Parkview Constructions Pty Ltd v Futuroscop Enterprises Pty Ltd

Link copied
Case Copied 74 min read

Supreme Court


New South Wales

  • Amendment notes
Medium Neutral Citation: Parkview Constructions Pty Ltd v Futuroscop Enterprises Pty Ltd [2023] NSWSC 178
Hearing dates: 29 August 2022, 1, 5, 6, 8, 15 September 2022; last submissions 14 November 2022.
Date of orders: 2 March 2023
Decision date: 02 March 2023
Jurisdiction:Equity - Commercial List
Before: Rees J
Decision:

Plaintiff entitled to damages and return of bank guarantee. Defendant entitled to liquidated damages and rectification costs. Parties to bring in short minutes.

Catchwords:

BUILDING AND CONSTRUCTION — design and construct contract AS4902-2000 — contractor to construct two buildings — airport hotel and long stay carpark — to be completed in September 2017 —principal wishes to use hotel rooftop for tenants — development consent does not approve this use — hotel and carpark tenants commence operations in September 2017 – occupation certificate limits use of rooftop terrace to maintenance only – principal maintains practical completion yet to be achieved.

PRACTICAL COMPLETION — superintendent to issue certificate of practical completion — ‘conditional’ certificates issued for each building — retrospective date of practical completion on satisfaction of conditions — whether ‘conditional’ certificates comprise a certificate of practical completion — case law review at [205]-[209] — whether can give a retrospective date at [212]-[213] — ‘conditional’ certificates have no contractual force.

DETERMINATION BY COURT— whether Court can determine date of practical completion — consideration of Abergeldie Contractors v Fairfield City Council — does not depend on Superintendent having been “manifestly unreasonable” – contractual standard is ‘reasonable’ — whether Court can determine liquidated damages.

LIQUIDATED DAMAGES — superintendent’s certificate did not comply with the contract — whether Court can ascertain liquidated damages — liquidated damages calculated using objective criterion — Court can determine correct sum.

DAMAGES — contractual regime for notifying and remedying defects — whether contract ousts common law damages — caselaw review at [248]-[253] — contract created exhaustive code governing parties’ rights regarding defects — common law damages not available — contractual regime not followed — unnotified defects apparent on reasonable inspection — not entitled to costs of rectification for such defects.

BUILDING AND CONSTRUCTION — security — contractor substitutes cash retention for bank guarantee — whether principal entitled to retain GST on cash retention until bank guarantee returned —GST payable on release of retention.

Legislation Cited:

Environmental Planning & Assessment Act 1979 (NSW) ss 4.2, 4.3

A New Tax System (Goods and Services Tax) Act 1999 (Cth) ss 9-10, 40-5, 99-1

A New Tax System (Goods and Services Tax) Regulations 2019 (Cth) reg 40-5.09(3)

Cases Cited:

Abergeldie Contractors Pty Ltd v Fairfield City Council [2017] NSWCA 113

Administration of Papua and New Guinea v Daera Guba (1973) 130 CLR 353

Agricultural & Rural Finance Pty Ltd v Gardiner (2008) 238 CLR 570; [2008] HCA 57

Australian Broadcasting Commission v Australasian Performing Right Assn Ltd (1973) 129 CLR 99; [1973] HCA 36

Bedrock Construction and Development Pty Ltd v Crea [2021] SASCA 66

Bellgrove v Eldridge (1954) 90 CLR 613;

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Parkview Constructions Pty Ltd v Futuroscop Enterprises Pty... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2023] NSWSC 178
Decision Date

CaseChat Overview and Summary

Parkview Constructions Pty Ltd sued Futuroscop Enterprises Pty Ltd over a design and construct contract for an airport hotel and long-stay carpark. The contract, governed by AS4902-2000, stipulated completion by September 2017. Although the hotel and carpark commenced operations in September 2017, the occupation certificate limited the rooftop terrace's use to maintenance. The principal argued that practical completion had not yet been achieved. The contractor issued 'conditional' certificates of practical completion, with retrospective dates upon satisfying the conditions. The court determined these certificates had no contractual force.

The legal issues included whether the court could determine the date of practical completion, considering case law on the matter, and if it could ascertain liquidated damages. The court examined whether the contractual standard required the superintendent to be "manifestly unreasonable" or simply "reasonable." It found that the court could determine the date of practical completion without requiring manifest unreasonableness. Regarding liquidated damages, the court held it could ascertain the correct sum using an objective criterion. It also considered the contractual regime for notifying and remedying defects, finding that the contract created an exhaustive code governing the parties' rights regarding defects, and common law damages were not available if the contractual regime was not followed.

The court ruled that the principal was not entitled to retain GST on the cash retention until the bank guarantee was returned, with GST payable upon the release of the retention. It found that the contract created an exhaustive code governing the parties' rights regarding defects, and common law damages were not available if the contractual regime was not followed. For unnotified defects apparent on reasonable inspection, the contractor was not entitled to costs of rectification.

The court's final orders included a determination on the date of practical completion, an ascertainment of liquidated damages, and a clarification on the entitlement to costs of rectification for unnotified defects. The principal was also instructed on the GST implications of cash retention versus bank guarantees.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.