Alexanderson Earthmover Pty Ltd v Civil Mining and Construction Pty Limited

Link copied
Case Copied 75 min read

SUPREME COURT OF QUEENSLAND

CITATION:

Alexanderson Earthmover Pty Ltd v Civil Mining & Construction Pty Limited [2021] QSC 86

PARTIES:

ALEXANDERSON EARTHMOVER PTY LTD ABN 98 100 496 937

(Plaintiff)

v
CIVIL MINING & CONSTRUCTION PTY LIMITED ABN 18 102 557 175

(Defendant)

FILE NO/S:

BS 13314 of 2017

DIVISION:

Trial Division

PROCEEDING:

Application

ORIGINATING COURT:

Supreme Court at Brisbane

DELIVERED ON:

29 April 2021

DELIVERED AT:

Brisbane

HEARING DATE:

27 November 2020

JUDGE:

Brown J

ORDER:

1.   Leave for the draft Fifth Further Amended Statement of Claim is refused. 

2.   The Plaintiff is given leave to replead the Fifth Further Amended Statement of Claim and to file a further amended statement of claim in its present form subject to the matters identified being rectified.

3.   The Plaintiff is to file a further amended statement of claim by 18 June 2021.

4.   The Plaintiff is to pay the Defendant’s costs of the application.

CATCHWORDS:

PROCEDURE – CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS – PLEADINGS – STRIKING OUT – GENERALLY –– where a previous strike out application had been brought – where orders were made to strike out parts of the pleadings – where the plaintiff re-pleaded aspects of the struck out pleadings – whether leave for the plaintiff to file and serve a Fifth Amended Statement of Claim should be refused – whether the plaintiff’s pleading remains deficient – whether particulars pleaded are relevant pre-contractual negotiations and factual matters relevant to identifying the surrounding circumstances of the transaction or extrinsic facts relevant to resolving ambiguity

Alexanderson Earthmover Pty Ltd v Civil Mining & Construction Pty Limited [2020] QSC 122, cited
Alexanderson Earthmover Pty Ltd v Civil Mining & Construction Pty Limited [2019] QSC 259, cited
Australasian Medical Insurance Ltd & Anor v CGU Insurance Ltd (2010) 271 ALR 142, cited
Barr Rock Pty Ltd v Blast Ice Cream Pty Ltd [2011] QCA 252, cited

Birbilis Bros Pty Ltd v Chubb Fire and Security Pty Ltd & Ors [2018] QSC 3, cited
Barclay Mowlem Construction Ltd v Dampier Port Authority (2006) 33 WAR 82, cited
BP Australia Pty Ltd v Nyran Pty Ltd (2003) 198 ALR 44, cited
BP Australia Pty Ltd v Nyran Pty Ltd [2004] FCAFC 163, cited
Built Environs WA Pty Ltd v Perth Airport (No 4) [2020] WASC 382, cited
CodelfaConstructions Pty Ltd v State Rail Authority of NSW (1982) 149 CLR 337, cited
DM Drainage & Constructions Pty Ltd (as trustee for DM Unit Trust t/as DM Civil) v Karara Mining Pty Ltd [2014] WASC 170, cited
Electricity Generation Corporation v Woodside Energy Ltd (2014) 251 CLR 640, cited
Hydrofibre Pty Ltd v Australian Prime Fibre Pty Ltd & Anor [2013] QSC 163, cited
John Doyle Construction Ltd v Laing Management (Scotland) Ltd [2004] BLR 295, cited
John Holland Construction & Engineering Pty Ltd v Kvaerner RJ Brown Pty Ltd (1996) 8 VR 681, cited
LBS Holdings P/L v The…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Alexanderson Earthmover Pty Ltd v Civil Mining and Construct... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2021] QSC 86
Decision Date

CaseChat Overview and Summary

Alexanderson Earthmover Pty Ltd sought leave to file a Fifth Further Amended Statement of Claim against Civil Mining and Construction Pty Limited. The matter was before the court on an application to strike out parts of the pleadings, where orders were previously made to strike out certain aspects. The plaintiff re-pleaded some of the struck out parts and sought leave to file a Fifth Further Amended Statement of Claim. The central legal issues were whether leave should be granted for the plaintiff to file and serve the Fifth Further Amended Statement of Claim, and if the pleading was still deficient.

