Spiers Earthworks Pty Ltd v Landtec Projects Corporation Pty Ltd [No 2]

Link copied
Case Copied 79 min read

JURISDICTION     :   SUPREME COURT OF WESTERN AUSTRALIA

TITLE OF COURT  :   THE COURT OF APPEAL (WA)

CITATION:   SPIERS EARTHWORKS PTY LTD -v- LANDTEC PROJECTS CORPORATION PTY LTD  [No 2] [2012] WASCA 53

CORAM:   McLURE P

NEWNES JA
MURPHY JA

HEARD:   5 JULY 2011 & ON THE PAPERS

DELIVERED          :   13 MARCH 2012

FILE NO/S:   CACV 67 of 2010

BETWEEN:   SPIERS EARTHWORKS PTY LTD

Appellant

AND

LANDTEC PROJECTS CORPORATION PTY LTD
Respondent

ON APPEAL FROM:

Jurisdiction              :  DISTRICT COURT OF WESTERN AUSTRALIA

Coram  :WAGER DCJ

Citation  :LANDTEC PROJECTS CORPORATION PTY LTD -v- SPIERS EARTHWORKS PTY LTD [2010] WADC 74

File No  :CIV 495 of 2007

Jurisdiction              :  DISTRICT COURT OF WESTERN AUSTRALIA

Coram  :WAGER DCJ

Citation  :LANDTEC PROJECTS CORPORATION PTY LTD -v- SPIERS EARTHWORKS PTY LTD [2010] WADC 74 (S)

File No  :CIV 495 of 2007

Catchwords:

Contract - Penalty - Liquidated damages clause - Property development - Agreement to complete works by specified date - Work not completed by specified date - Whether liquidated damages clause a penalty or genuine pre­estimate of loss

Building contract - AS2124­1986 - Extension of time clause - Prevention principle - Whether time 'at large' - Estoppel - Waiver - Variations - Contract - Objective intention of parties - Interest on unpaid payment certificates

Legislation:

Town Planning & Development Act 1928 (WA) (repealed)

Result:

Appeal allowed in part
Cross-appeal allowed in part

Category:    B

Representation:

Counsel:

Appellant:     Mr B P Wheatley

Respondent:     Mr A Metaxas & Mr B G Grubb

Solicitors:

Appellant:     Mossensons

Respondent:     Metaxas & Hager

Case(s) referred to in judgment(s):

620 Collins Street Pty Ltd v Abigroup Contractors Pty Ltd (No 2) [2006] VSC 491

Agricultural and Rural Finance Pty Ltd v Gardiner [2008] HCA 57; (2008) 238 CLR 570

Ange v First East Auction Holdings Pty Ltd [2011] VSCA 335

Bridge Pump Co Pty Ltd v Myles Southwest Fuel Supplies Pty Ltd (Unreported, WASCA, Library No 970636, 22 October 1997)

Bysouth v Shire of Blackburn and Mitcham (No 2) [1928] VLR 562

Codelfa Construction Pty Ltd v State Rail Authority of New South Wales [1982] HCA 24; (1982) 149 CLR 337

Coulton v Holcombe [1986] HCA 33; (1986) 162 CLR 1

Dunlop Pneumatic Tyre Co Ltd v New Garage and Motor Co Ltd [1914] UKHL 1; [1915] AC 79

Equuscorp Pty Ltd v Glengallan Investments Pty Ltd [2004] HCA 55; (2004) 218 CLR 471

Esanda Finance Corporation Ltd v Plessnig [1989] HCA 7; (1989) 166 CLR 131

Farah Constructions Pty Ltd v Say-Dee Pty Ltd [2007] HCA 22; (2007) 230 CLR 89

Gaymark Investments Pty Ltd v Walter Construction Group Ltd [1999] NTSC 143

IAC (Leasing) Ltd v Humphrey [1972] HCA 1; (1972) 126 CLR 131

Kane Constructions Pty Ltd v Sopov [2005] VSC 237; (2006) 22 BCL 92

Landtec Projects Corporation Pty Ltd v Spiers Earthworks Pty Ltd [2010] WADC 74 (S)

Lax v Glenmore Pty Ltd (1969) 90 WN (NSW) 703

MacMahon Construction Pty Ltd…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Spiers Earthworks Pty Ltd v Landtec Projects Corporation Pty... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2012] WASCA 53
Decision Date

