had been achieved. The court further assessed the plaintiff's claim for quantum meruit regarding works subject to variation and whether an agency by estoppel could override statutory requirements for written variations.
The court concluded that the plaintiff was not entitled to progress payments for works completed after the contract's termination. Regarding the counterclaim for defective works, the court held that the plaintiff was liable for the cost of rectification. The court found that estoppel could not override the statutory requirement for written variations. The court ordered that the retention monies be released to the plaintiff, subject to certain deductions for the cost of rectifying defective works. The court also directed the parties to exchange written submissions on costs.
Orders
Orders of the court
By 4.00pm Thursday 27 October 2022, the parties are to:
(a) Bring in Final Orders including relevant interest calculations and provision for the release of the Retention Monies consistent with my findings; and
(b) Exchange and deliver written submissions as to costs (if necessary), no longer than four pages.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.