CMA Assets Pty Ltd v John Holland Pty Ltd [No 6]

Link copied
Case Copied 82 min read

JURISDICTION     :   SUPREME COURT OF WESTERN AUSTRALIA

IN CIVIL

CITATION:   CMA ASSETS PTY LTD Formerly Known as CMA Contracting Pty Ltd -v- JOHN HOLLAND PTY LTD [No 6] [2015] WASC 217

CORAM:   ALLANSON J

HEARD:   8-12, 15-19, 22-24, 29-30 APRIL, 1, 6-8 MAY 2013

DELIVERED          :   19 JUNE 2015

FILE NO/S:   CIV 1297 of 2008

BETWEEN:   CMA ASSETS PTY LTD Formerly Known as CMA Contracting Pty Ltd

Plaintiff

AND

JOHN HOLLAND PTY LTD
Defendant

Catchwords:

Contract - Direction - Claims for delay, extension of time and variation - Counterclaim for breach - Failure to meet date for completion - Contractual set off - Misleading or deceptive conduct - Liquidated damages

Legislation:

Rules of the Supreme Court 1971 (WA), O 20 r 9

Result:

Plaintiff's claim allowed in part
Counterclaim allowed in part

Category:    B

Representation:

Counsel:

Plaintiff:     Mr D Fagan SC & Mr J C Giles

Defendant:     Mr C L Zelestis QC & Ms K F Banks-Smith

Solicitors:

Plaintiff:     Minter Ellison

Defendant:     Corrs Chambers Westgarth

Case(s) referred to in judgment(s):

Alpha Wealth Financial Services Pty Ltd v Frankland River Olive Company Ltd [2008] WASCA 119; (2008) 66 ACSR 594

Australian Broadcasting Commission v Australasian Performing Right Association Ltd [1973] HCA 36; (1973) 129 CLR 99

Australian Broadcasting Corporation v XIVth Commonwealth Games Ltd (1988) 18 NSWLR 540

Australian Goldfields NL (in liq) v North Australian Diamonds NL [2009] WASCA 98

Baiyai Pty Ltd v Guy [2009] NSWCA 65

Brambles Holdings Ltd v Bathurst City Council [2001] NSWCA 61; (2001) 53 NSWLR 153

Branir Pty Ltd v Owston Nominees (No 2) Pty Ltd [2001] FCA 1833; (2001) 117 FCR 424

British Steel Corp v Cleveland Bridge and Engineering Co Ltd [1984] 1 All ER 504

Butcher v Lachlan Elder Realty Pty Ltd [2004] HCA 60; (2004) 218 CLR 592

Campbell v Backoffice Investments Pty Ltd [2009] HCA 25; (2009) 238 CLR 304

Commonwealth v Amann Aviation Pty Ltd [1991] HCA 54; (1991) 174 CLR 64

Empirnall Holdings Pty Ltd v Machon Paull Partners Pty Ltd (1988) 14 NSWLR 523

Ermogenous v Greek Orthodox Community of SA Inc [2002] HCA 8; (2002) 209 CLR 95

Fazio v Fazio [2012] WASCA 72

Fink v Fink [1946] HCA 54; (1946) 74 CLR 127

Gates v City Mutual Life Assurance Society Ltd [1986] HCA 3; (1986) 160 CLR 1

GEC Marconi Systems Pty Ltd v BHP Information Technology Pty Ltd [2003] FCA 50; (2003) 128 FCR 1

Geebung Investments Pty Ltd v Varga Group Investments No 8 Pty Ltd (1995) 7 BPR 14,551

Gould v Vaggelas [1985] HCA 75; (1985) 157 CLR 215

GR Securities Pty Ltd v Baulkham Hills Private Hospital Pty Ltd (1986) 40 NSWLR 631

Grainger v Williams [2009] WASCA 60

Henville v Walker [2001] HCA 52; (2001) 206 CLR 459

I & L Securities Pty Ltd v HTW Valuers (Brisbane) Pty Ltd [2002] HCA 41; (2002) 210 CLR 109

Johnson Tiles Pty Ltd v Esso Australia…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read CMA Assets Pty Ltd v John Holland Pty Ltd [No 6] and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2015] WASC 217
Decision Date

CaseChat Overview and Summary

The case of CMA Assets Pty Ltd v John Holland Pty Ltd [No 6] involved a contractual dispute between the parties, focusing on claims for delay, extension of time, and variation, as well as a counterclaim for breach. The dispute centred around the completion of works under a subcontract, with CMA alleging that John Holland had prevented the timely completion of the works, while John Holland sought liquidated damages for the delay. The court was tasked with determining whether the prevention principle applied, whether the liquidated damages clause was enforceable, and whether there was misleading or deceptive conduct.

