Civil Mining and Construction Pty Ltd v Wiggins Island Coal Export Terminal Pty Ltd (No 2)

Link copied
Case Copied 15 min read

SUPREME COURT OF QUEENSLAND

CITATION:

Civil Mining & Construction Pty Ltd v Wiggins Island Coal Export Terminal Pty Ltd (No 2) [2017] QSC 218

PARTIES:

CIVIL MINING & CONSTRUCTION PTY LTD
(ABN 18 102 557 175)

(plaintiff)

v
WIGGINS ISLAND COAL EXPORT TERMINAL PTY LTD (ABN 20 131 210 038)

(defendant)

FILE NO:

No BS 6050 of 2013

DIVISION:

Trial

PROCEEDING:

Trial

ORIGINATING COURT:

Supreme Court at Brisbane

DELIVERED ON:

6 October 2017

DELIVERED AT:

Brisbane

HEARING DATE:

28 July 2017 and 21 August 2017

JUDGE:

Flanagan J

ORDER:

1.    The plaintiff is granted leave to re-open its case to call expert evidence in respect of the quantification of the Delay Claim.

2.    I will hear the parties as to further directions.

3.    Costs reserved.

CATCHWORDS:

EVIDENCE – ADDUCING EVIDENCE – COURSE OF EVIDENCE – RE-OPENING CASE – BY PARTY – where the plaintiff seeks leave to re-open its case to lead expert evidence to quantify a delay claim arising from the Court’s construction of the Contract – where final judgment cannot be given until quantification of the delay claim – whether the defendant would be prejudiced by the plaintiff re-opening the case – whether any issues of natural justice arise – whether the plaintiff should be bound by its pleading – whether the quantification could be done by the court

Water Board v Moustakas (1988) 180 CLR 491

COUNSEL:

B D O’Donnell QC with S J Webster for the plaintiff

D Kelly QC with M G Lyons for the defendant

SOLICITORS:

Thomson Geer for the plaintiff

Corrs Chambers Westgarth for the defendant

  1. On 19 May 2017 the Court delivered Reasons in this matter.  As a number of issues remained outstanding the Court could not give judgment.

  2. On 25 May 2017 directions were made for the filing and serving of written submissions in relation to:

    (a)the quantification of the Delay Claim and the defendant’s counterclaim in respect of the Delay Claim;

    (b)     the return of the Bank Guarantee;

    (c)     the quantification of payments to be made in relation to the Final Certificate; and

    (d)     interest.

  3. After the receipt of written submissions the matter was listed for hearing, limited to two hours, on 28 July 2017.  On that day it became apparent that the matter could not be completed within the allotted time.  A further hearing was conducted on 21 August 2017. 

    Quantification of the Delay Claim

  4. In the course of the two hearings it became evident that there is a dispute between the parties as to how the Delay Claim should be quantified. 

  5. On the second day of hearing CMC made an oral application to re-open its case for the limited purpose of leading expert evidence as to the quantification of the Delay Claim.  The re-opening sought by CMC was expressed by Senior Counsel as follows:

    “… both sides would be at liberty to call expert evidence to establish what is a reasonable rate for the overheads for the 208 days, and that expert evidence would be confined to the…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Civil Mining and Construction Pty Ltd v Wiggins Island Coal... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2017] QSC 218
Decision Date

CaseChat Overview and Summary

Civil Mining and Construction Pty Ltd (CMC) sued Wiggins Island Coal Export Terminal Pty Ltd (WICET) over a delay claim arising from a construction contract. The dispute centred on the quantification of the delay claim, specifically the calculation of on-site overheads for a 208-day extension of time. The parties had differing views on the methodology for calculating the daily rate for on-site overheads. The Federal Court of Australia was tasked with determining whether CMC could reopen its case to present expert evidence to quantify the delay claim, given that the final judgment hinged on this quantification. Additionally, the court had to assess whether WICET would be prejudiced by CMC reopening its case and whether any issues of natural justice would arise.

The court found that CMC was entitled to an extension of time of 208 days, but the quantification of the delay claim remained unresolved. The key issue was whether CMC should be permitted to reopen its case to present expert evidence on the appropriate daily rate for on-site overheads. The court considered the implications of CMC’s pleadings and the principle of natural justice in its decision. The court held that CMC’s pleadings did not limit its ability to present expert evidence on the correct methodology for calculating the daily rate for on-site overheads, as the task required by the contract had not been properly addressed by any expert. Consequently, the court granted CMC leave to reopen its case for this purpose, while reserving further directions and costs.

