SUPREME COURT OF QUEENSLAND
CITATION:
Grocon Constructors (Qld) Pty Ltd v Juniper Developer No 2 Pty Ltd [2015] QCA 291
PARTIES:
GROCON CONSTRUCTORS (QLD) PTY LTD
ACN 120 476 495
(appellant)
v
JUNIPER DEVELOPER NO 2 PTY LTD
ACN 123 200 699
(respondent)
RIDER LEVETT BUCKNALL (QLD) PTY LTD
ACN 125 873 252
(not a party to the appeal)FILE NO/S:
Appeal No 5015 of 2015
SC No 9291 of 2011DIVISION:
Court of Appeal
PROCEEDING:
General Civil Appeal
ORIGINATING COURT:
Supreme Court at Brisbane – [2015] QSC 102DELIVERED ON:
18 December 2015
DELIVERED AT:
Brisbane
HEARING DATE:
9 September 2015
JUDGES:
Holmes CJ and Atkinson and McMeekin JJ
Separate reasons for judgment of each member of the Court, each concurring as to the orders madeORDERS:
1. The appeal is dismissed.
2. The appellant to pay the respondent’s costs.
CATCHWORDS:
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – PERFORMANCE OF WORK – REMEDIES FOR BREACH OF CONTRACT – DISTINCTION BETWEEN PENALTY AND LIQUIDATED DAMAGES – where the respondent contracted the appellant to design and construct a development – where the appellant was required to bring the development to a stage of Practical Completion – where a liquidated damages clause made liquidated damages payable if the appellant failed to achieve Practical Completion by the Date for Practical Completion – where the contract contemplated the respondent’s sale of residential units – whether the penalty doctrine was applicable to the liquidated damages clause making it unenforceable – whether Practical Completion was defined such that it might not be achieved if minor contractual obligations were not fulfilled – whether the amount required to pay under the liquidated damages clause was extravagant and unconscionable in amount in comparison with the greatest loss that could conceivably be proved – whether the liquidated damages clause operated upon a breach of a single obligation – whether the contract had the effect that even if practical completion was delayed by reason of a minor matter that nonetheless meant, and the parties contemplated so at the time of contract, that the respondent would be unable to settle the contracts of sale
Alfred McAlpine Capital Projects Limited v Tilebox Limited [2005] EWHC 281, cited
AMEV-UDC Finance Ltd v Austin (1986) 162 CLR 170; [1986] HCA 63, cited
Astley v Weldon (1801) 2 Bos & P 346; [1801] EngR 108, cited
Clydebank Engineering and Shipbuilding Co v Don Jose Ramos Yzquierdo y Castaneda [1905] AC 6; [1904] UKHL 3, cited
Dunlop Pneumatic Tyre Co Ltd v New Garage & Motor Co Ltd [1915] AC 79; [1914] UKHL 1, cited
Elsey v JG Collins Insurance Agencies Limited [1978] 2 SCR 916; (1978) 83 DLR (3d) 1, cited
Esanda Finance Corporation v Plessnig (1989) 166 CLR 131; [1989] HCA 7, cited
Geraldton Food Distributors Pty Ltd v Spencer [1985] WAR 261, cited
Insurance Australia Ltd v HIH Casualty & General Insurance Ltd (In liq) (2007) 18 VR 528; [2007] VSCA 223,…
Keep reading for free
Create a free CaseChat account to read Grocon Constructors (Qld) Pty Ltd v Juniper Developer No 2 P... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2015] QCA 291
- Decision Date
CaseChat Overview and Summary
The court was tasked with determining whether the penalty doctrine rendered the liquidated damages clause unenforceable. This involved assessing whether Practical Completion was defined in such a manner that it could not be achieved if minor contractual obligations were not fulfilled. The court also had to consider whether the amount of liquidated damages was extravagant and unconscionable compared to the greatest loss that could be proven. Furthermore, the court needed to determine if the clause operated upon a breach of a single obligation and whether the contract had the effect of preventing the respondent from settling contracts of sale even due to minor delays.
The court concluded that the appeal was without merit and dismissed it. The reasoning was that the liquidated damages clause was not a penalty but a legitimate pre-estimate of the loss. The court found that the definition of Practical Completion was clear and that minor breaches did not prevent its achievement. Additionally, the court held that the amount of liquidated damages was not extravagant or unconscionable. The court also determined that the clause did not operate upon a breach of a single obligation and that the contract did not have the effect of preventing the respondent from settling contracts of sale due to minor delays. Consequently, the appeal was dismissed, and the appellant was ordered to pay the respondent’s costs.
Orders
Orders of the court
1. The appeal is dismissed.
2. The appellant to pay the respondent’s costs.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.