Lacaba Ahden Australia Pty Ltd v Bucyrus (Australia) Pty Ltd

Link copied
Case Copied 22 min read

SUPREME COURT OF QUEENSLAND

CITATION:

Lacaba Ahden Australia Pty Ltd v Bucyrus (Australia) Pty Ltd [2006] QSC 147

PARTIES:

LACABA AHDEN AUSTRALIA PTY LTD
(ACN 060 911 864)
(plaintiff/respondent)
v

BUCYRUS (AUSTRALIA) PTY LTD
(ACN 000 819 232)

(defendant/applicant)

FILE NO/S:

BS 4122 of 2002

DIVISION:

Trial Division

PROCEEDING:

Application

ORIGINATING COURT:

Supreme Court of Queensland

DELIVERED ON:

19 June 2006

DELIVERED AT:

Brisbane

HEARING DATE:

6 April 2006

JUDGE:

McMurdo J

ORDER:

1. The application filed on 16 March 2006 is dismissed. 

2. The defendant will pay the plaintiff’s costs of that application to be assessed.

CATCHWORDS:

PROCEDURE – SUPREME COURT PROCEDURE – QUEENSLAND – PRACTICE UNDER RULES OF COURT – PLEADING – PARTICULARS – where the plaintiff and defendant were in a contract for the erection of a dragline at a coal mine – where the plaintiff claimed a further amount owing for its work – where the plaintiff claimed that it had been delayed by certain acts which caused the date of completion to be delayed – where the defendant applied for further particulars of events which had allegedly caused the delay – whether further particulars should be provided

PROCEDURE – SUPREME COURT PROCEDURE – QUEENSLAND – PRACTICE UNDER RULES OF COURT – PLEADING – GENERALLY – where alternatively to its application for the provision of further particulars, the defendant argues that if the plaintiff cannot provide particulars than this part of its case should be struck out ­– where the defendant claimed the “global case” argued by the plaintiff caused oppression and unfairness ­– whether specified parts of the pleading should be struck out

Wharf Properties Ltd & Anor v Eric Cumine Associates & Ors (No 2) (1991) 52 BLR 8

COUNSEL:

J K Bond SC, with P R Franco for the plaintiff/respondent
R A Holt SC, with E J Longbottom for the defendant/ applicant

SOLICITORS:

Minter Ellison for the plaintiff/respondent
Phillips Fox for the defendant/applicant

  1. J:McMURDO  This is a further dispute about the plaintiff’s particulars in this contractual dispute concerning the erection and commissioning of a dragline at a coal mine.  The plaintiff claims that it has not been fully paid for its work and part of that case is that it is entitled to further sums because its achievement of practical completion was delayed by causes beyond its control, including acts or omissions of the defendant.  Last November, I determined an application by the defendant for further particulars of that delay claim, and this is yet a further application by the defendant for particulars of it. 

  1. The current statement of claim[1] now claims a total of about $2.4 million of which the claims affected by the present application account for about $2.1 million.  One of those claims is for the payment of a performance bonus.  It is common ground that the contract entitled the plaintiff to a bonus of $16,000 for each and every day by which the actual date of practical completion preceded the agreed  date, and that the actual date achieved…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Lacaba Ahden Australia Pty Ltd v Bucyrus (Australia) Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2006] QSC 147
Decision Date

CaseChat Overview and Summary

In the case of Lacaba Ahden Australia Pty Ltd v Bucyrus (Australia) Pty Ltd, the matter before the court involved a contractual dispute between the plaintiff and the defendant, concerning the erection of a dragline at a coal mine. The plaintiff sought additional payment for work performed, alleging that the defendant’s actions had caused delays, extending the project’s completion date. The defendant, in turn, sought further particulars of the events that allegedly caused the delay and argued that the plaintiff's "global case" was oppressive and unfair. The defendant further contended that if the plaintiff could not provide these particulars, certain parts of the claim should be struck out.

The central legal issues for the court to decide were whether the plaintiff was required to provide further particulars of the events that caused the alleged delay and if the defendant’s application to strike out parts of the plaintiff’s case due to the lack of such particulars was justified. The court needed to balance the defendant's right to a clear and concise statement of claim against the plaintiff’s rights under the rules of court, ensuring fairness and avoiding oppressive litigation.

The court dismissed the defendant’s application for further particulars and its alternative application to strike out parts of the plaintiff’s claim. The court held that the plaintiff's statement of claim was sufficient, and the defendant's demands for further particulars were not warranted. The court also found that the plaintiff’s "global case" did not cause oppression or unfairness to the defendant. Consequently, the defendant was ordered to pay the plaintiff's costs of the application.

Orders

Orders of the court

1. The application filed on 16 March 2006 is dismissed.

2. The defendant will pay the plaintiff’s costs of that application to be assessed.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established