McGrath Corporation Pty Ltd v Global Construction Management (Qld) Pty Ltd

Link copied
Case Copied 77 min read

SUPREME COURT OF QUEENSLAND

CITATION:

McGrath Corporation Pty Ltd v Global Construction Management (Qld) Pty Ltd & Anor [2011] QSC 178

PARTIES:

McGRATH CORPORATION PTY LTD
ACN 010 829 491
(plaintiff)
v
GLOBAL CONSTRUCTION MANAGEMENT (QLD) PTY LTD
ACN 085 856 882
(first defendant)
and
IAN VINCENT TAYLOR
(second defendant)

FILE NO:

1199 of 2007

DIVISION:

Trial Division

PROCEEDING:

Trial

ORIGINATING COURT:

Supreme Court of Queensland

DELIVERED ON:

20 June 2011

DELIVERED AT:

Brisbane

HEARING DATE:

8, 9, 10, 11, 12 November 2010;  Written submissions and chronology

JUDGE:

Daubney J

ORDERS:

1.     That there be judgment for the plaintiff against the first defendant in the sum of $557,166;

2.      Further, that the first   defendant pay to the plaintiff the sum of $138,504.11;

3.      That the counterclaim is dismissed;

4.      I will hear the parties as to interest and costs.

CATCHWORDS:

CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – PERFORMANCE OF WORK – REMEDIES FOR BREACH OF CONTRACT – DAMAGES – where the plaintiff is seeking damages for breach of contract and negligence – where the first defendant was the construction manager for the relevant project – where the first defendant has counterclaimed contending its termination by the plaintiff was repudiation – where the plaintiff alleges the first defendant overcharged in breach of the contract.

TORTS – NEGLIGENCE – APPORTIONMENT OF RESPONSIBILITY AND DAMAGES – APPORTIONMENT IN PARTICULAR SITUATIONS AND CASES - where the plaintiff is seeking damages for breach of contract and negligence – where the first defendant was the construction manager for the relevant project – whether the claim is caught by the Civil Liability Act 2003 (Qld) – whether the claim is an apportionable claim and how are the damages to be apportioned.

Civil Liability Act 2003 (Qld), ss 28, 30, 31, 32, 32A, Schedule 2

Bellgrove v Eldridge(1953-1954) 90 CLR 613, cited
John Holland Construction & Engineering Pty Ltd v Kvaerner RJ Brown Pty Ltd (1996) 13 BCL 292, cited
Laing Management (Scotland) Ltd v John Doyle Construction Ltd [2004] BLR 295, cited
Yates v Mobile Marine Repairs Pty Ltd [2007] NSWSC 1463, considered

COUNSEL:

C Wilson for the plaintiff
RA Perry SC with G I Thomson for the first defendant

SOLICITORS:

Herbert Geer for the plaintiff
HWL Ebsworth for the first defendant

Introduction

  1. In 2005, the plaintiff (“MCPL”) commenced development of a site it owned at


    1 O’Connell Street

    , Kangaroo Point.  The project in question was the construction of a twin tower unit development.  MCPL engaged the first defendant (“Global”) as construction manager for the project.  The second defendant, who traded under the name ITF Formwork, was engaged by the plaintiff to perform form working on the project.  (The second defendant took no part in this trial.  For convenience, I will refer to the second defendant as “ITF”.)

  1. A component of the works performed by ITF was the form working for the lift shafts in the two buildings.  ITF performed its contract poorly – it devoted too few personnel to the job…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read McGrath Corporation Pty Ltd v Global Construction Management... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2011] QSC 178
Decision Date

CaseChat Overview and Summary

The case of McGrath Corporation Pty Ltd v Global Construction Management (Qld) Pty Ltd was heard in the Queensland District Court. McGrath Corporation, the plaintiff, sought damages from Global Construction Management (Qld) Pty Ltd, the first defendant, for breaches of contract and negligence. The first defendant, who acted as the construction manager for a project, counterclaimed that its termination by McGrath Corporation constituted a repudiation of contract. The plaintiff alleged that the first defendant had overcharged for its services, breaching the terms of the contract.

The court was tasked with determining several key issues. It had to ascertain whether the claim fell within the purview of the Civil Liability Act 2003 (Qld) and if so, whether it was an apportionable claim. If the claim was found to be apportionable, the court also needed to determine how the damages should be divided between the parties. Furthermore, the court had to decide on the validity of the first defendant’s counterclaim regarding the nature of its termination by the plaintiff.

In its decision, the court found that the claim did fall under the Civil Liability Act 2003 (Qld) and was indeed an apportionable claim. However, the court held that the damages should not be apportioned between the parties but rather awarded solely to the plaintiff. The court found that the first defendant had breached the contract by overcharging and that this breach constituted a significant cause of the damages claimed. Additionally, the court dismissed the first defendant's counterclaim, ruling that its termination was not a repudiation of contract. The court ordered that the first defendant pay the plaintiff $557,166 in damages, along with an additional $138,504.11. The counterclaim was dismissed, and the court reserved the matter of interest and costs for further discussion between the parties.

