ABB Australia Pty Ltd v James Engineering Pty Ltd

Link copied
Case Copied 42 min read

CITATION:ABB Australia Pty Ltd v James Engineering Pty Ltd & Anor [2018] NTSC 91

PARTIES:ABB AUSTRALIA PTY LTD

(ABN 68 003 337 611)

v

JAMES ENGINEERING PTY LTD

(ABN 63 101 887 950)

and

TUHTAN, John

TITLE OF COURT:  SUPREME COURT OF THE NORTHERN TERRITORY

JURISDICTION:  SUPREME COURT exercising Territory jurisdiction

FILE NO:45 of 2018 (21822765)

DELIVERED:  21 December 2018

HEARING DATE:  30 November 2018

JUDGMENT OF:  Kelly J

CATCHWORDS:

Contracts (Security of Payments) Act – Whether purported determination of Adjudicator void as a result of jurisdictional error – first defendant applied for adjudication of payment claim – plaintiff ‘s response claimed (inter alia) an entitlement to set-off liquidated damages against any amount owing under the contract – submissions made by both plaintiff and first defendant joining issue on the merits of the plaintiff’s right to apply liquidated damages - Adjudicator declined to determine the merits of the plaintiff’s claimed set-off – Adjudicator held that for a dispute relating to liquidated damages to be adjudicated, there must be a payment dispute with respect to the liquidated damages and a separate application for adjudication – Adjudicator misunderstood the nature of the plaintiff’s defence of set-off - this error caused the Adjudicator to fail to take into account a matter required to be taken into account by s 34(1)(a) namely a substantial part of the plaintiff’s response prepared and served under s 29 – this amounted to a failure to perform a core function under the Act – purported determination not protected from judicial review by s 48(3) – purported determination void - Declaration that the Determination is a nullity – Order in the nature of certiorari setting aside the Determination

Contracts (Security of Payments) Act - Whether purported determination void as a result of failure to accord procedural fairness – Procedural fairness required that the Adjudicator notify the parties of proposed conclusions that were not put forward by the parties and could not be easily anticipated – statutory framework important when considering what procedural fairness requires - the Act provides for informal, summary interim determination within tight time limits and does not finally determine the rights of the parties - The nature of the Adjudicator’s role is such that it is not appropriate to scrutinise the reasoning process with the level of detail entailed in plaintiff’s submissions – Issues complained of “on the table” - No substantial denial of procedural fairness such as would amount to jurisdictional error – Ground dismissed

Application for leave to amend Originating Motion to add ground of review raised for the first time during the hearing – Amendments futile – Leave to amend refused

Construction Contracts Act 2004 (WA) ss 27, 31(2)(b), 32(1)(a), 32(3)(b)

Construction Contracts (Security of Payments) Act 2004 (NT) ss 4, 8, 18, 28, 29, 33(1)(a)&(b), 34(1)(a), 34(3)(b)&(c), 48
Supreme Court Rules o 56

AJ Lucas Operations Pty Ltd v Mac-Attack Equipment Hire Pty Ltd (2009) 25 NTLR 14; [2009] NTCA 4; Alliance Contracting Pty Ltd v James[2014] WASC…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read ABB Australia Pty Ltd v James Engineering Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2018] NTSC 91
Decision Date

CaseChat Overview and Summary

In the case of ABB Australia Pty Ltd v James Engineering Pty Ltd, the dispute arose from a payment claim made under a construction contract. ABB Australia, the subcontractor, claimed payment from James Engineering, the principal contractor. The key issues before the court were whether the adjudicator's determination was void due to a jurisdictional error and a failure to accord procedural fairness. The adjudicator had declined to determine the merits of ABB's right to set off liquidated damages against the amount owing under the contract. The court held that the adjudicator misunderstood the nature of the set-off defence, leading to a failure to take into account a matter required by the Act, which amounted to a jurisdictional error. The adjudicator's error caused the determination to be void.

The court also considered whether the adjudicator's failure to notify the parties of proposed conclusions amounted to a failure to accord procedural fairness. The court found that while procedural fairness was required, the nature of the adjudicator’s role and the statutory framework meant that the reasoning process did not need to be scrutinised in detail. The court concluded that there was no substantial denial of procedural fairness. Consequently, the ground of review regarding procedural fairness was dismissed. Additionally, the court refused leave to amend the originating motion to add a new ground of review raised during the hearing, deeming the amendment futile.

In summary, the court found that the adjudicator's determination was void due to a jurisdictional error and declined to grant relief on the basis of procedural fairness. The court refused the application for leave to amend the originating motion to include a new ground of review.

