District Court
New South Wales
Medium Neutral Citation: XJS World Pty Ltd v Central West Civil Pty Ltd [2024] NSWDC 465 Hearing dates: 26 June and 5 September 2024 Date of orders: 9 October 2024 Decision date: 09 October 2024 Jurisdiction: Civil Before: Weber SC DCJ Decision: See Orders
Catchwords: CONTRACT – Breaches of Contract – Building Contract - Contract Repudiation – Variations - Unpaid Invoices
Legislation Cited: Civil Procedure Act 2005 (NSW)
Evidence Act 1995 (NSW)
Cases Cited: Carbone v Fowler Homes Pty Ltd [2024] NSWCA 192
Commercial Union Assurance Co of Australia Ltd v Ferrcom Pty Ltd (1991) 22 NSWLR 389
Curnow Consulting Pty Ltd v JPD Media and Design Pty Ltd T/A Durie Design [2017] NSWSC 1171
Liebe v Molloy (1906) 4 CLR 347
McDonald v Dennys Lascelles Ltd (1933) 48 CLR 457
Probuild Constructions (Aust) Pty Ltd v DDI Group Pty Ltd (2017) 95 NSWLR 82
Update Constructions Pty Ltd v Rozelle Child Care Centre Ltd (1989) 20 NSWLR 251
Texts Cited: Nil
Category: Principal judgment Parties: Plaintiff: XJS World Pty Ltd
Defendant: Central West Civil Pty LtdRepresentation: Counsel:
Solicitors:
Plaintiff: Mr P A Horobin
Defendant: Mr J Young
Plaintiff: Hugh & Associates - Lawyers
Defendant: Blackwell Short
File Number(s): 2023/123947 Publication restriction: None
JUDGMENT
Introduction
-
These proceedings concern a property development in Bathurst. The plaintiff is the developer, the defendant is a civil engineering works contractor, which was engaged by the plaintiff.
-
The contract sued upon was entered into on 15 April 2021 and consists of the following (the references to the numbers in the parentheses are references to Exhibit PX 1):
Part A- Contract Schedule (pp. 143 – 144).
Part B - Contract Conditions (pp. 145 – 146)
Part C -All Civil Works as per Design Plans by Calare Civil and stamped acceptable for Construction Certificate in relation to the 10 Lot Residential at 38 Gilmour Street Kelso. Pursuant to Calare Civil Job No: 2015.0309 and comprising GO1,02,03. EW01,02,03,04. R01,02,03,04. C01. SW01,02. SO1 (pp. 95 – 109)
Part D - Schedule of Rates submitted by the defendant for the civil construction works to be undertaken to Bathurst Regional Council's Specifications and requirements to achieve a Subdivision Certificate for the Subdivision (pp. 147 – 150)
Part E - Bathurst Council DA 2015/0171 (pp. 151 – 171)
Part F -Electrical Design drawing EDS67212 (pp.110 – 112)
-
Calare Civil was the Civil Engineer engaged by the Plaintiff.
-
The substance of the work to be carried out by the Defendant was specified in clause 3 of the Contract Schedule (the works) (PX1 p143):
Undertake the Civil Construction works for proposed 10 Lot Subdivision at 38 Gilmour Street Kelso as per Calare Civil Plans stamped for a Construction Certificate on 22nd January 2021. All Works undertaken are to Conform to Bathurst Regional Council's Subdivision Civil Construction Specifications. All works are also to ensure compliance with specifications and terms of DA 2015/0171.
-
In summary, the Plaintiff alleges that the defendant breached the contract by failing to:
carry…
Keep reading for free
Create a free CaseChat account to read XJS World Pty Ltd v Central West Civil Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2024] NSWDC 465
- Decision Date
CaseChat Overview and Summary
The primary legal issues were whether the defendant had repudiated the contract, whether there were variations that were not compensated, and whether the unpaid invoices were valid and enforceable. The court needed to determine if the plaintiff had a valid cause of action for the defendant's alleged breaches.
The court found that the defendant had indeed repudiated the contract by failing to complete the work as per the agreement. There were variations that were not adequately compensated, and the unpaid invoices were valid. The court held that the plaintiff was entitled to recover the costs associated with the breaches. The defendant's arguments for set-off and mitigation were rejected as they did not sufficiently address the primary issues of contract repudiation and unpaid work.
The court ordered Central West Civil Pty Ltd to pay XJS World Pty Ltd the sum of $[amount] for the unpaid invoices and an additional sum for the variations that were not compensated. The defendant was also ordered to pay interest on the unpaid amounts and the plaintiff's costs of the proceeding.
Orders
Orders of the court
See Orders