The court examined the pleadings and determined that the plaintiff's pleading remained deficient in several respects. The court noted that the plaintiff needed to amend the pleadings to remove irrelevant prior negotiations and to clarify the objective facts derived from the prior negotiations. Additionally, the plaintiff had to remove particulars of all draft contracts except for the one provided on 14 November 2011. The court also required the plaintiff to clarify the relationship between certain dates in the pleadings. Furthermore, the plaintiff's claim for damages did not sufficiently plead causation and needed either to be amended or for the plaintiff to demonstrate that it could not disentangle the labour costs or supervision costs in a similar manner to the access claims. The court did not accept the defendant's contention that the access delays and standby claims were still pleaded as global claims or were objectively ambiguous. However, the court directed the parties to confer to further refine the productivity and standby schedule in question.

The court refused leave for the reformulated Claim for Damages and ordered the plaintiff to replead the Fifth Further Amended Statement of Claim, subject to rectifying the identified matters. The court gave the plaintiff leave to file a further amended statement of claim by 18 June 2021. The plaintiff was also ordered to pay the defendant's costs of the application.

Orders

Orders of the court

1. Leave for the draft Fifth Further Amended Statement of Claim is refused.

2. The Plaintiff is given leave to replead the Fifth Further Amended Statement of Claim and to file a further amended statement of claim in its present form subject to the matters identified being rectified.

3. The Plaintiff is to file a further amended statement of claim by 18 June 2021.

4. The Plaintiff is to pay the Defendant’s costs of the application.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

I would therefore not provide leave for the reformulated Claim for Damages in paragraphs 44A –44C as it has not overcome the deficiencies in the pleading previously identified.Conclusion Based on the above analysis, I do not consider that leave should be given for the draft 5FASOC, given: (a)The pleading needs to be amended in relation to the prior negotiations to remove the prior negotiations which are no longer relied upon by the Plaintiff, those which I have determined are irrelevant and to make clear the objective facts which are said to have been mutually known by the parties derived from the prior negotiations; (b)To remove the particulars of all of the draft contracts other than the reference to the draft provided on 14 November 2011; (c)To amend the claim to make clear the relationship between the date in 26(a) and 32D; (d)The damages claim referred to in 44A – 44C does not sufficiently plead causation and must either be amended or, if the Plaintiff is to pursue it on the basis that it cannot disentangle the labour costs or supervision costs in a similar manner to what it has done in relation to the access claims and standby to plead the necessary preconditions for a global claim. In reaching this determination, however, I have not accepted the contention of the Defendant that the access delays and standby claims are still pleaded as global claims or are objectively ambiguous. While now identifying the relevant causative effect of the lack of sufficient access through the differential between the planned productivity for the particular work front and the actual productivity which resulted in the category of equipment to be used for that work front not being able to be utilised as planned, they have successfully pleaded the relevant causal link between the alleged breach and the loss of productivity and standby hours claimed. Similarly, I have not accepted that the claim for delayed completion remains a global claim given it has now also been calculated by reference to the work done in relation to the particular work front utilising the particular categories of plant sufficiently that each group is separate and distinct from the other as are the access delays, or at least that is arguably so on the face of the pleadings. As to the productivity and standby schedule, I will hear from the parties as to whether I should direct that they confer in order to be able to further refine the schedule in question. Orders 1.Leave for the draft 5FASOC is refused. 2.The Plaintiff is given leave to replead the draft 5FASOC and to file a further amended statement of claim in its present form subject to the above matters identified being rectified. 3.The Plaintiff is to file a further amended statement of claim by 18 June 2021.4.The Plaintiff is to pay the Defendant’s costs of the application. The Plaintiff has not been successful in obtaining leave and in any event, was obliged to bring the present application.

Ratio Decidendi

Legal Principle Established