The court's decision allowed CMC to present expert evidence to quantify the delay claim, ensuring that the task outlined in the contract was properly addressed. This decision was grounded in the need for the court to have the benefit of expert assistance in quantifying the delay claim, particularly given the significant omissions and discrepancies in the Overheads Spreadsheet. The court's ruling was also influenced by the principle of natural justice, ensuring that CMC had the opportunity to present its case in the most effective manner possible. The court reserved further directions and costs for later determination.

Orders

Orders of the court

1. The plaintiff is granted leave to re-open its case to call expert evidence in respect of the quantification of the Delay Claim.

2. I will hear the parties as to further directions.

3. Costs reserved.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established

At Reasons [1069] I found that CMC was entitled to an extension of time of 208 days. The parties were required to provide further submissions in having Exhibit 427 recalculated so as to reflect the use of Mr Roberts’ reasonable rates and incorporating a weighted average. The parties have recalculated Exhibit 427 by reference to Mr Roberts’ reasonable rates. There is no dispute that the weighted average daily rate is $11,627.63. Using that rate, CMC’s total entitlement to on‑Site overheads is $2,418,546.03. As WICET has already paid CMC $4,087,233.21 in respect of the Delay Claim, CMC would be obliged to repay WICET $1,668,687.18. CMC submits that this weighted average daily rate cannot be regarded as a “reasonable rate” under clause 40.5(c) of the General Conditions of the Contract and it should not be adopted. CMC submits that there is a more appropriate way to determine a “reasonable rate or price” under clause 40.5(c) for the 208 days of delay caused by WICET that uses Mr Roberts’ reasonable rates, but adopts a different methodology for determining the appropriate daily rate.[11] WICET’s position is that the quantum of the Delay Claim should be determined by requiring CMC to repay to WICET $1,668,687.18. That is, CMC should be bound by the calculation exercise identified in Exhibit 427. [11] Plaintiff’s Further Submissions, [7].Consideration CMC seeks to re-open its case primarily because no expert carried out the task of assessing a reasonable rate for on-Site overheads for the period of 208 days constituting the extension of time. Mr Roberts in carrying out his analysis did analyse each day of the 11 delay events. WICET therefore suggests that Mr Roberts’ analysis incorporates all but 28 days of the 208 day period for the extension of time. CMC submits however, that Mr Roberts carried out a different exercise at valuing actual on-Site resources for discrete periods of delay. Some of the periods of the delay events overlap. CMC therefore submits that Mr Roberts has only analysed 141 days of the 208 days of the extension of time period. Even if it is accepted that Mr Roberts has analysed a large number of days that fall within the 208 day period, it remains the case that neither expert carried out the task required upon a proper construction of clause 36. The Court therefore does not have the benefit of such expert assistance for the purposes of quantifying the Delay Claim. The real issue in dispute between the parties is whether CMC should continue to be bound by the resources identified in the Overheads Spreadsheet. CMC submits that the spreadsheet contains significant omissions and discrepancies that make it an unsuitable basis for calculating CMC’s on-Site overheads. Annexure C to CMC’s further submissions identifies 14 substantial omissions in the Overheads Spreadsheet. CMC submits that notably those omissions are at the “back-end” of the project, such that they substantially impact upon the weighted average approach.[12] CMC submits that Mr Roberts’ utilisation of the spreadsheet is the basis for only valuing CMC’s on-Site overheads by one method (valuing at the time of the delay). This cannot mean that it is automatically suitable to use for another method (valuing at the ending of the project). CMC further submits that the Overheads Spreadsheet was not incorporated into its pleading. It is apparent, in my view, that the figure pleaded in paragraph 221(b) of the Eighth Further Statement of Claim is derived from Mr Roberts’ Appendix 3.3 which utilised the Overheads Spreadsheet. The fact that the spreadsheet is indirectly incorporated into CMC’s pleading is not however, the end of the matter. CMC has already, without objection, departed from its pleaded case as to how the relevant delay is identified. Having been permitted to depart from its pleaded case in this respect there is no difficulty, in my view, with permitting CMC to re-open its case for the purposes of quantifying the Delay Claim based on the Court’s construction of clause 36. Neither CMC’s pleading nor how it conducted its case limits CMC in now establishing, by expert evidence, an appropriate average daily rate for on-Site overheads for the extension of time of 208 days. This is the task that clause 40.5(c) of the General Conditions of the Contract requires.[13][12] Plaintiff’s Further Submissions, [14]-[15].[13] Plaintiff’s Further Submissions, [11].