Novawest Contracting Pty Ltd v Taras Nominees Pty Ltd

Link copied
Case Copied 27 min read

SUPREME COURT OF VICTORIA

CAUSES JURISDICTION

Not Restricted

No. 5374 of 1998

NOVAWEST CONTRACTING PTY LTD Plaintiff
v
TARAS NOMINEES PTY LTD Defendant

---

JUDGE: Gillard J.
WHERE HELD: Melbourne
DATE OF HEARING: 30 October 1998
DATE OF JUDGMENT: 23 December 1998
CASE MAY BE CITED AS: Novawest Contracting Pty Ltd v. Taras Nominees Pty Ltd
MEDIA NEUTRAL CITATION: [1998] VSC 205

---

BUILDING CONTRACT - Standard form general conditions AS 2124-1992 - Interim Certificate - Payable without deduction - No entitlement to set-off claim for damages for delay - Parties exclude the right.

---

APPEARANCES: Counsel Solicitors
For the Plaintiff  MR P.H. BARTON Kennedy Guy
For the Defendant  MR M.B. PHIPPS, Q.C. with Logie-Smith Lanyon
MR M.G. ROBERTS

HIS HONOUR:

  1. This is an appeal from a judgment entered for the plaintiff by the Master on an application for summary judgment pursuant to Order 22 of the Rules of Court.

    Parties

  2. The plaintiff, Novawest Contracting Pty Ltd ("the plaintiff") is a company which carries on the business of civil engineering and construction.

  3. The defendant, Taras Nominees Pty Ltd ("the defendant") carries on the business of land developer.

    Basic facts

  4. The basic facts which led to the dispute between the parties and the proceeding in the court can be briefly stated.

  5. By an agreement made on 14 April 1997, the defendant engaged the plaintiff to construct certain road and drainage works and other works within a development known as the Citiwest Garden Estate at Maribyrnong.

  6. Pursuant to the terms of the contract, a company, Fisher Stewart Pty Ltd, was appointed as superintendent of and under the agreement.

  7. The contract provided for progress payments for works progressively carried out by the plaintiff. The procedure was for the plaintiff to make application to the superintendent and the superintendent was authorised to issue a certificate stating the amount of the payment and within a time period of 28 days after receipt of the application for payment or within 14 days of the issue by the payment certificate whichever was the earlier, the defendant was obliged to pay the contractor the amount set out in the certificate.

  8. The superintendent issued two progress payments being No. 7 on 7 January 1998 in the sum of $81,210 and No. 8 on 26 February 1998 in the sum of $148,260.

  9. The defendant refused to pay the full amounts due under the certificates, contending that there had been delays in the works caused by the plaintiff and defendant was entitled to recover liquidated damages for the delay.

  10. As a consequence, a writ was issued in this court and the plaintiff made application for summary judgment pursuant to Order 22. The matter came on before a Master and on 29 September 1998, the Master ordered that the defendant pay the sum of $190,845.56 which sum included interest. He also ordered that the defendant pay the costs.

  11. The defendant appeals.

    The issues

  12. The plaintiff asserts that it is entitled to judgment on the certificates in accordance with the terms of the…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Novawest Contracting Pty Ltd v Taras Nominees Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[1998] VSC 205
Decision Date

CaseChat Overview and Summary

Novawest Contracting Pty Ltd brought an action against Taras Nominees Pty Ltd regarding a dispute arising from a building contract. The central issue was whether Novawest was entitled to payment of an interim certificate without any deductions, despite Taras's claims for damages for delay. The case was heard in the Supreme Court of New South Wales.

The primary legal issue was whether the contractual terms allowed for the withholding of payment under the circumstances. Specifically, the court had to determine whether the exclusion of the right to set-off claims for damages for delay in the contract was effective and enforceable. The contract in question incorporated the Standard Form General Conditions AS 2124-1992, which included a clause specifying that the contractor was to be paid an interim certificate amount without any deduction, unless otherwise agreed in writing.

The court found that the clause in the contract effectively excluded the right to set-off claims for damages for delay. It held that Taras's attempt to deduct the interim certificate payment to offset its claims for damages was not permissible under the terms of the contract. The court reasoned that the exclusion clause was clear and unambiguous, and therefore, Taras was not entitled to withhold payment. The decision underscored the importance of contractual clarity and the enforceability of exclusion clauses when properly drafted and included in the contract.

The court ordered Taras to pay Novawest the full amount of the interim certificate, without any deductions. It also awarded costs to Novawest, reflecting the clear entitlement under the contract terms.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.