SUPREME COURT OF QUEENSLAND
CITATION:
Wiggins Island Coal Export Terminal Pty Limited v Civil Mining & Construction Pty Ltd [2017] QCA 296
PARTIES:
WIGGINS ISLAND COAL EXPORT TERMINAL PTY LIMITED
ACN 131 210 038
(appellant)
v
CIVIL MINING & CONSTRUCTION PTY LTD
ACN 102 557 175
(respondent)FILE NO/S:
Appeal No 10845 of 2017
SC No 6050 of 2013DIVISION:
Court of Appeal
PROCEEDING:
General Civil Appeal
ORIGINATING COURT:
Supreme Court at Brisbane – [2017] QSC 218 (Flanagan J)DELIVERED ON:
4 December 2017
DELIVERED AT:
Brisbane
HEARING DATES:
22 – 23 November 2017
JUDGES:
Fraser and Gotterson and McMurdo JJA
ORDERS:
1. Allow the appeal.
2. Set aside the order granting leave to the respondent to re-open its case.
3. Set aside the order made on 6 October 2017 that the costs be reserved.
4. Order the respondent to pay the costs of the application heard on 28 July and 21 August 2017 and the costs of the appeal.
CATCHWORDS:
PROCEDURE – PROCEDURAL ASPECTS OF EVIDENCE – OTHER MATTERS – where a dispute arose in which the respondent claimed about $14.5 million and the appellant counterclaimed about $12.5 million – where the case was tried over 36 days and resulted in a judgment running to more than 300 pages (the May Reasons) – where one of the respondent’s claims was for costs associated with delays, caused by the appellant, in reaching practical completion under a contract (the Delay Claim) – where the respondent had sought a particular method of calculation of the Delay Claim but, in closing submissions, sought to advance a new method of calculation, but did not seek leave to re-open its case – where the appellant did not object to the new argument but submitted that if that new method was accepted, certain modifications should be made to the method – where the trial judge accepted the new method with the modifications urged by the appellants – where the final orders could not be pronounced without further submissions on how those modifications could be made – where the May reasons required further submissions on the recalculation of an exhibit in accordance with the appellant’s modifications – where the result of that recalculation was agreed between the parties but there followed extensive written and oral submissions from the respondent, urging a different method of calculation, in the course of which the respondent applied to re-open its case – where, in a reserved judgment, the respondent was given leave to re-open – where the appellant appealed the decision to give leave to re-open – whether the judge erred and a substantial injustice would result
Adam P Brown Male Fashions Pty Ltd v Philip Morris Inc (1981) 148 CLR 170; [1981] HCA 39, cited
Civil Mining & Construction Pty Ltd v Wiggins Island Coal Export Terminal Pty Ltd [2017] QSC 85, related
Civil Mining & Construction Pty Ltd v Wiggins Island Coal Export Terminal Pty Ltd (No 2) [2017] QSC 218, reversed
In re the…
Keep reading for free
Create a free CaseChat account to read Wiggins Island Coal Export Terminal Pty Limited v Civil Mini... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2017] QCA 296
- Decision Date
CaseChat Overview and Summary
The legal issues the court had to address revolved around the admissibility and application of the new method of calculation proposed by the respondent at the closing stage of the trial. The appellant argued that if the new method was accepted, certain modifications should be applied to it, while the respondent sought to present expert evidence to quantify the delay costs under this new method. The court's task was to determine whether the trial judge erred in granting leave to the respondent to reopen its case and whether such an error would result in a substantial injustice. The respondent's application to reopen its case was pivotal, as it aimed to present expert evidence to quantify the delay costs under the newly proposed method, which required further clarification and agreement on the modifications suggested by the appellant.
The court found that the order granting leave to the respondent to reopen its case was erroneous and would result in a substantial injustice. The trial judge had required further submissions on how the modifications to the new method of calculation should be implemented. However, the court noted that the trial had proceeded in the usual manner, with the parties expected to present all evidence before making final submissions. The respondent's attempt to introduce a new method of calculation at the closing stage, without seeking leave to reopen its case, was improper. The court held that the respondent's case should have been concluded based on the evidence already presented, and the trial judge's decision to allow the respondent to reopen its case to present expert evidence on the new method was an error. Consequently, the court allowed the appeal, set aside the orders granting leave to reopen the case and reserving costs, and ordered the respondent to pay the costs of the proceedings.
Orders
Orders of the court
1. Allow the appeal.
2. Set aside the order granting leave to the respondent to re-open its case.
3. Set aside the order made on 6 October 2017 that the costs be reserved.
4. Order the respondent to pay the costs of the application heard on 28 July and 21 August 2017 and the costs of the appeal.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
The order which was made was that CMC have leave to re-open its case “to call expert evidence in respect of the quantification of the Delay Claim.”Consideration No order was made in this case for the determination of any issue ahead of other issues. The trial proceeded in the usual way, with the parties expected to adduce all of the evidence upon which they might wish to rely, before they made final submissions and the judgment was reserved. CMC presented its Delay Claim in the alternative. Its primary argument became that it was to be compensated for being delayed in reaching practical completion later than the parties had agreed. For that argument, CMC had to prove the facts by which its entitlement under clause 36 could be quantified. In its submissions at the end of the trial, CMC assured the judge that this could be done from the evidence which had been adduced. In the May Reasons, the judge referred to no evidentiary gap in CMC’s case. He required only the assistance of the parties in an exercise of mathematical calculation, upon the basis of the evidence already before the court. The issues which the parties had required the judge to determine are evident from the May Reasons at [803] to [839]. The judge accepted CMC’s case that the cost of the entirety of its on-Site overheads, over the period of 208 days, was recoverable. Most importantly, there was no issue as to what were in fact the resources which contributed to CMC’s on-Site overheads during this period. The resources which constituted the on-Site overheads were evidenced by the Overheads Spreadsheet. This document was initially prepared by CMC and, after some changes had been made by another consultant, it was briefed to Mr Roberts, who made some adjustments after reviewing it. The document, as adjusted by Mr Roberts, was accepted by Mr Tsipis. There was no controversy about its content and that it incorporated all of the relevant contributors to CMC’s on-Site overheads. Moreover, as the judge held in the October Reasons, the document had been effectively incorporated into CMC’s pleading. CMC’s case, as presented to the judge after the May Reasons, departs from the common ground of the Overheads Spreadsheet. As the judge said in his October Reasons,[22] there was a question of “whether CMC should continue to be bound by the resources identified in the Overheads Spreadsheet.”[22]At [20]. In its written submissions dated 5 July 2017, WICET did agree that there were some omissions from the Spreadsheet. It conceded that there were particular instances where contemporaneous documents (ie. timesheets, daily costing sheets or meeting minutes) recorded a person working on-site on a particular day, but where that resource has not been included in the Spreadsheet.[23] These were simply adjustments to correct clerical errors in the Spreadsheet. By conceding them, WICET did not agree to a different meaning to be given to the expression “on-Site overheads”, than that from which the Spreadsheet had been prepared.[23]WICET’s submissions dated 5 July 2017 paragraph 27.