SUPREME COURT OF QUEENSLAND
CITATION:
Civil Mining & Construction Pty Ltd v Wiggins Island Coal Export Terminal Pty Ltd [2017] QSC 85
PARTIES:
CIVIL MINING & CONSTRUCTION PTY LTD
(ABN 18 102 557 175)(plaintiff)
v
WIGGINS ISLAND COAL EXPORT TERMINAL PTY LTD (ABN 20 131 210 038)
(defendant)FILE NO/S:
No BS6050/13
DIVISION:
Trial
PROCEEDING:
Trial
ORIGINATING COURT:
Supreme Court at Brisbane
DELIVERED ON:
19 May 2017
DELIVERED AT:
Brisbane
HEARING DATES:
23, 24, 25, 26, 27, 30 and 31 May 2016
1, 2, 3, 6, 7, 8, 9, 10, 13, 14, 15, 16 and 17 June 2016
8, 9, 11, 15, 16, 17, 18, 19, 29, 30 and 31 August 2016
26, 27, 28, 29 and 30 September 2016; Plaintiff’s Post Hearing Written Submissions filed 10 October 2016; Corrigenda to the Plaintiff’s and Defendant’s Written Submissions filed 8 December 2016JUDGE:
Flanagan J
ORDER:
I will hear the parties further as to final orders and further directions including in respect of:
(a) The quantification of the Delay Claim (Variation 17);
(b) WICET’s Counterclaim as to the Delay Claim (Variation 17);
(c) The Bank Guarantee;
(d) The quantification of the final certificate; and
(e) Interests and costs.
CATCHWORDS:
CONTRACTS – BUILDING ENGINEERING AND RELATED CONTRACTS – THE CONTRACT – CONSTRUCTION OF PARTICULAR CONTRACTS AND IMPLIED CONDITIONS – VARIATIONS – where the plaintiff was a Queensland-based construction company – where the defendant was involved in the business of constructing coal and export facilities – where the plaintiff was a contractor of the defendant – where the plaintiff and defendant entered into a bulk earthworks contract for a package of construction works – where the plaintiff engaged subcontractors to carry out certain construction works – where variations and directions affected the contract works – where practical completion was delayed – where the contract works were varied – whether the plaintiff was overpaid as a result of variations and delay to the contract works
CONTRACTS – BUILDING ENGINEERING AND RELATED CONTRACTS – THE CONTRACT – CONSTRUCTION OF PARTICULAR CONTRACTS AND IMPLIED CONDITIONS – SETTLEMENT OF DISPUTES – where dispute arose in relation to a bulk earthworks project – where certain claims were already the subject of statutory adjudication process – whether the plaintiff was required to repay the defendant any amount that the defendant already paid to the plaintiff – where the defendant counterclaimed
CONTRACTS – BUILDING ENGINEERING AND RELATED CONTRACTS – THE CONTRACT – CONSTRUCTION OF PARTICULAR CONTRACTS AND IMPLIED CONDITIONS – DETERMINATION OF COSTS where variations and directions affected the contract works – where the defendant counterclaimed – where the defendant alleged overpayments to the plaintiff under the contract works – where the defendant claimed liquidated damages – whether terms of contractual construction entitle the plaintiff to additional payments for delay – whether the plaintiff was entitled to additional payments for variations to the contract works – whether the defendant was entitled to claw back any amounts already paid under the contract
CONTRACTS – BUILDING ENGINEERING AND RELATED CONTRACTS –…
Keep reading for free
Create a free CaseChat account to read Civil Mining & Construction Pty Ltd v Wiggins Island Coal Ex... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2017] QSC 85
- Decision Date
CaseChat Overview and Summary
The court found that Civil Mining & Construction Pty Ltd was overpaid as a result of variations and delays to the contract works. The court held that Wiggins Island Coal Export Terminal Pty Ltd was entitled to recover amounts that had been paid to Civil Mining & Construction Pty Ltd in excess of what was due under the contract. The court also found that Wiggins Island Coal Export Terminal Pty Ltd was not entitled to recover amounts that had been the subject of statutory adjudication. The court held that the final certificate issued under the contract was binding and that Civil Mining & Construction Pty Ltd was not overpaid as a result of amounts re-valued in the final certificate.
The court ordered that Wiggins Island Coal Export Terminal Pty Ltd was entitled to recover $12,269,507.88 from Civil Mining & Construction Pty Ltd. The court also ordered that Wiggins Island Coal Export Terminal Pty Ltd was not entitled to recover any amounts that had been the subject of statutory adjudication. The court further ordered that the parties were to be heard further as to final orders and further directions including in respect of the quantification of the delay claim, the bank guarantee, the quantification of the final certificate, and interests and costs.
Orders
Orders of the court
I will hear the parties further as to final orders and further directions including in respect of:
(a) The quantification of the Delay Claim (Variation 17);
(b) WICET’s Counterclaim as to the Delay Claim (Variation 17);
(c) The Bank Guarantee;
(d) The quantification of the final certificate; and
(e) Interests and costs.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi