HIGH COURT OF AUSTRALIA
Stephen, Mason, Aickin, Wilson and BrennanJJ.
CODELFA CONSTRUCTION PTY. LTD. v. STATE RAIL AUTHORITY OF N.S.W.
11 May 1982
Contract—Arbitration
Contract—Construction—Implied terms—Frustration—Contract to carry out excavations for rail authority—Completion required by certain date—Contractor working three shifts seven days per week—Injunction granted to third party restraining contractor from working at certain times—Whether implied term of contract that authority would grant reasonable extension of time and indemnify contractor against additional costs occasioned by grant of injunction—Whether injunction frustrated contract—Extrinsic evidence of intention. Arbitration—Jurisdiction to entertain claim that contract frustrated—Power to award interest on award—Compound interest—Supreme Court Act 1970 (N.S.W.), s. 94(1).
Decisions
1982, May 11.
The following written judgments were delivered:-
STEPHEN J. I have had the considerable advantage of reading the judgments of a number of the members of the Court. In consequence I am able to confine myself to the expression of my agreement with what has been written by others. (at p344)
2. Five distinct matters were canvassed in this appeal. As to the first, concerned with the implication of a term in the contract between the parties, I agree with all that my brother Mason has said. (at p344)
3. The second matter concerns the doctrine of frustration. As to it, I agree with what has been said concerning it by each of my brothers Mason and Aickin. On the question of the rise and fall clause I agree with Aickin J. and, on the matters of the power to award interest and the power to award compound interest, I agree with Mason J. (at p345)
MASON J. I have had the advantage of reading the reasons for judgment prepared by Brennan J. in which the relevant facts and questions are comprehensively set out.
(1) Implied Term. (at p345)
2. In this ocean of litigious controversy there is one large island of agreement between the parties. It is common ground that their contract consists of the agreement dated 21 March 1972 and the various documents which it incorporates. The appellant does not suggest that dehors the agreement and the incorporated documents there is to be found a term actually agreed upon by the parties which together with the contract documents stands as the true contract or which stands in its own right as a collateral contract. Nor does the appellant suggest that there is a case for rectification arising from the existence of such a term on the footing that it was inadvertently omitted from the contract documents. The appellant's case is that a term has to be implied in the contract to give it business efficacy, to make it workable. Consequently, there is no contest as to what constitutes the contract; rather the contest is as to its meaning and effect. (at p345)
3. When we say that the implication of a term raises an issue as to the meaning and effect of the contract we do not intend by that statement to convey that the court is…
Keep reading for free
Create a free CaseChat account to read Codelfa Construction Pty Ltd v State Rail Authority of New S... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [1982] HCA 24
- Decision Date
CaseChat Overview and Summary
The High Court was required to determine whether the contract had been frustrated by the granting of the injunction. It also had to consider whether there was an implied term in the contract that the Authority would grant a reasonable extension of time and indemnify the contractor for additional costs arising from the injunction. Furthermore, the Court had to assess the jurisdiction of an arbitrator to entertain a claim that the contract was frustrated and the power to award compound interest on an arbitral award.
The Court held that the injunction did not frustrate the contract. It reasoned that frustration occurs when an unforeseen event makes performance impossible or radically different from what was contemplated by the parties. In this instance, the injunction was a consequence of the contractor's own actions in commencing work, and the contract itself contained provisions for extensions of time in certain circumstances. The Court found no basis for implying a term that the Authority would grant an extension of time and indemnity for costs occasioned by the injunction, as such a term was not necessary to give business efficacy to the contract and was not within the reasonable contemplation of the parties. The Court also affirmed the arbitrator's jurisdiction to determine the issue of frustration and the power to award interest.
The High Court dismissed the contractor's appeal, upholding the decision of the lower courts.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi