DISTRICT COURT OF QUEENSLAND
CITATION:
Midson Construction (Qld) Pty Ltd v The Haggarty Group Pty Ltd [2021] QDC 280
PARTIES:
MIDSON CONSTRUCTION (QLD) PTY LTD
ABN 28 135 951 549
(Plaintiff)
v
THE HAGGARTY GROUP PTY LTD
ABN 62 142 220 184
(Defendant)
FILE NO:
BD889/21
DIVISION:
Civil
PROCEEDING:
Application
ORIGINATING COURT:
District Court at Brisbane
DELIVERED ON:
10 December 2021
DELIVERED AT:
Brisbane
HEARING DATE:
20 August 2021
JUDGE:
Porter QC DCJ
ORDER:
[1] As to the question whether clause 14(a) of the contract between the Plaintiff and the Defendant of 4 August 2020 (the Contract) is void for uncertainty, the answer is that the Contract is not void for uncertainty.
[2] As to the question whether clause 14(a) of the Contract is void as a penalty, the answer is that the Contract is not void as a penalty.
[3] As to the question whether, properly construed, the Plaintiff’s entitlement to recover liquidated damages for delay under the Contract was lost in circumstances where the following factual circumstances are assumed for the purposes of this application only:
(a) The Plaintiff was the cause of the Defendant’s delay; or
(b) The delay was caused by the Plaintiff’s breach of the Contract;
the answer is that the Plaintiff’s entitlement has not been lost in those circumstances.
CATCHWORDS:
CONTRACTS – REMEDIES – LIQUIDATED DAMAGES – PENALTY – where plaintiff claims liquidated damages from defendant under a subcontract – where defendant challenges liability for liquidated damages on three bases – where defendant contends that the liquidated damages clause in the subcontract is uncertain – where defendant contends that the liquidated damages clause is void as a penalty – where defendant contends that plaintiff is not entitled to liquidated damages because its acts prevented defendant from reaching Practical Completion and the so-called prevention principle is not excluded by the terms of the subcontract – whether the liquidated damages clause is void for uncertainty – whether the liquidated damages clause is void as a penalty – whether plaintiff’s entitlement to recover liquidated damages for delay under the subcontract was lost in circumstances where it is assumed that plaintiff was the cause of defendant’s delay or the delay was caused by plaintiff’s breach of the subcontract
LEGISLATION:
Uniform Civil Procedure Rules 1999 (Qld), r. 483, Part 5 of Chapter 13
CASES:
Andrews v ANZ Banking Group Ltd (2012) 247 CLR 205
C B Darvall & Darvall v Moloney (2006) 236 ALR 796
Clydebank Engineering and Shipbuilding Company v Don Jose Ramos Yzquierdo y Castaneda [1905] AC 6
Dunlop Pneumatic Tyre Co Ltd v New Garage and Motor Co Ltd [1915] AC 79
Grocon Constructors (Qld) Pty Ltd v Juniper Developer (No 2) Pty Ltd [2015] QCA 291
Hervey Bay (JV) Pty Ltd v Civil Mining and Construction Pty Ltd [2008] QSC 58
Kane Constructions Pty Ltd v Sopov [2005] VSC 237
Law v Local Board of Redditch [1892] 1 QB 127
Keep reading for free
Create a free CaseChat account to read Midson Construction (Qld) Pty Ltd v The Haggarty Group Pty L... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2021] QDC 280
- Decision Date
CaseChat Overview and Summary
The court examined whether the liquidated damages clause was void for uncertainty, void as a penalty, and whether the Plaintiff's entitlement to recover liquidated damages for delay was lost under the prevention principle. The court found that the clause was neither void for uncertainty nor as a penalty. The court also ruled that the Plaintiff's entitlement to recover liquidated damages for delay was not lost under the prevention principle. The court's reasoning was based on the clear terms of the subcontract and the absence of any evidence to support the Defendant's claims.
The court ordered that the liquidated damages clause in the subcontract was not void for uncertainty or as a penalty, and that the Plaintiff's entitlement to recover liquidated damages for delay was not lost under the prevention principle. The court's decision was based on the clear terms of the subcontract and the absence of any evidence to support the Defendant's claims. The court did not dismiss the proceeding or make any other order.
Orders
Orders of the court
[1] As to the question whether clause 14(a) of the contract between the Plaintiff and the Defendant of 4 August 2020 (the Contract) is void for uncertainty, the answer is that the Contract is not void for uncertainty.
[2] As to the question whether clause 14(a) of the Contract is void as a penalty, the answer is that the Contract is not void as a penalty.
[3] As to the question whether, properly construed, the Plaintiff’s entitlement to recover liquidated damages for delay under the Contract was lost in circumstances where the following factual circumstances are assumed for the purposes of this application only:
(a) The Plaintiff was the cause of the Defendant’s delay; or
(b) The delay was caused by the Plaintiff’s breach of the Contract;
the answer is that the Plaintiff’s entitlement has not been lost in those circumstances.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi