Probuild Constructions (Aust) Pty Ltd v DDI Group Pty Ltd

Link copied
Case Copied 71 min read

Court of Appeal


Supreme Court


New South Wales

  • Summary available
Medium Neutral Citation: Probuild Constructions (Aust) Pty Ltd v DDI Group Pty Ltd [2017] NSWCA 151
Hearing dates:15 September 2016
Decision date: 23 June 2017
Before: Beazley ACJ at [1],
McColl JA at [2],
Macfarlan JA at [146]
Decision:

Appeal dismissed with costs.

Catchwords:

BUILDING AND CONSTRUCTION – subcontract for renovation works – payment claim under Building and Construction Industry Security of Payment Act 1999 (NSW) – where variations directed by principal after Date for Practical Completion – where Date of Practical Completion 114 days late – where principal sought to reduce payment claim to nil by way of set-off based on liquidated damages claim for delayed completion

  ADMINISTRATIVE LAW – procedural fairness – where adjudicator rejected liquidated damages claim – whether adjudicator applied prevention principle – whether application of prevention principle denial of procedural fairness
Legislation Cited: Building and Construction Industry Security of Payment Act 1999 (NSW)
Civil Procedure Act 2005 (NSW)
Uniform Civil Procedures Rules 2005 (NSW)
Cases Cited: 620 Collins Street Pty Ltd v Abigroup Contractors Pty Ltd (No 2) [2006] VSC 491
Abel Point Marina (Whitsundays) Pty Ltd v Uher [2006] QSC 295
Alcatel Australia Ltd v Scarcella (1998) 44 NSWLR 349
Built Environs Pty Ltd v Tali Engineering Pty Ltd [2013] SASC 84
Cardinal Project Services Pty Ltd v Hanave Pty Ltd (2011) 81 NSWLR 716; [2011] NSWCA 399
Chase Oyster Bar Pty Ltd v Hamo Industries Pty Ltd (2010) 78 NSWLR 393; [2010] NSWCA 190
Clarence Street Pty Ltd v Isis Projects Pty Ltd (2005) 64 NSWLR 448; [2005] NSWCA 391
Falgat Constructions Pty Ltd v Equity Australia Corp Pty Ltd (2005) 62 NSWLR 385; [2005] NSWCA 49
Gaymark Investments Pty Ltd v Walter Construction Group Ltd (1999) 16 BCL 449; [1999] NTSC 143
Gipping Construction Ltd v Eaves Ltd [2008] EWHC 3134 (TCC)
Grocon Constructors Pty Ltd v Planit Cocciardi Joint Venture (No 2) (2009) 26 VR 172; [2009] VSC 426
Hawkins Construction (Aust) Pty Ltd v Mac’s Industrial Pipework Pty Ltd [2002] NSWCA 136
Holme v Guppy (1838) 150 ER 1195; 3 M&W 387
John Holland Pty Ltd v Roads and Traffic Authority of New South Wales [2007] NSWCA 140
Kioa v West (1985) 159 CLR 550; [1985] HCA 81
Multiplex Constructions Pty Ltd v Luikens [2003] NSWSC 1140
Multiplex Constructions (UK) Ltd v Honeywell Control Systems Ltd (No 2) [2007] EWHC 447
Musico v Davenport [2003] NSWSC 977
Nepean Engineering Pty Ltd v Total Process Services Pty Ltd (in liq) (2005) 64 NSWLR 462; [2005] NSWCA 409
Northbuild Construction Pty Ltd v Central Interior Linings Pty Ltd [2012] 1 Qd R 525; [2011] QCA 22
Peak Construction (Liverpool) Ltd v McKinney Foundations Ltd [1970] 1 BLR 111
Peninsula Balmain Pty Ltd v Abigroup Contractors Pty Ltd [2002] NSWCA 211; (2002) 18 BCL 322
Re Minister for Immigration and Multicultural Affairs; Ex parte Lam (2003) 214 CLR 1; [2003] HCA 6
Re…
CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Probuild Constructions (Aust) Pty Ltd v DDI Group Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2017] NSWCA 151
Decision Date

CaseChat Overview and Summary

The dispute in *Probuild Constructions (Aust) Pty Ltd v DDI Group Pty Ltd* concerned a payment claim made by DDI Group Pty Ltd (the respondent) under the *Building and Construction Industry Security of Payment Act 1999* (NSW) for renovation works carried out for Probuild Constructions (Aust) Pty Ltd (the appellant). The appellant sought to reduce the payment claim to nil by claiming set-off for liquidated damages due to the respondent's alleged delay in completing the works. The matter came before the Court of Appeal of New South Wales.

The primary legal issues before the Court of Appeal were whether the adjudicator, in rejecting the appellant's claim for liquidated damages, had wrongly applied the prevention principle, and if so, whether this constituted a denial of procedural fairness to the appellant. The court also considered the impact of variations directed by the principal after the date for practical completion and the fact that practical completion was ultimately achieved 114 days late.

The Court of Appeal held that the adjudicator had correctly applied the prevention principle. This principle dictates that a party cannot rely on a breach of contract by the other party to found a claim for damages if the first party's own conduct prevented the other party from performing their obligations. In this instance, the appellant's direction of variations after the date for practical completion was found to have prevented the respondent from achieving practical completion by the stipulated date. Consequently, the appellant was not entitled to claim liquidated damages for the delay. The court found no denial of procedural fairness, as the appellant had been given an opportunity to present its case regarding the liquidated damages claim.

The appeal was dismissed, and the appellant was ordered to pay the costs of the appeal.

Orders

Orders of the court

Appeal dismissed with costs.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.