Supreme Court
New South Wales
Medium Neutral Citation: H & M Constructions (NSW) Pty Ltd v Golden Rain Development Pty Ltd (No 4) [2023] NSWSC 925 Hearing dates: 24 – 27 July and 2 August 2023 Date of orders: 09 August 2023 Decision date: 09 August 2023 Jurisdiction: Equity - Technology and Construction List Before: Stevenson J Decision: Plaintiff builder’s case fails; defendant developer entitled to liquidated damages and access to security provided in accordance with the contract
Catchwords: BUILDING AND CONSTRUCTION – design and construct contract – practical completion – superintendent to issue certificate of practical completion or give reasons for not doing so – superintendent issued “conditional” certificate of practical completion – purported retrospective date of practical completion on satisfaction by builder of specified conditions – contractual status of conditional certificate – whether Court can in any event determine when practical completion took place
CONTRACTS – “prevention principle” – whether developer took over builder’s obligations and prevented builder from performing those obligations
ESTOPPEL – whether developer induced builder to understand that effect of conditional certificate was to fix time for determination of liquidated damages and delay costs
UNCONSCIONABLE CONDUCT – whether developer engaged in unconscionable conduct
Legislation Cited: Australian Securities and Investments Commission Act 2001 (Cth)
Competition and Consumer Act 2010 (Cth), Sch 2 – Australian Consumer Law
Environmental Planning and Assessment Act 1979 (NSW)
Cases Cited: Abergeldie Contractors Pty Ltd v Fairfield City Council [2017] NSWCA 113
Australian Securities and Investments Commission v Kobelt (2019) 267 CLR 1; [2019] HCA 18
Australian Securities and Investments Commission v Westpac Banking Corporation (Omnibus) [2022] FCA 515
Good Living Company Pty Ltd as trustee for the Warren Duncan Trust No 3 v Kingsmede Pty Ltd (2021) 284 FCR 424; [2021] FCAFC 33
Parkview Constructions Pty Ltd v Futuroscop Enterprises Pty Ltd [2023] NSWSC 178
Probuild Constructions (Aust) Pty Ltd v DDI Group Pty Ltd (2017) 95 NSWLR 82; [2017] NSWCA 151
Spiers Earthworks Pty Ltd v Landtec Projects Corporation Pty Ltd (No 2) [2012] WASCA 53
Waltons Stores (Interstate) Limited v Maher (1988) 164 CLR 387; [1988] HCA 7
Category: Principal judgment Parties: H & M Constructions (NSW) Pty Ltd (Plaintiff/Cross-Defendant)
Golden Rain Development Pty Ltd (Defendant/Cross-Claimant)Representation: Counsel:
Solicitors:
N Simpson with S T Hanscomb (Plaintiff/Cross-Defendant)
N J Kidd SC with J Dooley (Defendant/Cross-Claimant)
Pinsent Masons (Plaintiff/Cross-Defendant)
Allens (Defendant/Cross-Claimant)
File Number(s): 2021/115569
JUDGMENT
-
On 20 October 2015 the plaintiff, H & M Constructions (NSW) Pty Ltd (“the Builder”), entered into a design and construct contract (“the Contract”) with the defendant, Golden Rain Development Pty Ltd (“the Developer”) to design and construct 109 high rise apartments known as the Sugarcube Apartments (“the Apartments”), eight terraces known as the Honeycomb Terraces (“the Terraces”) and various public domain roads (“the Dedicated Public Roads”) on a former industrial site in Erskineville. [1]
1. The Contract enabled the Superintendent, Urban Pty Ltd, to specify "separable portions" of the works. In June 2017, the Superintendent directed that the Apartments and all…
Keep reading for free
Create a free CaseChat account to read H & M Constructions (NSW) Pty Ltd v Golden Rain Development... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2023] NSWSC 925
- Decision Date
CaseChat Overview and Summary
The court had to determine whether the conditional certificate was a valid form of practical completion under the contract, and if the court could ascertain the actual date of practical completion. Additionally, the court examined whether Golden Rain had taken over the builder's obligations, thus preventing H & M from completing the project. Another point of contention was whether Golden Rain had induced H & M to believe that the conditional certificate fixed the time for determining liquidated damages and delay costs. Furthermore, H & M alleged that Golden Rain engaged in unconscionable conduct.
The court concluded that the conditional certificate did not legally constitute practical completion. It also held that Golden Rain did not prevent H & M from performing their obligations, as the developer had not taken over the builder's duties. The court found no evidence that Golden Rain induced H & M to accept the conditional certificate as a definitive completion date. Finally, the court ruled that Golden Rain did not engage in unconscionable conduct. As a result, H & M's claims were dismissed, and the court declined to determine the date of practical completion.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.