SUPREME COURT OF QUEENSLAND

CITATION:

Alexanderson Earthmover Pty Ltd v Civil Mining & Construction Pty Limited [2020] QSC 122

PARTIES:

ALEXANDERSON EARTHMOVER PTY LTD ABN 98 100 496 937

(Plaintiff)

v
CIVIL MINING & CONSTRUCTION PTY LIMITED ABN 18 102 557 175

(Defendant)

FILE NO/S:

BS 13314 of 2017

DIVISION:

Trial Division

PROCEEDING:

Application

ORIGINATING COURT:

Supreme Court at Brisbane

DELIVERED ON:

15 May 2020

DELIVERED AT:

Brisbane

HEARING DATE:

20 April 2020

JUDGE:

Brown J

ORDER:

1.   The words “to the extent of any inconsistency only” and “and which was thereafter varied from time to time by the matters particularised in paragraph 8 of the Statement of Claim” in paragraph 4B(b)(i) of the Further Amended Reply are struck out;

2.   Paragraph 47A the Fourth Further Amended Statement of Claim (4FASOC) should be struck out with liberty to re-plead;

3.   The plaintiff is to provide particulars in respect of the facts matters and circumstances relied upon in respect of the “reasonable rate” referred to in schedule F1 and F2 and the particulars of the work actually performed in respect of [126] and [133] of the 4FASOC; and

4.   The matter is to be listed for review and consideration of further orders including as to costs in the week of 25 May 2020 or 1 June 2020 at 9.00am. The parties are to liaise with the Brown J’s associate in this regard.

CATCHWORDS:

PROCEDURE – CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS – PLEADINGS – STRIKING OUT – GENERALLY – where the defendant contends that part of the plaintiff’s pleading is inconsistent and ambiguous – where a previous strike out application had been brought – where orders were made to strike out parts of the pleadings – where the plaintiff re-pleaded aspects of the struck out pleadings in similar terms – whether the plaintiff can reasonably plead global causation – whether a global claim can be pleaded in the alternative where the plaintiff had not pleaded material facts or provided particulars as to the basis for “reasonable cost” or “fair market rate” – where the basis for the “reasonable cost” and “fair market rate” were within the knowledge of the plaintiff – whether the particulars are inadequate – whether the particulars are ambiguous, irrelevant or confusing – whether the particulars support the allegations made

Uniform Civil Procedure Rules 1999 (Qld), r 149, r 155, r 161, r 162
Alexanderson Earthmover Pty Ltd v Civil Mining & Construction Pty Limited [2019] QSC 259, cited

Danidale Pty Ltd v Abigroup Contractors Pty Ltd [2007] VSC 391, considered
Civil Mining & Construction Pty Ltd v Wiggins Island Coal
Export Terminal Pty Ltd [2017] QSC 85, considered
Lacaba Ahden Australia Pty ltd v Buycrys (Australia) Pty Ltd [2006] QSC 147, distinguished
LBS Holdings P/L v The Body Corporate for Condor Community Title Scheme 13200 [2004] QSC 229, followed
Masters v Cameron (1954) 91 CLR 353, considered
McGrath Corporation Pty Ltd v Global Construction Management (Qld) Pty Ltd [2011] QSC…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Alexanderson Earthmover Pty Ltd v Civil Mining and Construct... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2020] QSC 122
Decision Date

CaseChat Overview and Summary

Alexanderson Earthmover Pty Ltd, the plaintiff, filed a suit against Civil Mining and Construction Pty Limited, the defendant, in a legal dispute concerning a contract for earthmoving services. The case was heard in the Supreme Court of Queensland. The plaintiff sought damages for breach of contract and unjust enrichment, while the defendant argued that the plaintiff's claims were not adequately substantiated and sought to have parts of the pleadings struck out.

The court needed to decide whether the plaintiff could reasonably plead global causation in the alternative and if it was permissible to plead a global claim when the plaintiff had not provided material facts or particulars to support the basis for "reasonable cost" or "fair market rate." Additionally, the court had to assess whether the particulars provided were inadequate, ambiguous, irrelevant, or confusing, and whether they adequately supported the allegations made by the plaintiff.

The court ruled that the plaintiff's case was based on a reasonable rate and expectation damages for the contract claim, and therefore, it was not satisfied that certain parts of the pleadings should be struck out. However, the court did order that the plaintiff provide particulars of the facts, matters, and circumstances relied upon to assert the reasonable rate in schedules F1 and F2, which applied to the additional work executed. The court considered that the clarification provided by the plaintiff and the fact that evidence would be provided through affidavits and expert reports would be sufficient for the defendant to understand the case they needed to address. The court struck out certain words and a paragraph of the pleadings, granted the plaintiff leave to re-plead, and required the plaintiff to provide further particulars. The matter was listed for review and consideration of further orders, including costs, in the week of 25 May 2020 or 1 June 2020.

Orders

Orders of the court

1. The words “to the extent of any inconsistency only” and “and which was thereafter varied from time to time by the matters particularised in paragraph 8 of the Statement of Claim” in paragraph 4B(b)(i) of the Further Amended Reply are struck out;

2. Paragraph 47A the Fourth Further Amended Statement of Claim (4FASOC) should be struck out with liberty to re-plead;

3. The plaintiff is to provide particulars in respect of the facts matters and circumstances relied upon in respect of the “reasonable rate” referred to in schedule F1 and F2 and the particulars of the work actually performed in respect of [126] and [133] of the 4FASOC; and

4. The matter is to be listed for review and consideration of further orders including as to costs in the week of 25 May 2020 or 1 June 2020 at 9.00am. The parties are to liaise with the Brown J’s associate in this regard.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

I am not satisfied that [126] and [133] should be struck out given that it is evident that the plaintiffs case is based on a reasonable rate and for the contract claim, expectation damages. However, I will order that the particulars be provided of the facts, matters and circumstances relied upon by the Plaintiff to assert the reasonable rate in F1 and F2 which applied to the additional work executed. Given the clarification by the Plaintiff of its case, and the fact that the evidence in this matter is to be provided by way of affidavit and expert reports, that should be sufficient for the Defendant to know the case it has to meet, even if the terminology used between [126] and [133] are different. Conclusion and Orders In the circumstances, the orders of the court will be: (a)The words “to the extent of any inconsistency only” and “and which was thereafter varied from time to time by the matters particularised in paragraph 8 of the Statement of Claim” in paragraph 4B(b)(i) of the Further Amended Reply are struck out; (b)Paragraph 47A the Fourth Further Amended Statement of Claim (4FASOC) should be struck out with liberty to re-plead; (c)The plaintiff is to provide particulars in respect of the facts matters and circumstances relied upon in respect of the “reasonable rate” referred to in schedule F1 and F2 and the particulars of the work actually performed in respect of [126] and [133] of the 4FASOC; and(d)The matter is to be listed for review and consideration of further orders including as to costs in the week of 25 May 2020 or 1 June 2020 at 9.00am. The parties are to liaise with the Brown J’s associate in this regard.

Ratio Decidendi

Legal Principle Established