SUPREME COURT OF QUEENSLAND
CITATION:
Santos Ltd v Fluor Australia Pty Ltd [2017] QSC 153
PARTIES:
SANTOS LIMITED ABN 80 007 550 923
(plaintiff)
v
FLUOR AUSTRALIA PTY LTD ABN 28 004 511 942(defendant)
FILE NO/S:
No 12939 of 2016
DIVISION:
Trial
PROCEEDING:
Application
ORIGINATING COURT:
Supreme Court at Brisbane
DELIVERED ON:
26 July 2017
DELIVERED AT:
Brisbane
HEARING DATE:
18 May 2017
JUDGE:
Flanagan J
ORDER:
1. I adjourn Fluor’s application to strike out paragraphs 92, 93, 94, 106 (to the extent it incorporates 105(a) and 105(c)), 185, 186, 187, 190 and 191 of the statement of claim.
2. The balance of Fluor’s application filed 6 April 2017 is dismissed.
3. I will hear the parties as to costs.
CATCHWORDS:
PROCEDURE – CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS – PLEADINGS – STRIKING OUT – DISCLOSING NO REASONABLE CAUSE OF ACTION OR DEFENCE – where the defendant applies to strike out paragraphs of the plaintiff’s claim – where the relevant parts of the statement of claim concern breaches of subcontracts the defendant entered into to carry out the work under the contract - whether paragraphs of the statement of claim fail to disclose a reasonable cause of action - whether the statement of claim identifies “global” or “total costs” claims – whether there is a “global” or “total costs claim” – whether a “global” or “total costs” claim is permissible in the circumstances – whether it is sufficient for a plaintiff to plead the material facts which are said to give rise to a causal connection
PROCEDURE – CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS – PLEADINGS – STRIKING OUT – EMBARRASSING, TENDENCY TO CAUSE PREJUDICE, SCANDALOUS, UNNECESSARY ETC OR CAUSING DELAY IN PROCEEDINGS – where the defendant applies to strike out paragraphs of the plaintiff’s claim - whether paragraphs of the statement of claim do not sufficiently inform the defendant of the case to be met – whether the statement of claim would impose an unreasonable or unfair burden on the defendant that would prejudice, embarrass or delay a fair trial – whether the plaintiff sufficiently pleaded a causal connection - whether the plaintiff sufficiently pleads the causal connection between the breaches and amount claimed
Uniform Civil Procedure Rules 1999, r 171
Bond Corporation Pty Ltd v Thiess Contractors Pty Ltd (1987) 14 FCR 215, cited
DM Drainage & Constructions Pty Ltd v Karara Mining Ltd [2014] WASC 170, applied
John Doyle Constructions Ltd v Laing Management (Scotland) Ltd [2004] BLR 295, cited
John Holland Construction & Engineering Pty Ltd v Kvaerner RJ Brown Pty Ltd & Anor (1996) 8 VR 681, cited
Kousa International LLC v CPB Contractors Pty Ltd [2017] WASC 11, applied
LBS Holdings Pty Ltd v The Body Corporate for Condor Community Title Scheme 13200 & Ors [2004] QSC 229, cited
Mainteck Services Pty Ltd v Stein Heurtey SA & Anor [2014] NSWCA 184, cited
McGrath Corporation Pty Ltd v Global Construction Management (Qld) Pty Ltd [2011]…
Keep reading for free
Create a free CaseChat account to read Santos Ltd v Fluor Australia Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2017] QSC 153
- Decision Date
CaseChat Overview and Summary
The court was required to decide whether certain paragraphs of the statement of claim fail to disclose a reasonable cause of action or defence, whether the statement of claim identifies “global” or “total costs” claims, and whether it is permissible for a plaintiff to plead the material facts which are said to give rise to a causal connection. The court was also required to decide whether the statement of claim would impose an unreasonable or unfair burden on the defendant that would prejudice, embarrass, or delay a fair trial. The court found that the statement of claim sufficiently pleaded the material facts which are said to give rise to a causal connection. The court also found that the statement of claim did not identify a “global” or “total costs” claim. The court held that it is sufficient for a plaintiff to plead the material facts which are said to give rise to a causal connection. The court found that the statement of claim did not impose an unreasonable or unfair burden on the defendant that would prejudice, embarrass, or delay a fair trial.