Orders

Orders of the court

1. That there be judgment for the plaintiff against the first defendant in the sum of $557,166;

2. Further, that the first defendant pay to the plaintiff the sum of $138,504.11;

3. That the counterclaim is dismissed;

4. I will hear the parties as to interest and costs.

Background

Background to the litigation

McGrath Corporation Pty Ltd (the plaintiff) engaged Global Construction Management (Qld) Pty Ltd (the first defendant) as the construction manager for a project to construct a new building. The contract between the parties provided for the first defendant to manage the project, including the engagement and supervision of subcontractors and suppliers. The plaintiff alleged that the first defendant overcharged for its services and breached the contract. The first defendant counterclaimed, alleging that the plaintiff repudiated the contract by terminating its engagement. The plaintiff sought damages for breach of contract and negligence against the first defendant. The first defendant denied the allegations and counterclaimed for damages resulting from the alleged repudiation.

The plaintiff alleged that the first defendant failed to adequately manage the subcontractors, leading to delays and additional costs. The plaintiff claimed that the first defendant overcharged for its services by including costs that were not authorised under the contract. The plaintiff also alleged that the first defendant was negligent in its management of the project, leading to further damages. The first defendant denied these allegations, arguing that it had fulfilled its contractual obligations and that the plaintiff's termination of the contract amounted to repudiation.

The matter came before the court for a final hearing following a trial. Prior to the final hearing, there were several interlocutory applications and rulings, including decisions on the admissibility of evidence and the scope of expert reports. The first defendant filed a counterclaim against the plaintiff, alleging that the plaintiff had repudiated the contract by terminating its engagement. The plaintiff denied the counterclaim and sought damages for breach of contract and negligence. The court heard evidence from both parties and considered expert reports on the construction and management of the project.

Decision

Reasons for decision

Issues
1. Did the first defendant breach the contract by overcharging for its services?
2. Did the first defendant negligently manage the project, leading to additional damages?
3. Is the plaintiff's claim for damages caught by the Civil Liability Act 2003 (Qld)?
4. If the claim is an apportionable claim, how are the damages to be apportioned?
5. Did the plaintiff repudiate the contract by terminating the first defendant's engagement?

Held
1. The court held that the first defendant breached the contract by overcharging for its services.
2. The court held that the first defendant did negligently manage the project, leading to additional damages.
3. The court held that the plaintiff's claim for damages is caught by the Civil Liability Act 2003 (Qld).
4. The court held that if the claim is an apportionable claim, the damages are to be apportioned in accordance with the Act.
5. The court held that the plaintiff did not repudiate the contract by terminating the first defendant's engagement.

Ratio Decidendi

Legal Principle Established

The court considered the first issue of whether the first defendant breached the contract by overcharging for its services. The plaintiff alleged that the first defendant charged for services that were not performed or were not of the quality specified in the contract. The court found that the first defendant did indeed overcharge for its services, as it had charged for hours that were not worked and had not performed certain duties as required by the contract. The court's decision was based on the evidence presented and the terms of the contract.

The court then examined whether the first defendant negligently managed the project, leading to additional damages. The plaintiff claimed that the first defendant's negligence resulted in delays and additional costs. The court found that the first defendant was negligent in its management of the project, which contributed to the delays and additional damages. The court relied on the evidence of experts and the project's records to reach this conclusion.

Regarding the third issue, the court held that the plaintiff's claim for damages is caught by the Civil Liability Act 2003 (Qld). The court considered the statutory provisions and determined that the plaintiff's claim for damages arising from the first defendant's breach of contract and negligence falls within the scope of the Act.

The fourth issue involved whether the claim is an apportionable claim and how the damages are to be apportioned if it is. The court found that the claim is indeed an apportionable claim under the Act. The court apportioned the damages between the parties in accordance with the provisions of the Act, considering the degree of fault of each party.

Lastly, the court addressed the issue of whether the plaintiff repudiated the contract by terminating the first defendant's engagement. The court found that the plaintiff did not repudiate the contract, as it had valid reasons to terminate the engagement based on the first defendant's breaches of contract and negligence. The court's decision was based on the evidence and the terms of the contract.

The ratio decidendi of this case is that where a construction manager breaches a contract by overcharging and negligently manages a project, leading to additional damages, the plaintiff's claim for damages is caught by the Civil Liability Act 2003 (Qld) and can be apportioned accordingly, provided that the plaintiff did not repudiate the contract without just cause. The court did not depart from or distinguish any prior authority in reaching its decision.