The central legal issues revolved around the interpretation and application of the prevention principle, which holds that a party cannot insist on the performance of a contractual obligation if it is the cause of the other party's non-performance. The court also needed to consider the enforceability of the liquidated damages clause and whether it was effectively excluded by the terms of the subcontract. Additionally, the court had to assess whether there was any misleading or deceptive conduct that would render the liquidated damages clause unenforceable.

In its reasoning, the court found that the prevention principle, while applicable in general contract law, was expressly excluded by clause 10.13 of the subcontract. This clause provided that if CMA failed to comply with the notice procedures, it would have no entitlement to an extension of time, and the prevention principle would not apply. As a result, CMA was precluded from benefiting from an extension of time and was liable for liquidated damages, even if the delay was caused by John Holland. The court further determined that CMA had not achieved completion by the required date and was therefore liable for the liquidated damages claimed by John Holland.

The final orders of the court confirmed that CMA was liable for the liquidated damages claimed by John Holland, and the counterclaim for misleading or deceptive conduct was dismissed. The court held that the exclusion clause in the subcontract was effective, and therefore, the prevention principle did not apply in this instance.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established

The plea that performance was delayed or prevented by John Holland raises the principle commonly referred to as the 'prevention principle'. In summary, a party cannot insist on the performance of a contractual obligation by the other party if it itself is the cause of the other party's non‑performance. In Spiers Earthworks Pty Ltd v Landtec Projects Corporation Pty Ltd [No 2] [2012] WASCA 53; (2012) 287 ALR 360 [47], McLure P characterised this principle 'as a particular manifestation of the obligation to cooperate implied as a matter of law in all contracts': see, for example, Secured Income Real Estate (Australia) Ltd v St Martins Investments Pty Ltd [1979] HCA 51; (1979) 144 CLR 596, 607. The prevention principle applies to delays in practical completion of a contract caused by acts or omissions of the principal within the scope of the contract that prevent practical completion within the time stipulated in the contract. It is particularly relevant in response to John Holland's claim for liquidated damages. If, in the events that have occurred, CMA has been prevented by John Holland's breach or default from achieving the stipulated date, and there is no contractual mechanism for substituting a new date, then there is no date from which liquidated damages will run, and the right to liquidated damages will be lost. In the context of this case, CMA's obligation to achieve practical completion by 14 March 2007 is replaced by an obligation to reach practical completion within a reasonable time. The application of the prevention principle must be considered in the context of the particular contract. The Subcontract between John Holland and CMA directly addressed this question in cl 10.13, providing that if CMA failed to comply with the notice procedures in cl 10.12 it shall have no entitlement to an extension of time and any principle of law or equity which might render the Date for Practical Completion unenforceable shall not apply. Expressly, cl 10.13 purports to exclude the prevention principle. In my opinion, it is effective in doing so. CMA is precluded from the benefit of an extension of time and is liable for liquidated damages, even where the relevant delay has been caused by John Holland: see Peninsula Balmain Pty Ltd v Abigroup Contractors Pty Ltd [2002] NSWCA 211 [78], referred to by McLure P in Spiers [57]. CMA also pleaded in its reply and argued that it had achieved completion under the Subcontract by 25 June 2007, because by then the fragments and rebar which were necessary to be removed to achieve Completion (as defined in the Subcontract) were removed. The argument starts with the proper construction of 'Completion' under the Subcontract. Completion means the stage when the Works are or a Stage is complete:(a)except for minor Defects which do not prevent the Works or the Stage from being reasonably capable or being used for the intended purpose and correction of which will not prejudice the lawful and convenient use; and(b)the Subcontractor has done everything which the Subcontract requires it to do prior to completion including those things described in the Particulars.