KOUSA INTERNATIONAL LLC -v- CPB CONTRACTORS PTY LTD FORMERLY KNOWN AS LEIGHTON CONTRACTORS PTY LTD [2017] WASC 11
| SUPREME COURT OF WESTERN AUSTRALIA | Citation No: | [2017] WASC 11 | |
| Case No: | CIV:2036/2016 | 19 JANUARY 2016 | |
| Coram: | ALLANSON J | 20/01/17 | |
| 5 | Judgment Part: | 1 of 1 | |
| Result: | Application dismissed | ||
| B | |||
| PDF Version |
| Parties: | KOUSA INTERNATIONAL LLC CPB CONTRACTORS PTY LTD FORMERLY KNOWN AS LEIGHTON CONTRACTORS PTY LTD |
Catchwords: | Practice and procedure Pleadings Application for further and better particulars Turns on own facts |
Legislation: | Rules of the Supreme Court 1971 (WA), O 20 r 13(1) |
Case References: | Barclay Mowlem Construction Ltd v Dampier Port Authority [2006] WASC 281; (2006) 33 WAR 82 |
JURISDICTION : SUPREME COURT OF WESTERN AUSTRALIA
- IN CHAMBERS
- Plaintiff
AND
CPB CONTRACTORS PTY LTD FORMERLY KNOWN AS LEIGHTON CONTRACTORS PTY LTD
Defendant
Catchwords:
Practice and procedure - Pleadings - Application for further and better particulars - Turns on own facts
Legislation:
Rules of the Supreme Court 1971 (WA), O 20 r 13(1)
Result:
Application dismissed
Category: B
Representation:
Counsel:
Plaintiff : Mr D J Morris
Defendant : Mr J Garas
Solicitors:
Plaintiff : HHG Legal Group
Defendant : Clyde & Co (Perth Office)
Case(s) referred to in judgment(s):
Barclay Mowlem Construction Ltd v Dampier Port Authority [2006] WASC 281; (2006) 33 WAR 82
- ALLANSON J:
Kousa International
1 CPB Contractors Pty Ltd (then known as Leighton Contractors Pty Ltd) was a contractor on a construction project for a wind farm near Geraldton. CPB and Kousa International LLC contracted for Kousa to manufacture, supply, and deliver 22 wind turbine tower structures. CPB erected the towers on site.
2 In 2016, Kousa brought this action against CPB for money owed under the contract. CPB defends the proceedings and counterclaims. In the counterclaim, CPB pleads that Kousa breached the contract. In particular, it pleads that as a consequence of defects and related rectification work, and the late delivery of replacement parts, CPB was delayed in reaching the practical completion date stipulated in its contract with the principal (the Main Contract). CPB claims an indemnity for damages and loss it suffered and incurred, including liquidated damages it was required to pay under the Main Contract for delay in completion.
The defence and counterclaim
3 In its amended defence and counterclaim, CPB pleads these facts:
(1) The contract required Kousa to deliver tower sections in two deliveries: on 14 April 2012 and 1 June 2012. By cl 28.13 of their contract, the parties acknowledged and agreed that delivery of the towers was critical to CPB being able to achieve the contractual completion date under the Main Contract: par 2.
(2) The second delivery of towers on 27 June 2012…
Keep reading for free
Create a free CaseChat account to read Kousa International LLC v CPB Contractors Pty Ltd Formerly K... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2017] WASC 11
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the court was whether the plaintiff's statement of claim provided sufficient particulars to enable the defendant to respond adequately to the allegations. CPB Contractors argued that the plaintiff's claim lacked the necessary detail and specificity to understand the nature of the alleged breaches, thereby impeding their ability to prepare a proper defence. The court had to determine if the plaintiff's application for further and better particulars was justified and whether the case turned on its own specific facts.
The court dismissed the application, holding that the plaintiff's statement of claim was sufficiently detailed. The judge found that the allegations were clear enough to allow the defendant to formulate a response and that the case did not require particulars beyond what had already been provided. The court emphasised that the plaintiff's claims were not overly complex and that any lack of detail did not stem from the inherent nature of the case but rather from the plaintiff's drafting. The dismissal of the application meant that the defendant would proceed to defend the action based on the existing particulars provided by the plaintiff.
Orders
Orders of the court
Application dismissed
Background
Background to the litigation
Evidence
Evidence before the court
Decision
Reasons for decision
Ratio Decidendi