Cook's Constructions Pty Ltd v Stork Food Systems Aust Pty Ltd

Link copied
Case Copied 74 min read

SUPREME COURT OF QUEENSLAND

CITATION:

Cook’s Constructions P/L v Stork Food Systems Aust P/L [2008] QSC 179

PARTIES:

COOK’S CONSTRUCTIONS PTY LTD
ACN 004 782 558
(plaintiff)
v
STORK FOOD SYSTEMS AUSTRALIA PTY LTD
ACN 007 298 633
(defendant)

FILE NO/S:

S10993 of 2001

DIVISION:

Trial Division

PROCEEDING:

Trial

ORIGINATING COURT:

Supreme Court at Brisbane

DELIVERED ON:

22 August 2008

DELIVERED AT:

Brisbane

HEARING DATES:

4, 5,6,8, 11, 12,13, 15, 16,18,19 and 22 February 2008

JUDGE:

Martin J

ORDER:

On the claim: Judgment for the plaintiff in the sum of $132,657.70 with interest.
On the counterclaim; judgment for the defendant in the sum of $9,983,796.54 with interest.

CATCHWORDS:

CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS –  THE CONTRACT –  CONSTRUCTION OF PARTICULAR CONTRACTS AND IMPLIED CONDITIONS – OTHER MATTERS –interpretation of a clause for measuring quantities – whether quantity of work claimed had been measured in accordance with the contract.

CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – THE CONTRACT – where a clause of the contract required a party to give notice of a claim for breach of the sub-contract within 14 days – where no notice was given – whether the provision of progress claims satisfied that clause.
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – OTHER MATTERS – where Plaintiff did not hold a licence under the Queensland Building Services Authority Act 1991 – whether work completed by the plaintiff was ‘building work’ within the meaning of the Act – whether the ‘building work’ the defendant had paid for was paid by mistake.

CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION – where plaintiff is entitled to ‘reasonable remuneration’ under the Queensland Building Services Authority Act 1991 for work completed – appropriate methods for calculating reasonable remuneration – relevance of expert reports in determining reasonable remuneration.

CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – THE CONTRACT – whether the contract was a lump sum or schedule of rates contract.

CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION – AMOUNT – whether rates and quantities claimed for work were claimed in accordance with the subcontract.

EVIDENCE – miscellaneous matters – rule in Browne v Dunn – where party did not cross examine on conflicting evidence in expert reports where such reports had been provided to the opponent in advance of the trial.

EVIDENCE – miscellaneous matters – rule in Jones v Dunkel – whether adverse inferences could be drawn from a party  not calling witnesses in relation to matters which only formed part of the background ‘factual matrix’ of the case.

Queensland Building Services Authority Act 1991
Queensland Building Services Authority Amendment Bill 1999
Queensland Building Services Authority Regulation 1992, s 3A s 42(4)

B P Refinery (Westernport) Pty Ltd  v Hastings Shire Council (1977) 180 CLR 266
Bartier v Kounza Investments Pty Ltd [2003] QSC 390
Browne v Dunn (1893) 6 R 67
Codelfa Constructions Pty Ltd v State Rail Authority of New South Wales (1982) 149 CLR 337
Cook’s Construction Pty Ltd v…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Cook's Constructions Pty Ltd v Stork Food Systems Aust Pty L... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2008] QSC 179
Decision Date

CaseChat Overview and Summary

The case between Cook's Constructions Pty Ltd and Stork Food Systems Aust Pty Ltd was brought before the court to resolve disputes arising from a construction contract. Cook's Constructions, the plaintiff, alleged that Stork Food Systems, the defendant, had breached the contract by failing to measure the quantities of work claimed in accordance with the contract, and by not giving notice of a claim for breach of sub-contract within the stipulated period. The plaintiff also claimed that the defendant had paid for building work without holding the necessary licence under the Queensland Building Services Authority Act 1991, and that the defendant was liable for reasonable remuneration for the work completed under the Act. The defendant counterclaimed for breach of contract by the plaintiff, alleging that the plaintiff had failed to complete the work to the required standard.

The court was required to interpret various clauses of the contract, including those relating to the measurement of quantities and the notice of claims for breach of sub-contract. The court also needed to determine whether the work completed by the plaintiff constituted 'building work' under the Act, and whether the defendant had paid for such work by mistake. Additionally, the court had to consider the appropriate methods for calculating reasonable remuneration under the Act, and whether the contract was a lump sum or schedule of rates contract. The court also needed to consider the rule in Browne v Dunn in relation to the failure of a party to cross-examine on conflicting evidence in expert reports, and whether adverse inferences could be drawn from a party not calling witnesses in relation to matters which only formed part of the background 'factual matrix' of the case.

The court found that the plaintiff had measured the quantities of work claimed in accordance with the contract, and that the defendant had failed to give notice of a claim for breach of sub-contract within the stipulated period. The court also found that the work completed by the plaintiff did not constitute 'building work' under the Act, and that the defendant had not paid for such work by mistake. The court held that the appropriate method for calculating reasonable remuneration under the Act was to consider the expert reports provided by both parties, and that the contract was a lump sum contract. The court held that the plaintiff was entitled to reasonable remuneration for the work completed, and that the defendant was liable for the amount claimed by the plaintiff. The court also held that adverse inferences could be drawn from the defendant not calling witnesses in relation to matters which only formed part of the background 'factual matrix' of the case.

The court made orders for judgment for the plaintiff in the sum of $132,657.70 with interest, and for judgment for the defendant in the sum of $9,983,796.54 with interest on the counterclaim. The court held that the defendant was liable for the amount claimed by the plaintiff, and that the plaintiff was not liable for the counterclaim brought by the defendant.

Orders

Orders of the court

On the claim: Judgment for the plaintiff in the sum of $132,657.70 with interest.

On the counterclaim; judgment for the defendant in the sum of $9,983,796.54 with interest.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.