JURISDICTION : SUPREME COURT OF WESTERN AUSTRALIA
TITLE OF COURT : THE COURT OF APPEAL (WA)
CITATION: SPIERS EARTHWORKS PTY LTD -v- LANDTEC PROJECTS CORPORATION PTY LTD [No 2] [2012] WASCA 53
CORAM: McLURE P
NEWNES JA
MURPHY JA
HEARD: 5 JULY 2011 & ON THE PAPERS
DELIVERED : 13 MARCH 2012
FILE NO/S: CACV 67 of 2010
BETWEEN: SPIERS EARTHWORKS PTY LTD
Appellant
AND
LANDTEC PROJECTS CORPORATION PTY LTD
Respondent
ON APPEAL FROM:
Jurisdiction : DISTRICT COURT OF WESTERN AUSTRALIA
Coram :WAGER DCJ
Citation :LANDTEC PROJECTS CORPORATION PTY LTD -v- SPIERS EARTHWORKS PTY LTD [2010] WADC 74
File No :CIV 495 of 2007
Jurisdiction : DISTRICT COURT OF WESTERN AUSTRALIA
Coram :WAGER DCJ
Citation :LANDTEC PROJECTS CORPORATION PTY LTD -v- SPIERS EARTHWORKS PTY LTD [2010] WADC 74 (S)
File No :CIV 495 of 2007
Catchwords:
Contract - Penalty - Liquidated damages clause - Property development - Agreement to complete works by specified date - Work not completed by specified date - Whether liquidated damages clause a penalty or genuine preestimate of loss
Building contract - AS21241986 - Extension of time clause - Prevention principle - Whether time 'at large' - Estoppel - Waiver - Variations - Contract - Objective intention of parties - Interest on unpaid payment certificates
Legislation:
Town Planning & Development Act 1928 (WA) (repealed)
Result:
Appeal allowed in part
Cross-appeal allowed in part
Category: B
Representation:
Counsel:
Appellant: Mr B P Wheatley
Respondent: Mr A Metaxas & Mr B G Grubb
Solicitors:
Appellant: Mossensons
Respondent: Metaxas & Hager
Case(s) referred to in judgment(s):
620 Collins Street Pty Ltd v Abigroup Contractors Pty Ltd (No 2) [2006] VSC 491
Agricultural and Rural Finance Pty Ltd v Gardiner [2008] HCA 57; (2008) 238 CLR 570
Ange v First East Auction Holdings Pty Ltd [2011] VSCA 335
Bridge Pump Co Pty Ltd v Myles Southwest Fuel Supplies Pty Ltd (Unreported, WASCA, Library No 970636, 22 October 1997)
Bysouth v Shire of Blackburn and Mitcham (No 2) [1928] VLR 562
Codelfa Construction Pty Ltd v State Rail Authority of New South Wales [1982] HCA 24; (1982) 149 CLR 337
Coulton v Holcombe [1986] HCA 33; (1986) 162 CLR 1
Dunlop Pneumatic Tyre Co Ltd v New Garage and Motor Co Ltd [1914] UKHL 1; [1915] AC 79
Equuscorp Pty Ltd v Glengallan Investments Pty Ltd [2004] HCA 55; (2004) 218 CLR 471
Esanda Finance Corporation Ltd v Plessnig [1989] HCA 7; (1989) 166 CLR 131
Farah Constructions Pty Ltd v Say-Dee Pty Ltd [2007] HCA 22; (2007) 230 CLR 89
Gaymark Investments Pty Ltd v Walter Construction Group Ltd [1999] NTSC 143
IAC (Leasing) Ltd v Humphrey [1972] HCA 1; (1972) 126 CLR 131
Kane Constructions Pty Ltd v Sopov [2005] VSC 237; (2006) 22 BCL 92
Landtec Projects Corporation Pty Ltd v Spiers Earthworks Pty Ltd [2010] WADC 74 (S)
Lax v Glenmore Pty Ltd (1969) 90 WN (NSW) 703
MacMahon Construction Pty Ltd…
Keep reading for free
Create a free CaseChat account to read Spiers Earthworks Pty Ltd v Landtec Projects Corporation Pty... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2012] WASCA 53
- Decision Date
CaseChat Overview and Summary
The court examined the relevant legal issues, including the interpretation of the liquidated damages clause, the extension of time clause, and the consequences of the contractor's failure to comply with the notice requirements. The court also considered the contractor's misconduct and unreasonable rejection of a settlement offer as grounds for denying costs to the contractor. The court ultimately decided that the contractor should be awarded their costs, as there was no clear authority that would support depriving the contractor of costs due to their conduct. The court found that the contractor's failure to comply with the notice requirements did not preclude them from being awarded an extension of time, as the superintendent's power to extend time could be exercised in the interests of both parties. The court also determined that the contractor's misconduct and unreasonable rejection of a settlement offer did not warrant the denial of costs.
