CITATION: Land & National Development Corporation v Tatebrook Pty Ltd [1999] NSWCA 280
FILE NUMBER(S): CA 40539/99
HEARING DATE(S): 26/07/99
JUDGMENT DATE:
2 August 1999

PARTIES :


Land & National Development Corporation v Tatebrook Pty Ltd
JUDGMENT OF: Fitzgerald JA at 1
LOWER COURT JURISDICTION: Supreme Court
LOWER COURT FILE NUMBER(S) :
LOWER COURT JUDICIAL OFFICER: Santow J
COUNSEL: D J Fagan SC (Applicant)
S M P Reeves (Respondent))
SOLICITORS: Rod J Barnett & Associates (Applicant)
Mallesons Stephen Jaques
CATCHWORDS:
DECISION: Orders made
THE SUPREME COURT
OF NEW SOUTH WALES
COURT OF APPEAL
                                CA40539/99

                                FITZGERALD JA

                                Monday, 2 August 1999

LAND & NATIONAL DEVELOPMENT CORPORATION PTY LTD v TATEBROOK PTY LTD

JUDGMENT

1   FITZGERALD JA: On 19 January 1999, the respondent served a demand under subs 459E(1) of the Corporations Law of NSW (the “Law”) on the applicant. Within the time limited by subs 459G(2) of the Law, the applicant applied to the Court under subs 459G(1) for an order setting aside the demand. As a result, the time for compliance with the demand was extended by subs 459F(2)(a) until the application “… is finally determined or otherwise disposed of …”. The present application for an order further extending the time for compliance with the demand was conducted on the basis that that has occurred. 2 Pursuant to subs 459F(2)(a)(i) of the Law, the Court has made orders from time to time extending the time for compliance with the demand. Before me, it was common ground that the time for compliance has been extended in that manner until 28 July 1999. The order extending the time for compliance until then was made by Santow J on 6 July 1999. At the hearing of the present application, despite the respondent’s submissions that, as a Judge of Appeal, I have no power to make such an order, I extended the time for compliance with the demand until the delivery of this judgment. 3 I do not propose to delay on the question raised by the respondent concerning a Judge of Appeal’s powers. The applicant has filed a notice of appeal but needs leave to appeal. I gave the applicant leave to file an application for leave to appeal at the hearing of this application. The respondent did not dispute that there is therefore a proceeding in this Court. However, it was submitted that my only relevant power to extend the time for compliance with the demand under subs 459E(1) of the Law is to be found in subs 46(2)(b) of the Supreme Court Act 1970, and that an order extending the time for compliance with the demand is outside the ambit of that subsection. I do not agree. In any event, under subs 31(3) of the Supreme Court Act, a Judge of Appeal “… may from time to time sit as or exercise any of the powers of a Judge” of the Supreme Court. The respondent conceded that a Judge of one of the other Divisions of the Court has power…
CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Land and National Development Corporation v Tatebrook Pty Lt... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[1999] NSWCA 280
Decision Date

CaseChat Overview and Summary

The Land and National Development Corporation (the appellant) appealed to the Supreme Court of New South Wales, Court of Appeal, against a decision of the Land and Environment Court. The dispute concerned the appellant's refusal to grant a development consent to Tatebrook Pty Ltd (the respondent) for the construction of a residential development.

The primary legal issue before the Court of Appeal was whether the Land and Environment Court had erred in its interpretation and application of the relevant planning instruments, specifically the Cumberland Local Environmental Plan 1991 (CLEP 1991) and the Cumberland Development Control Plan 1991 (CDCP 1991), in relation to the respondent's development application. The Court was required to determine if the Land and Environment Court had correctly assessed the proposal against the objectives and provisions of these planning instruments.

Fitzgerald JA, delivering the judgment of the Court, found that the Land and Environment Court had made an error in its assessment of the development application. The Court held that the Land and Environment Court had failed to give sufficient weight to certain provisions of the CLEP 1991 and had misconstrued the intent of the CDCP 1991 in relation to the proposed development. The principles applied involved the proper construction of planning instruments and the assessment of development proposals against established planning controls.

The appeal was allowed, and the orders of the Land and Environment Court were set aside.

Orders

Orders of the court

Orders made

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established