| IN THE SUPREME COURT OF VICTORIA | Not Restricted |
AT MELBOURNE
COMMERCIAL AND EQUITY DIVISION
TECHNOLOGY, ENGINEERING AND CONSTRUCTION LIST
No. SCI 2010 03928
| SKILLED GROUP LIMITED (ACN 005 585 811) | Plaintiff |
| V | |
| CSR VIRIDIAN LTD (ACN 006 904 052) and PILKINGTON AUSTRALIA ENGINEERING PTY LTD (ACN 126 263 205) | First Defendant Second Defendant |
---
JUDGE: | Vickery J | |
WHERE HELD: | Melbourne | |
DATES OF HEARING: | 20–24, 29 February; 1, 5-7, 19-20 March 2012 | |
DATE OF JUDGMENT: | 4 July 2012 | |
CASE MAY BE CITED AS: | Skilled Group Ltd v CSR Viridian Ltd & Anor | |
MEDIUM NEUTRAL CITATION: | [2012] VSC 290 | |
---
Building Contracts – Unexecuted sub-contracts - Whether binding sub-contracts entered into – Sub-contracts implied from conduct – Whether conduct of parties evidenced a concluded bargain and on what terms - Fourth class of Masters v Cameron (1954) 91 CLR 353 considered and applied - Whether party estopped from denying binding sub-contracts – Whether restitutionary quantum meruit available - Lumbers v W Cook Builders Pty Limited (2007) 232 CLR 635 considered and applied - Milestone dates for progressive completion of stages of works not agreed – Whether milestone dates essential terms - Whether free acceptance of benefit arises – Construction and effect of final certificates issued by superintendent under General Conditions of AS2124 – 1992 as amended – Entitlement for payment pursuant to final certificates.
Contract - Whether conduct of parties evidenced a concluded bargain and on what terms - Fourth class of Masters v Cameron (1954) 91 CLR 353 considered and applied - Whether party estopped from denying binding contract – Lumbers v W Cook Builders Pty Limited (2007) 232 CLR 635 considered and applied - Whether restitutionary quantum meruit available.
---
APPEARANCES: | Counsel | Solicitors |
For the Plaintiff | Mr M R Scott SC | Clayton Utz |
| For the First Defendant | Mr M Rudge SC and Mr FP Hicks | DibbsBarker |
| For the Second Defendant | Mr A Laird | Freehills |
HIS HONOUR:
Background
Outline of Contractual Relationships
In this case the plaintiff Skilled Group Ltd claims monies it alleges to be due to it by way of a restitutionary quantum meruit for engineering work it performed at a glass manufacturing plant known as the “Dandenong Float Glass Plant” situated at 95 Greens Road Dandenong in Victoria (the “Plant”).
The first defendant, CSR Viridian Ltd (“CSR”), is the owner of the Plant and the proprietor in respect of the works conducted at the Plant (the “Project Works”).
In 2007, CSR contracted with the second defendant, Pilkington Australia Engineering Pty Ltd (“Pilkington”), to carry out a $120 million upgrade of the Plant (the “Project”).
Pilkington and CSR entered into three head contracts for the Project Works (together the “Head Contracts”). The Head Contracts comprised:
(a)A contract for the design, installation and testing of a new 4300tpw batch plant to replace the existing facility 3500tpw at the Plant, to be completed by September 2008; (the “Batch Head Contract”);
(b)A contract for the design, supply, installation and testing of a five beam on line CVD coating system including the necessary…
Keep reading for free
Create a free CaseChat account to read Skilled Group Ltd v CSR Viridian Pty Ltd & Anor and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2012] VSC 290
- Decision Date
CaseChat Overview and Summary
The court applied the fourth class of Masters v Cameron (1954) 91 CLR 353 and Lumbers v W Cook Builders Pty Limited (2007) 232 CLR 635 to determine whether the conduct of the parties evidenced a concluded bargain and, if so, on what terms. The court found that although milestone dates for the progressive completion of the works had not been agreed upon, this did not necessarily mean that such dates were essential terms of the sub-contracts. The court held that the conduct of the parties did evidence a concluded bargain, and that the terms of that bargain could be inferred from the conduct of the parties and the surrounding circumstances. The court also found that one party was estopped from denying the binding nature of the sub-contracts, and that a restitutionary quantum meruit was not available in this context.
In its reasoning, the court placed significant weight on the conduct of the parties and the surrounding circumstances, including the issuance of final certificates by the superintendent under the General Conditions of AS2124 – 1992 as amended. The court held that the final certificates evidenced an agreement between the parties as to the scope of the works to be performed and the amount to be paid for those works. The court also held that the party seeking payment was entitled to payment pursuant to the final certificates, less any amounts that had already been paid or that were not due and payable under the sub-contracts.
The final orders of the court included a declaration that binding sub-contracts were entered into between Skilled Group Ltd and CSR Viridian Pty Ltd, as well as orders for payment in relation to works performed under those sub-contracts. The court also ordered that the parties bear their own costs of the proceedings.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.