| IN THE SUPREME COURT OF VICTORIA | Not Restricted |
AT MELBOURNE
COMMERCIAL AND EQUITY DIVISION
TECHNOLOGY ENGINEERING AND CONSTRUCTION LIST
No. 04899 of 2013
| MAINSTREAM (AUST) PTY LTD (ACN 088 304 483) | Plaintiff |
| v | |
| GILPIP BAYSIDE PROJECTS PTY LTD (ACN 088 010 374) | Defendant |
---
JUDGE: | VICKERY J |
WHERE HELD: | MELBOURNE |
DATE OF HEARING: | 31 OCTOBER 2013 |
DATE OF JUDGMENT: | 13 NOVEMBER 2013 |
CASE MAY BE CITED AS: | MAINSTREAM (AUST) PTY LTD v GILPIP BAYSIDE PROJECTS PTY LTD |
MEDIUM NEUTRAL CITATION: | [2013] VSC 610 |
---
PRACTICE AND PROCEDURE – Interlocutory Application – Injunction – Action to restrain enforcement of guarantee clause – Contract – Security for Payment clauses – Financial liability while Parties in dispute – Clauses 37.4 and 42.1 of the Australian Standard General Conditions of Contract AS4000 – 1997
---
APPEARANCES: | Counsel | Solicitors |
| For the Plaintiff | Mr B Archer (Solicitor) | Brendan J Archer |
| For the Defendant | Mr G Hellyer | Nevett Ford Lawyers |
HIS HONOUR:
This is an application by the Plaintiff, Mainstream (Aust) Pty Ltd (“Mainstream”), for an interlocutory injunction to restrain the Defendant, Gilpip Bayside Projects Pty Ltd (“Gilpip”), from having recourse to a bank guarantee provided under a building contract in the sum of $73,000.
By an agreement dated 12 July 2010 (the “Contract”), the Defendant, Gilpip, engaged the Plaintiff, Mainstream, to refurbish an existing building and construct additional residential accommodation for Gilpip at a site located at 17 to 31 Tanti Avenue, Mornington and undertake associated works (together known as the “Macartan’s project”) for the agreed sum of $9,649,176.
The Contract incorporated the Australian Standard General Conditions of Contract AS4000 -1997 (the “General Conditions”).
Pursuant to the Contract the date for completion of the works was 15 September 2011. The present position is that, save for some relatively minor maintenance and/or defect items, the works have been completed.
A superintendent (the “Superintendent”) was appointed under the Contract.
In addition to the sum of $9,700,000 which Gilpip has paid to Mainstream for the contract works, Mainstream has received payment of approximately $2.8 million for carrying out reinstatement works following significant damage to the works which was caused by a fire on or about 23 October 2011.
The Contract has given rise to a complex web of litigation. Mainstream has initiated three separate sets of proceedings in this Court each involving relatively small sums of money.
This proceeding is an application by Mainstream to restrain the Defendant Gilpip from having recourse to a bank guarantee in the sum of $73,000, which is the amount Gilpip claims the Plaintiff is required to pay to it pursuant to the final certificate, dated 16 August 2013 issued under the Contract by the Superintendent.
Background
By notice dated 9 July 2012, pursuant to clause 42.1 of the General Conditions of Contract, Mainstream gave notice of dispute in relation to the Superintendent’s rejection of it’s claim for extensions of time for completion and in respect to the Superintendent’s calculation of liquidated damages. At a conference on 20 July 2012 Mainstream and Gilpip entered…
Keep reading for free
Create a free CaseChat account to read Mainstream (Aust) Pty Ltd v Gilpip Bayside Projects Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2013] VSC 610
- Decision Date
CaseChat Overview and Summary
The primary legal issues before the court involved the interpretation and application of the security for payment clauses under AS4000-1997, specifically Clauses 37.4 and 42.1. The court was required to determine whether Gilpip was entitled to enforce the guarantee clause under the circumstances presented, particularly in light of the parties' dispute over an act of prevention. Additionally, the court needed to consider the broader implications of enforcing the guarantee on Mainstream's financial obligations and the practical consequences for the continuation of the construction project.
The court examined the contractual terms and found that Clause 37.4 of AS4000-1997 provided for the principal's right to require the contractor to provide security in the event of a dispute, while Clause 42.1 outlined the process for resolving such disputes. The court concluded that the guarantee clause was enforceable and that Mainstream's application to restrain its enforcement was not justified, given the contractual provisions and the lack of a clear legal basis for excusing compliance with the guarantee requirement. The court emphasised that the dispute over an act of prevention did not absolve Mainstream of its obligations under the contract.
The final orders of the court dismissed Mainstream's application for an injunction, allowing Gilpip to proceed with enforcing the guarantee clause as per the contractual terms. The court's decision underscored the importance of adhering to contractual obligations and highlighted the potential consequences for contractors who seek to avoid financial security requirements in the midst of contractual disputes.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.