Background

Background to the litigation

Decision

Reasons for decision

The submissions, which form part of the Adjudication Response, contain extensive submissions headed “Part D: ABB’s claim for liquidated damages” ending:Conclusion36.58For the above reasons, each of JE’s contentions regarding its liquidated damages liability fails. ABB’s set-off should be allowed by the adjudicator. [emphasis added] In his Determination the Adjudicator determined that there was an amount of $1,516,310.40 owing by ABB to James Engineering. The Determination purports to summarise the Payment Schedule on p 10. It states:c) The reasons for withholding payment were:i)The applicant has no contractual entitlement to make the Payment Claim; andii)The contract sum and the variations identified in the payment claim have been previously claimed and previously assessed and paid by the respondent and nothing further is owed to the applicant.d) Attachment A to the payment scheduled stated;“… Note that the final contract sum, within Table A, does not include the Liquidated Damages debt due and payable by James to ABB (refer to the attachments).”e) Attachment A had appended to it a copy of a letter addressed to the applicant and dated 4 August 2017 claiming payment of liquidated damages in the amount of $1,746,160 + GST. The summary did not characterise ABB’s references to liquidated damages as amounting to a set-off. The Adjudicator set out his “REASONS FOR THE DETERMINATION” beginning at p 19. These begin:100)Pursuant to section 34 of the CCA, I have considered the following matters in making this determination:a) the application for adjudication and its attachments;b) the response and its attachments; andc) the further written submissions validly made by the parties.…101)I have considered the claims for variations and the respondent’s claim for liquidated damages separately. The adjudicator dealt with liquidated damages in a separate section beginning on p 62 in the following way.RESPONDENT’S LIQUIDATED DAMAGES295)The respondent has made submissions regarding liquidated damages it considers it is entitled to set-off against money otherwise payable to the applicant (if any).296)The applicant submitted the Payment Claim on 22 December 2017 for $2,129,234.80 incl. GST297)The respondent issued a payment schedule on 11 January 2018 that indicated the respondent proposed to pay $0.00 (nil).298)The payment schedule indicated that the adjusted Contract Price was $15,525,171.95 + GST. The payment further indicated that “ABB agreed backcharges were $69,668.99 + GST”.299)There is no mention of liquidated damages in the amount of $1,746.160.00 being applied in the payment schedule.300)The respondent attached a letter of demand dated 4 August 2017 that it sent to the applicant demanding payment of liquidated damages in the amount of $1,746,160.00 and that letter concluded by stating:“7. ABB further confirms that any other back charges and/or offset amount, due to James acts or omissions, (including any James Punch list items rectification and/or previously detailed Quality issues) are not considered for the purposes of calculating liquidated Damages.…ABB reserves its rights under the Contract and at law in relation to any failure by James to pay the liquidated damages by the 4th September 2017.”301)The respondent never set-off the liquidated damages in relation to which on 4 August 2017 it had notified the application were owing and accordingly, there can be no liquidated damages in dispute for the purposes of this application for adjudication.302)In order for a dispute relating to liquidated damages to be adjudicated, the respondent was required make its claim for liquidated damages by way of the payment schedule and then, if the applicant rejected the respondent’s claim for liquidated damages, either party was entitled to make an application for adjudication in relation to the payment dispute.303)Section 4 of the CCA states;“payment claim means a claim made under a construction contract:(a)by the contractor to the principal for payment of an amount in relation to the performance by the contractor of its obligations under the contract; or (b)by the principal to the contractor for payment of an amount in relation to the performance or non-performance by the contractor of its obligations under the contract.”304)For the avoidance of doubt, a payment claim includes a claim made by the respondent on the applicant.305)Section 8 of the CCA states;A payment dispute arises if:(a)a payment claim has been made under a contract and either:(i)the claim has been rejected or wholly or partly disputed;or(ii)when the amount claimed is due to be paid, the amount has not been paid in full; or(b)when an amount retained by a party under the contract is due to be paid under the contract, the amount has not been paid; or(c)when any security held by a party under the contract is due to be returned under the contract, the security has not been returned.306)In this case if the respondent had applied liquidated damages, then that would be a payment claim for the purposes of the CCA and the respondent would have accrued a right to have the payment disputed adjudicated when the applicant rejected the respondent’s claim.307)If the respondent did not accept the applicant’s rejection of its claim for liquidated damages, under section 28 of the CCA, the respondent had 90 days from the date that the dispute had arisen to make an adjudication application.308)Alternatively, the respondent could have applied the liquidated damages by way of the payment schedule and if the applicant had considered that to give rise to a payment dispute, then the applicant was entitled to make an application for adjudication in relation to the liquidated damages.309)For the above stated reasons, there is no claim for liquidated damages in relation to this application for adjudication and, therefore, there can be no payment dispute in relation to liquidated damages for me to determine.[emphasis in original in each case]

Ratio Decidendi

Legal principle established