The court adjourned Fluor’s application to strike out certain paragraphs of the statement of claim and dismissed the balance of Fluor’s application. The court will hear the parties as to costs.
Orders
Orders of the court
1. I adjourn Fluor’s application to strike out paragraphs 92, 93, 94, 106 (to the extent it incorporates 105(a) and 105(c)), 185, 186, 187, 190 and 191 of the statement of claim.
2. The balance of Fluor’s application filed 6 April 2017 is dismissed.
3. I will hear the parties as to costs.
Background
Background to the litigation
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
It follows that paragraph 173 of the statement of claim should not be struck out.Category 4: CDJV acceleration claim Fluor seeks to strike out paragraphs 31, 37, 102 and 106 of the statement of claim. Paragraphs 31 and 37 fall under the heading “Breaches of the CDJV Subcontract” and the subheading “Delays to initial baseline schedule between September 2011 and March 2012”. Paragraphs 31 and 37 need to be understood in the context of their surrounding paragraphs. Paragraph 29 pleads that on 10 November 2011 CDJV submitted to Fluor its initial baseline schedule. This is referred to in the pleading as the November 2011 Baseline Schedule. This schedule included dates by which Fluor was to provide CDJV with certain AFC Drawings and access to parts of the site on which the CDJV Work was to be constructed, as well as the dates by which certain aspects of the CDJV Work were to be commenced and completed. Paragraph 30 pleads that between 14 September 2011 and 1 March 2012 Fluor failed in a number of respects. These include a failure to provide CDJV with AFC Drawings in a manner sufficient to enable CDJV to undertake the relevant Work without delay and, further or alternatively, complete the CDJV Work by the CDJV Milestone Dates. Paragraph 30 makes similar allegations in relation to Free Issue Materials and access. Particulars of these failures are identified in Schedule 5 and in particular 5.1, 5.2 and 5.3. By reference to Schedule 5 Fluor asserts that in respect of the alleged breaches in paragraph 30 Santos purports to provide particulars of 66 individual alleged failures.[58][58] Fluor’s Outline of Submissions in Reply, [58]. Paragraph 31 pleads that as a result of the matters pleaded in paragraph 30:(a) the progress of the CDJV Work was delayed; and(b)further or alternatively, CDJV could not complete the CDJV Work by the CDJV Milestone Dates; and(c) accordingly, Fluor breached certain pleaded terms of the CDJV Subcontract. Paragraph 32 pleads that on 6 February 2012 Fluor requested that CDJV accelerate the activities comprised in the CDJV Work to overcome the effect of the delay in the execution of the CDJV Work described in paragraph 31(a) and to enable CDJV to complete the CDJV Work by the CDJV Milestone Dates. Paragraph 33 pleads that CDJV provided Fluor with its proposal for the acceleration of the activities comprised in the CDJV Work. Paragraph 35 pleads that Fluor approved a document titled “Revision 10E”. It is in this context that paragraph 37 pleads that but for the occurrence of the events that are pleaded in paragraph 30, it would not have been necessary for the activities comprised in the CDJV Work to be accelerated and performed in the matter set out in Schedule 10E. Paragraph 38 pleads that on 5 November 2012 CDJV notified Fluor that CDJV was entitled to be compensated for the extra costs that it had incurred or would incur as a result of the acceleration of activities comprised in the CDJV Work that was required pursuant to Schedule 10E. CDJV’s estimate of the total amount of compensation that it was entitled to claim as a result of this acceleration was $101,250,000.