In summary, the court held that the contractor was the successful party and awarded them their costs. The court found that the contractor's failure to comply with the notice requirements did not preclude them from being awarded an extension of time, and that their misconduct and unreasonable rejection of a settlement offer did not warrant the denial of costs. The court followed the decision in Peninsula Balmain Pty Ltd v Abigroup Contractors Pty Ltd [2002] NSWCA 211, which held that a contractor's failure to make a claim within time precludes an extension of time, and the contractor remains liable for liquidated damages, even if the delay had been caused by events otherwise falling within the prevention principle.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
There is a conflict of authority in Australia as to the consequence of a principal relying on a contractor's failure to comply with the notice requirements as a ground for rejecting the contractor's claim for an extension of time. In New South Wales it has been held that the prevention principle does not apply where the contractor failed to satisfy a condition enlivening its contractual right to an extension of time: Turner Corporation Ltd v (in liq) Co-ordinated Industries Pty Ltd (1995) 11 BCL 202 (Rolfe J), upheld on appeal (Turner Corporation Ltd v Co‑ordinated Industries Pty Ltd [1995] NSWCA 476); Turner Corporation Ltd (Receiver & Manager Appointed) v Austotel Pty Ltd (1997) 13 BCL 378, 384 ‑ 385 (Cole J). A contrary conclusion was reached by Bailey J in Gaymark Investments Pty Ltd v Walter Construction Group Ltd [1999] NTSC 143. He concluded that the prevention principle applied in the event of a contractor's loss of entitlement to an extension of time because of a failure to give the required notice unless the liquidated damages clause gives the superintendent a discretionary power to extend time. The New South Wales Court of Appeal in Peninsula Balmain Pty Ltd v Abigroup Contractors Pty Ltd [2002] NSWCA 211 upheld the correctness of the Turner Corporation cases. In Peninsula Balmain, the contractor had not sought or been granted extensions of time for a period prior to the principal terminating the building contract. However, a referee appointed by a judge pursuant to the New South Wales Supreme Court rules exercised the discretionary power of the superintendent to grant an extension of time. The building contract included the General Conditions of Contract AS 2124 ‑ 1992, cl 35.5 of which is in materially the same terms as its equivalent in the first contract. The New South Wales Court of Appeal held that, even without the superintendent having the power to extend time, a contractor's failure to make a claim within time precludes an extension of time and the contractor remains liable for liquidated damages, even if the delay had been caused by events otherwise falling within the prevention principle [78]. Further, the court concluded that the superintendent's power, and the power of the referee in his stead, to extend time in the absence of written notice is capable of being exercised in the interests of both the principal and the contractor, and the superintendent is obliged to act honestly and impartially in deciding whether to exercise that power [79]. I understand the proposition to be that, by reason of the superintendent's obligation to act fairly and impartially, he or she is under a duty to consider the exercise of the power to extend time (absent an entitlement), at least upon a request from the contractor to do so. This court is obliged to follow Peninsula Balmain unless convinced it is clearly wrong: Farah Constructions Pty Ltd v Say-Dee Pty Ltd (2007) 230 CLR 89 [135]. Neither party expressly challenged the correctness of the decision. It has been followed in Victoria: 620 Collins Street PtyLtd vAbigroup Contractors Pty Ltd (No 2) [2006] VSC 491. I have reservations as to the correctness of the conclusion that anyone other than the superintendent can grant an extension of time under cl 35.5 of the General Conditions. However, it is unnecessary to determine the question because there is another route which has the same practical effect.