CaseChat Overview and Summary

In the case of Spiers Earthworks Pty Ltd v Landtec Projects Corporation Pty Ltd [No 2], the parties were embroiled in a building and construction dispute, with the developer, Spiers Earthworks, as the plaintiff, and the contractor, Landtec Projects Corporation, as the defendant. The case revolved around the interpretation of a liquidated damages clause and an extension of time clause in their contract. The developer sought payment from the contractor for non-completion of works by the specified date, while the contractor counterclaimed. At first instance, the trial judge allowed part of the developer's claim and part of the contractor's counterclaim, resulting in a net flow of money in favour of the developer of approximately $24,000. The developer was ordered to pay the costs of the developer's claim, while no costs were awarded in respect of the contractor's counterclaim. Upon appeal, the contractor was found to be the successful party, with a net flow of money in their favour of approximately $123,000. The contractor argued that they should be awarded their costs, while the developer contended that the contractor's misconduct and unreasonable rejection of a settlement offer should result in the denial of costs to the contractor.

The court examined the relevant legal issues, including the interpretation of the liquidated damages clause, the extension of time clause, and the consequences of the contractor's failure to comply with the notice requirements. The court also considered the contractor's misconduct and unreasonable rejection of a settlement offer as grounds for denying costs to the contractor. The court ultimately decided that the contractor should be awarded their costs, as there was no clear authority that would support depriving the contractor of costs due to their conduct. The court found that the contractor's failure to comply with the notice requirements did not preclude them from being awarded an extension of time, as the superintendent's power to extend time could be exercised in the interests of both parties. The court also determined that the contractor's misconduct and unreasonable rejection of a settlement offer did not warrant the denial of costs.

In summary, the court held that the contractor was the successful party and awarded them their costs. The court found that the contractor's failure to comply with the notice requirements did not preclude them from being awarded an extension of time, and that their misconduct and unreasonable rejection of a settlement offer did not warrant the denial of costs. The court followed the decision in Peninsula Balmain Pty Ltd v Abigroup Contractors Pty Ltd [2002] NSWCA 211, which held that a contractor's failure to make a claim within time precludes an extension of time, and the contractor remains liable for liquidated damages, even if the delay had been caused by events otherwise falling within the prevention principle.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

JUDGMENT OF THE COURT: These supplementary reasons deal with the costs of the appeal in this matter and the order for costs made by the trial judge with respect to the proceedings at first instance. We will adopt, in these reasons, the abbreviations used in this court's principal reasons for judgment. The underlying dispute was in the nature of a building/construction dispute. At first instance, the developer, who was the plaintiff (the respondent in the appeal), claimed certain moneys from the contractor, who was the defendant (the appellant in the appeal). The contractor counterclaimed. The judge, in effect, allowed part of the developer's claim and allowed part of the contractor's counterclaim. The net 'flow of money' between the two parties, on the trial judge's findings, was approximately $24,000 in favour of the developer. As to costs, the judge ordered the contractor to pay the developer's costs of the developer's claim, and ordered that there be no order for costs in respect of the contractor's counterclaim. As a result of this appeal, there is a net flow of money the other way. Excluding interest, there is now a net flow of money from the developer to the contractor of approximately $123,000. The contractor (appellant) contends, without objection from the developer (respondent), that as a consequence, the contractor is to be regarded as the successful party at first instance, and in the appeal, within the meaning of O 66 r 1 of the Rules of the Supreme Court1971 (WA). In that regard, the parties referred to Badge Constructions Pty Ltd v Penbury Coast Pty Ltd [1999] SASC 6 [12]; Keywest Construction Group Pty Ltd v Footscray Holdings Pty Ltd (Unreported, WASC, Library No 930078, 23 February 1993) (Anderson J); BMD Major Projects Pty Ltd v Victorian Urban Development Authority (No 2) [2007] VSC 441 [8] ‑ [10]. See also Miles v Palm Bridge Pty Ltd [2001] WASC 42 [51]; LNC Harper Davidson Pty Ltd v Keywest Building Co Pty Ltd (Unreported, WASC, Library No 7192, 13 July 1988) (Kennedy J); Kane Constructions Pty Ltd v Sopov (No 2) [2005] VSC 492 [64] ‑ [66] (Warren CJ). The developer contends, however, that even though the contractor is to be regarded as the successful party, there exist grounds upon which it is appropriate, in the particular circumstances of this case, to deprive the contractor of its costs. In substance, two grounds are alleged. One is that the contractor had misconducted the proceedings at trial and in the appeal. The other is that the contractor had unreasonably rejected a settlement offer on the morning of the first day of the trial. With respect to the alleged misconduct, the developer relies upon two authorities - Capolingua v Phylum Pty Ltd (1991) 5 WAR 137 and Verna Trading Pty Ltd v New India Assurance Co Ltd [1991] 1 VR 129 at 156. In Capolingua v Phylum, the successful defendants were deprived of their costs and it was held that justice required that there be no order as to costs. In that case, there were deficiencies in the defendants' pleading. Those deficiencies, combined with the conduct of the defendants' solicitors at a mediation conference, and the defendants' failure to comply with pre‑trial orders, served to obscure the real issues at trial. This caused unnecessary evidence to be led, and caused the opportunity to dispose of the matter expeditiously by way of a preliminary issue to be lost. In Verna Trading v New India Assurance Co the successful defendant, an insurer, was ordered to pay the plaintiff's (the insured's) costs on a solicitor/client basis up to the first day of the trial. The defendant insurer had, following receipt of the plaintiff's claim under the policy, given no indication as to why it denied liability; it had failed in its pleadings to admit facts which were within its knowledge; it had asserted defences which were later abandoned at trial; and in the early part of the trial it raised for the first time defences upon which it ultimately succeeded.

Ratio Decidendi

Legal Principle Established

There is a conflict of authority in Australia as to the consequence of a principal relying on a contractor's failure to comply with the notice requirements as a ground for rejecting the contractor's claim for an extension of time. In New South Wales it has been held that the prevention principle does not apply where the contractor failed to satisfy a condition enlivening its contractual right to an extension of time: Turner Corporation Ltd v (in liq) Co-ordinated Industries Pty Ltd (1995) 11 BCL 202 (Rolfe J), upheld on appeal (Turner Corporation Ltd v Co‑ordinated Industries Pty Ltd [1995] NSWCA 476); Turner Corporation Ltd (Receiver & Manager Appointed) v Austotel Pty Ltd (1997) 13 BCL 378, 384 ‑ 385 (Cole J). A contrary conclusion was reached by Bailey J in Gaymark Investments Pty Ltd v Walter Construction Group Ltd [1999] NTSC 143. He concluded that the prevention principle applied in the event of a contractor's loss of entitlement to an extension of time because of a failure to give the required notice unless the liquidated damages clause gives the superintendent a discretionary power to extend time. The New South Wales Court of Appeal in Peninsula Balmain Pty Ltd v Abigroup Contractors Pty Ltd [2002] NSWCA 211 upheld the correctness of the Turner Corporation cases. In Peninsula Balmain, the contractor had not sought or been granted extensions of time for a period prior to the principal terminating the building contract. However, a referee appointed by a judge pursuant to the New South Wales Supreme Court rules exercised the discretionary power of the superintendent to grant an extension of time. The building contract included the General Conditions of Contract AS 2124 ‑ 1992, cl 35.5 of which is in materially the same terms as its equivalent in the first contract. The New South Wales Court of Appeal held that, even without the superintendent having the power to extend time, a contractor's failure to make a claim within time precludes an extension of time and the contractor remains liable for liquidated damages, even if the delay had been caused by events otherwise falling within the prevention principle [78]. Further, the court concluded that the superintendent's power, and the power of the referee in his stead, to extend time in the absence of written notice is capable of being exercised in the interests of both the principal and the contractor, and the superintendent is obliged to act honestly and impartially in deciding whether to exercise that power [79]. I understand the proposition to be that, by reason of the superintendent's obligation to act fairly and impartially, he or she is under a duty to consider the exercise of the power to extend time (absent an entitlement), at least upon a request from the contractor to do so. This court is obliged to follow Peninsula Balmain unless convinced it is clearly wrong: Farah Constructions Pty Ltd v Say-Dee Pty Ltd (2007) 230 CLR 89 [135]. Neither party expressly challenged the correctness of the decision. It has been followed in Victoria: 620 Collins Street PtyLtd vAbigroup Contractors Pty Ltd (No 2) [2006] VSC 491. I have reservations as to the correctness of the conclusion that anyone other than the superintendent can grant an extension of time under cl 35.5 of the General Conditions. However, it is unnecessary to determine the question because there is another route which has the same practical effect.