Medium Neutral Citation: Grandview Ausbuilder Pty Ltd v Budget Demolitions Pty Ltd [2018] NSWSC 1647 Hearing dates: 24, 25 October 2018; further written submissions ending 29 October 2018. Date of orders: 02 November 2018 Decision date: 02 November 2018 Jurisdiction: Equity - Corporations List Before: Parker J Decision: See [71]
Catchwords: CORPORATIONS – winding up – winding up in insolvency – application to set aside creditor’s statutory demand under Corporations Act 2001 (Cth), s 459H – debt arising under the Building and Construction Industry Security of Payments Act 1999 (NSW) – offsetting claims – offsetting claim for liquidated damages for failure to complete construction contract by individual milestone dates or overall completion date – where builder prevented sub-contractor from completing works by dates specified in the contract – entitlement to recover liquidated damages
CORPORATIONS – winding up – winding up in insolvency – application to set aside creditor’s statutory demand under Corporations Act 2001 (Cth), s 459H – debt arising under the Building and Construction Industry Security of Payments Act 1999 (NSW) – offsetting claims – offsetting claim for cost of completing work – claim foreshadowed in supporting affidavit but not yet accrued at time of s 459H application – not an offsetting claim
CORPORATIONS – winding up – winding up in insolvency – application to set aside creditor’s statutory demand under Corporations Act 2001 (Cth), s 459H – debt arising under the Building and Construction Industry Security of Payments Act 1999 (NSW) – whether conditions should be imposed under Corporations Act 2001 (Cth), s 459M on an order varying the demand – conditions imposed requiring proceedings to be brought and claim amount paid into courtLegislation Cited: Building and Construction Industry Security for Payment Act 1999 (NSW), ss 14, 15
Corporations Act 2001 (Cth), ss 459G, 459H, 459M, 459SCases Cited: 185L6 Pty Ltd v Strata Corporation 07176 Inc [2011] SASC 164
Aldoga Aluminium Pty Ltd v De Silva Starr Pty Ltd [2005] NSWSC 284
Biron Capital Ltd v Velowing Pty Ltd [2003] NSWSC 1181
Broke Hills Estate Pty Ltd v Oakvale Wines Pty Ltd (2005) 23 ACLC 1,266; [2005] NSWSC 638
Diploma Construction (WA) Pty Ltd v KPA Architects Pty Ltd [2014] WASCA 91
Equuscorp Pty Ltd v Perpetual Trustees WA Ltd (1997) (1997) 80 FCR 296; 25 ACSR 675; [1997] FCA 1366
Get'm Pty Ltd v Triulcio [2004] NSWSC 291
Graywinter Properties Pty Ltd v Gas & Fuel Corp Superannuation Fund (1996) 70 FCR 452; [1996] FCA 822
John Shearer Ltd & Arrowcrest Group Pty Ltd v Gehl Company (1995) 60 FCR 136; [1995] FCA 1034
Kerslake Superannuation Pty Ltd v C and L Building Pty Ltd (2010) 4 BFRA 668; [2010] NSWSC 424
Macleay Nominees v Belle Property East Pty Ltd [2001] NSWSC 743
M & D Demir Pty Ltd v Graf Plumbing Pty Ltd [2004] NSWSC 553
Ozone Manufacturing Pty Ltd v Deputy Commissioner of Taxation (2006) 94 SASR 269; [2006] SASC 91
Keep reading for free
Create a free CaseChat account to read Grandview Ausbuilder Pty Ltd v Budget Demolitions Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2018] NSWSC 1647
- Decision Date
CaseChat Overview and Summary
The court was required to determine whether the offsetting claims existed and were valid under the Corporations Act 2001 (Cth). Specifically, it had to consider if the claim for liquidated damages was an existing debt that could be offset against the statutory demand. Additionally, the court had to decide if a claim for the cost of completing the work, which was not yet accrued at the time of the application, could be considered an offsetting claim. The court also had to consider if any conditions should be imposed on an order varying the statutory demand under section 459M of the Corporations Act 2001 (Cth). The court found that the claim for liquidated damages was valid and could be offset against the statutory demand, whereas the claim for the cost of completing the work was not an existing debt and could not be considered an offsetting claim. As a result, the statutory demand was set aside with conditions that required the proceedings to be brought and the claim amount to be paid into court.
In summary, the court held that the statutory demand issued by Budget Demolitions Pty Ltd could be set aside due to the valid offsetting claim for liquidated damages. However, the claim for the cost of completing the work, which was not yet accrued, was not considered an offsetting claim. The court imposed conditions on the order, requiring that the proceedings be brought and the claim amount paid into court. This decision highlights the importance of considering all valid offsetting claims when evaluating statutory demands and the potential imposition of conditions to manage the process.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.