Midson Construction (Qld) Pty Ltd v The Haggarty Group Pty Ltd

Link copied
Case Copied 43 min read

DISTRICT COURT OF QUEENSLAND

CITATION:

Midson Construction (Qld) Pty Ltd v The Haggarty Group Pty Ltd [2021] QDC 280

PARTIES:

MIDSON CONSTRUCTION (QLD) PTY LTD

ABN 28 135 951 549

(Plaintiff)

v

THE HAGGARTY GROUP PTY LTD

ABN 62 142 220 184

(Defendant)

FILE NO:

BD889/21

DIVISION:

Civil

PROCEEDING:

Application

ORIGINATING COURT:

District Court at Brisbane

DELIVERED ON:

10 December 2021

DELIVERED AT:

Brisbane

HEARING DATE:

20 August 2021

JUDGE:

Porter QC DCJ

ORDER:

[1]          As to the question whether clause 14(a) of the contract between the Plaintiff and the Defendant of 4 August 2020 (the Contract) is void for uncertainty, the answer is that the Contract is not void for uncertainty.

[2]          As to the question whether clause 14(a) of the Contract is void as a penalty, the answer is that the Contract is not void as a penalty.

[3]          As to the question whether, properly construed, the Plaintiff’s entitlement to recover liquidated damages for delay under the Contract was lost in circumstances where the following factual circumstances are assumed for the purposes of this application only:

(a)     The Plaintiff was the cause of the Defendant’s delay; or

(b)     The delay was caused by the Plaintiff’s breach of the Contract;

the answer is that the Plaintiff’s entitlement has not been lost in those circumstances.

CATCHWORDS:

CONTRACTS – REMEDIES – LIQUIDATED DAMAGES –   PENALTY – where plaintiff claims liquidated damages from defendant under a subcontract – where defendant challenges liability for liquidated damages on three bases – where defendant contends that the liquidated damages clause in the subcontract is uncertain – where defendant contends that the liquidated damages clause is void as a penalty – where defendant contends that plaintiff is not entitled to liquidated damages because its acts prevented defendant from reaching Practical Completion and the so-called prevention principle is not excluded by the terms of the subcontract – whether the liquidated damages clause is void for uncertainty – whether the liquidated damages clause is void as a penalty – whether plaintiff’s entitlement to recover liquidated damages for delay under the subcontract was lost in circumstances where it is assumed that plaintiff was the cause of defendant’s delay or the delay was caused by plaintiff’s breach of the subcontract  

LEGISLATION:

Uniform Civil Procedure Rules 1999 (Qld), r. 483, Part 5 of Chapter 13

CASES:

Andrews v ANZ Banking Group Ltd (2012) 247 CLR 205

C B Darvall & Darvall v Moloney (2006) 236 ALR 796

Clydebank Engineering and Shipbuilding Company v Don Jose Ramos Yzquierdo y Castaneda [1905] AC 6

Dunlop Pneumatic Tyre Co Ltd v New Garage and Motor Co Ltd [1915] AC 79

Grocon Constructors (Qld) Pty Ltd v Juniper Developer (No 2) Pty Ltd [2015] QCA 291

Hervey Bay (JV) Pty Ltd v Civil Mining and Construction Pty Ltd [2008] QSC 58

Kane Constructions Pty Ltd v Sopov [2005] VSC 237

Law v Local Board of Redditch [1892] 1 QB 127

Paciocco v ANZ Banking Group Ltd (2016) 258 CLR 525

Peninsula Balmain Pty Limited v…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Midson Construction (Qld) Pty Ltd v The Haggarty Group Pty L... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Find similar cases

Other decisions on the same topics. Each opens in a new tab.

Details

Case
[2021] QDC 280
Decision Date

CaseChat Overview and Summary

Midson Construction (Qld) Pty Ltd (the Plaintiff) sued The Haggarty Group Pty Ltd (the Defendant) for liquidated damages claimed under a subcontract. The Defendant contested the claim on three grounds: the liquidated damages clause in the subcontract was uncertain, the clause was void as a penalty, and the Plaintiff's entitlement to liquidated damages for delay was lost under the prevention principle. The case was heard by the Queensland Court of Appeal, which was required to determine the validity of the liquidated damages clause and the Defendant's defences.

The court examined whether the liquidated damages clause was void for uncertainty, void as a penalty, and whether the Plaintiff's entitlement to recover liquidated damages for delay was lost under the prevention principle. The court found that the clause was neither void for uncertainty nor as a penalty. The court also ruled that the Plaintiff's entitlement to recover liquidated damages for delay was not lost under the prevention principle. The court's reasoning was based on the clear terms of the subcontract and the absence of any evidence to support the Defendant's claims.

The court ordered that the liquidated damages clause in the subcontract was not void for uncertainty or as a penalty, and that the Plaintiff's entitlement to recover liquidated damages for delay was not lost under the prevention principle. The court's decision was based on the clear terms of the subcontract and the absence of any evidence to support the Defendant's claims. The court did not dismiss the proceeding or make any other order.

Orders

Orders of the court

[1] As to the question whether clause 14(a) of the contract between the Plaintiff and the Defendant of 4 August 2020 (the Contract) is void for uncertainty, the answer is that the Contract is not void for uncertainty.

[2] As to the question whether clause 14(a) of the Contract is void as a penalty, the answer is that the Contract is not void as a penalty.

[3] As to the question whether, properly construed, the Plaintiff’s entitlement to recover liquidated damages for delay under the Contract was lost in circumstances where the following factual circumstances are assumed for the purposes of this application only:

(a) The Plaintiff was the cause of the Defendant’s delay; or

(b) The delay was caused by the Plaintiff’s breach of the Contract;

the answer is that the Plaintiff’s entitlement has not been lost in those circumstances.

Background

Background to the litigation

Decision

Reasons for decision

Part 5 of Chapter 13 deals with Separate Questions. It provides:Part 5 Separate decision on questions 482 Definition for pt 5 In this part— question includes a question or issue in a proceeding, whether of fact or law or partly of fact and partly of law, and whether raised by pleadings, agreement of parties or otherwise. 483 Order for decision and statement of case for opinion (1)The court may make an order for the decision by the court of a question separately from another question, whether before, at, or after the trial or continuation of the trial of the proceeding. (2)... 484 Orders, directions on decision If a question is decided under this part, the court may, subject to rule 475, make the order, grant the relief and give the directions that the nature of the case requires.485 Disposal of proceedings The court may, in relation to a decision of a question under this part, as the nature of the case requires— (a)dismiss the proceeding or the whole or part of a claim for relief in the proceeding; or (b)give judgment, including a declaratory judgment; or (c)make another order. 486 Form and content of separate question A separate question or questions must— (a)set out the question or questions to be decided; and (b)be divided into paragraphs numbered consecutively. In C B Darvall & Darvall v Moloney (2006) 236 ALR 796, Wilson J observed:[42]The Court has a wide discretion whether to order the separate determination of questions, and the contemporary approach is to do so where questions can conveniently be so decided, even though this may not necessarily resolve the whole dispute. In Reading Australia Pty Ltd v Australian Mutual Provident Society Branson J reviewed the principles relevant to the application of a cognate provision in the Federal Court Rules. Her Honour noted that – “(d) where the preliminary question is one of mixed fact and law, it is necessary that the question can be precisely formulated and that all of the facts that are on any fairly arguable view relevant to the determination of the question are ascertainable either as facts assumed to be correct for the purposes of the preliminary determination, or as agreed facts or as facts to be judicially determined.”[43]Here the parties presented the Court with a list of separate questions in relation to the estoppel and indemnity questions. In relation to the former they said –“The following are the facts agreed upon by the parties” and then set out in separate paragraphs more than 4 pages of facts upon which the Court was asked to determine certain questions. By agreement, those facts were supplemented at the hearing by a number of affidavits and a further agreed fact. In relation to the indemnity questions they said –“The Court is asked to assume the following facts and contentions”and then set out in separate paragraphs more than a page of facts and contentions, before saying –“In light of the assumed facts and contentions, the following questions are stated for determination by the Court.”[44]At the hearing it became apparent that those representing Darvalls saw a significant difference between “facts agreed upon between the parties” and “assumed facts and contentions” – a difference not recognised by those representing the liquidators. Senior counsel for Darvalls was at pains to dispel any suggestion that his clients had sought some forensic advantage. He submitted that there was utility in proceeding on the basis that if the Court considered the assumed facts to be sufficient to arrive at conclusions on the indemnity issues, that would foreclose the issue on those questions, but if it considered them insufficient, that would not foreclose the issue. The essence of his submission seemed to be that if the Court took the view that because of the assumed facts, no matter what other facts might be proved, his clients could not succeed, then a long factual inquiry would be obviated.[45]It is not the Court’s function to determine questions on a hypothetical basis. The questions in relation to legal expenses incurred from 17 December 1999 are of mixed fact and law. In Bass v Permanent Trustee Co Ltd the High Court said –“Special problems can arise where the preliminary question is one of mixed fact and law. As Brooking J pointed out in Jacobson v Ross, it is necessary in that situation that there be precision both in formulating the question and in specifying the facts upon which it is to be decided. His Honour added: ‘Care must be taken to ensure that, in one way or another, all the facts that are on any fairly arguable view relevant to the determination of the question are ascertainable ... as facts assumed to be correct for the purposes of the preliminary determination, or as facts which both sides accept as correct, or as facts which are to be judicially determined. Failure to do this, and in particular failure to perceive that the facts alleged in a pleading are some only of the facts relevant to the determination of the preliminary question, may make the order for preliminary determination unfruitful.’ Quite apart from rendering the ‘order for preliminary determination unfruitful’, the failure to identify the relevant facts or the means by which they are to be ascertained may result in procedures which do not conform to the judicial process. That is a matter to which it will be necessary to return.”(footnotes omitted)

Ratio Decidendi

Legal principle established