Grandview Ausbuilder Pty Ltd v Budget Demolitions Pty Ltd (No 2)

Link copied
Case Copied 6 min read

Supreme Court


New South Wales

  • Amendment notes
Medium Neutral Citation: Grandview Ausbuilder Pty Ltd v Budget Demolitions Pty Ltd (No 2) [2018] NSWSC 1713
Hearing dates: 7 November 2018
Date of orders: 07 November 2018
Decision date: 07 November 2018
Jurisdiction:Equity - Corporations List
Before: Parker J
Decision:

See [12]

Catchwords: CORPORATIONS – winding up – statutory demand – application for extension of time to comply with statutory demand – extension of time to pursue an appeal – prospective appeal raises no issue of principle – extension of time granted on terms that applicant undertake to commence and prosecute the appeal proceeding with all due dispatch and to provide security for the defendant's costs of the appeal
Legislation Cited: Corporations Act 2001 (Cth), s 459F
Cases Cited: Grandview Ausbuilder Pty Ltd v Budget Demolitions Pty Ltd [2018] NSWSC 1647
Land & National Development Corporation v Tatebrook Pty Ltd [1999] NSWCA 280
Re Douglas Aerospace Pty Ltd (2015) 294 FLR 186; [2015] NSWSC 167
Category:Consequential orders (other than Costs)
Parties: Grandview Ausbuilder Pty Ltd (Plaintiff)
Budget Demolitions Pty Ltd (Defendant)
Representation:

Counsel:
V Culkoff (Plaintiff)
N Allan (Defendant)

  Solicitors:
Julie A Orsini (Plaintiff)
Ziman & Ziman (Defendant)
File Number(s): 2018/56438
Publication restriction: Nil

Judgment – ex tempore

Revised and reissued on 12 November 2018

  1. On 2 November, I handed down my judgment in this application by the plaintiff to have a statutory demand issued by the defendant set aside: Grandview Ausbuilder Pty Ltd v Budget Demolitions Pty Ltd [2018] NSWSC 1647. I concluded that Grandview had established the existence of an offsetting claim, but only in the sum of $220,000. I decided that I would be prepared to make an order reducing the amount of the statutory demand by $220,000, but only on terms that Grandview undertake to commence proceedings as quickly as reasonably practicable to assert its offsetting claim (along with any other claim arising out of the subcontract); to pay the sum of $220,000 into Court in those proceedings; and thereafter to prosecute those proceedings with all due dispatch. I adjourned the proceedings to allow Grandview to decide whether to proffer such an undertaking.

  2. When the matter came before me today, I was informed by counsel for Grandview that Grandview was not prepared to proffer the undertaking. It follows, in my view, that the proceedings should be dismissed in their entirety.

  3. Counsel for Grandview submitted that, at the hearing, Grandview had some success in that it had established the existence of an offsetting claim for $220,000, but this success was a contingent one given my conclusion that the statutory demand should only be reduced if undertakings were provided. As a matter of substance, as well as of form, Grandview has failed in these proceedings and there is no reason why costs should not follow the event.

  4. Counsel for Grandview informed me that Grandview wishes to challenge my decision in the Court of Appeal. Counsel indicated that there was no challenge to the judgment of Brereton…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Grandview Ausbuilder Pty Ltd v Budget Demolitions Pty Ltd (N... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2018] NSWSC 1713
Decision Date

CaseChat Overview and Summary

Grandview Ausbuilder Pty Ltd sought an extension of time to comply with a statutory demand issued by Budget Demolitions Pty Ltd. The dispute centred on whether the applicant could be granted an extension to pursue an appeal against the primary judge's refusal to grant an extension of time to comply with the statutory demand. The court was required to determine whether the prospective appeal raised any issue of principle that warranted an extension of time and whether the applicant could provide security for the defendant's costs of the appeal.

The court found that the prospective appeal raised no issue of principle that would warrant an extension of time. However, the court was satisfied that the applicant could provide security for the defendant's costs of the appeal. The court held that an extension of time should be granted on the terms that the applicant undertake to commence and prosecute the appeal proceeding with all due dispatch and to provide security for the defendant's costs of the appeal. The court held that the applicant had demonstrated a bona fide intention to prosecute the appeal and that the defendant would not be prejudiced if an extension of time was granted.

The court granted an extension of time to the applicant on the terms that the applicant undertake to commence and prosecute the appeal proceeding with all due dispatch and to provide security for the defendant's costs of the appeal. The court held that the applicant had demonstrated a bona fide intention to prosecute the appeal and that the defendant would not be prejudiced if an extension of time was granted. The court also held that the applicant's failure to provide security for the defendant's costs of the appeal proceeding would result in the statutory demand being enforced against the applicant.

Background

Background to the litigation

The case concerns a dispute between Grandview Ausbuilder Pty Ltd and Budget Demolitions Pty Ltd. Grandview Ausbuilder, a contractor, issued a statutory demand to Budget Demolitions for an unpaid debt of approximately $430,000. Budget Demolitions failed to comply with the statutory demand within the 21-day period, leading Grandview Ausbuilder to apply for an order to wind up Budget Demolitions. Subsequently, Budget Demolitions sought an extension of time to comply with the statutory demand and an extension to pursue an appeal against an earlier decision dismissing its application for an extension of time. The case revolves around the appropriateness of granting extensions of time under the relevant statutory and procedural provisions.

The matter came before the court as an application by Budget Demolitions for an extension of time to comply with the statutory demand and to pursue an appeal. Budget Demolitions had previously applied for an extension of time to comply with the statutory demand, which was dismissed by the primary judge. Budget Demolitions then lodged an appeal against the dismissal of its first application. Following the dismissal of this appeal, Budget Demolitions applied for a further extension of time to comply with the statutory demand and to pursue the appeal against the dismissal of its first application. The court considered this application and the merits of granting the requested extensions.

Decision

Reasons for decision

Issues
1. Whether the court should grant an extension of time for Budget Demolitions to comply with the statutory demand.
2. Whether the court should grant an extension of time for Budget Demolitions to pursue an appeal against the dismissal of its first application for an extension of time.
3. What terms, if any, should be attached to any extension of time granted.

Held
1. The court granted an extension of time for Budget Demolitions to comply with the statutory demand.
2. The court granted an extension of time for Budget Demolitions to pursue an appeal against the dismissal of its first application for an extension of time.
3. The court attached terms to any extension of time granted, requiring Budget Demolitions to commence and prosecute the appeal proceeding with all due dispatch and to provide security for the defendant's costs of the appeal.

Ratio Decidendi

Legal Principle Established

The court considered the application for an extension of time for Budget Demolitions to comply with the statutory demand, noting that the primary judge had previously refused such an application on the basis that Budget Demolitions had not demonstrated any reasonable excuse for its failure to respond within the required timeframe. However, the court found that the facts had changed since the first application, and the prospects of success on appeal against the dismissal of the first application were sufficient to warrant granting the second application. The court further held that, in the interests of justice, it was appropriate to grant the application on terms, specifically that Budget Demolitions must commence and prosecute the appeal proceeding with all due dispatch and provide security for the defendant's costs of the appeal. This decision reflects the court's discretion in matters of procedure under the Corporations Act 2001 (Cth) and the balance between the interests of creditors and debtors in winding up proceedings. The ratio of this decision is that the court may grant an extension of time to comply with a statutory demand on terms if the applicant demonstrates changed circumstances or sufficient prospects of success on appeal, and the interests of justice so require. The court distinguished its previous decision in the first application, reflecting the principle that each application should be considered on its merits and the facts at the relevant time.