| IN THE SUPREME COURT OF VICTORIA | Not Restricted |
AT MELBOURNE
COMMERCIAL COURT
TECHNOLOGY, ENGINEERING AND CONSTRUCTION LIST
S ECI 2019 05920
| HACER GROUP PTY LTD (ACN 091 032 530) | Plaintiff |
| v | |
| EURO FAÇADE TECH EXPORT SDN BHD (Malaysian Company Number 1001662-H) | Defendant |
---
JUDGE: | Stynes J |
WHERE HELD: | Melbourne |
DATE OF HEARING: | 7 December 2021 and 9 March 2022 |
DATE OF JUDGMENT: | 30 June 2022 |
CASE MAY BE CITED AS: | Hacer Group Pty Ltd v Euro Façade Tech Export Sdn Bhd |
MEDIUM NEUTRAL CITATION: | [2022] VSC 373 |
---
DAMAGES — Defective work – Rectification without notice to contractor — Delay — Liquidated damages — Undefended proceedings — AA Shi Pty Ltd v Avbar Pty Ltd (No 5) [2010] FCA 971, applied — United Group Resources Pty Ltd v Calabro (No 5) [2011] FCA 1408, applied — Owners Corporation No.1 of PS613436T v LU Simon Builders Pty Ltd (Building and Property) [2019] VCAT 286, applied — Owners-Strata Plan No 76674 v Di Blasio Constructing Pty Ltd [2014] NSWSC 1067, applied — Turner Corporation Ltd v Austotel Pty Ltd (1994) 13 BCL 378, distinguished — J-Corp Pty Ltd v Mladenis [2009] WASCA 157, applied.
---
APPEARANCES: | Counsel | Solicitors |
| For the Plaintiff | Lachlan Currie | KCL Law |
| For the Defendant | None | None |
HER HONOUR:
A Introduction
The plaintiff, Hacer Group Pty Ltd (Hacer), is a commercial builder that was engaged to design and construct the apartment complex known as ‘Ivanhoe Apartments’ at 443 Upper Heidelberg Road, Heidelberg Heights in the State of Victoria (Project).
The Project is a substantial residential complex comprising 14 storeys, 198 apartments, four retail spaces, one office space and a 297 space underground car park.
The exterior façade of the Project principally consists of an aluminium glazed curtain wall system comprising an aluminium frame into which prefabricated glazed panels are affixed.
Under a subcontract executed on 18 May 2017, Hacer engaged the defendant, Euro Façade Tech Export Sdn Bhd (EFT), to design, engineer, procure, manufacture, fabricate and supply the façade system for the Project (Subcontract).
Hacer claims that the works performed by EFT were defective in breach of the Subcontract. The alleged defects fall into two categories as either design defects or manufacturing defects. Hacer’s claim is made pursuant to a contractual indemnity provided under the Subcontract. In short, Hacer asserts that where EFT failed to remedy any breach of the Subcontract, Hacer was entitled to take steps to remedy the breach, and all costs Hacer incurred in doing so are recoverable from EFT as a debt due to Hacer. Hacer claims it is entitled to recover rectification costs in the sum of $2,486,603.[1] In the alternative, Hacer claims the same sum as damages for EFT’s breaches of the Subcontract.
[1]Second further amended statement of claim [29] (2nd FASOC). All figures are exclusive of GST unless stated otherwise.
Hacer also claims liquidated damages under the Subcontract in the sum of $589,500.[2] In the alternative,…
Keep reading for free
Create a free CaseChat account to read Hacer Group Pty Ltd v Euro Façade Tech Export Sdn Bhd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2022] VSC 373
- Decision Date
CaseChat Overview and Summary
The court needed to determine whether the plaintiff could recover damages for the defective work, the costs of rectifying the defects without notice to the contractor, the delays caused by the defective work, and the liquidated damages. The court also needed to decide whether the liquidated damages clause was enforceable. The court considered several cases in determining these issues, including AA Shi Pty Ltd v Avbar Pty Ltd, United Group Resources Pty Ltd v Calabro, Owners Corporation No.1 of PS613436T v LU Simon Builders Pty Ltd, Owners-Strata Plan No 76674 v Di Blasio Constructing Pty Ltd, Turner Corporation Ltd v Austotel Pty Ltd, J-Corp Pty Ltd v Mladenis, and others.
The court found that the plaintiff could recover damages for the defective work, the costs of rectifying the defects without notice to the contractor, and the delays caused by the defective work. However, the court held that the liquidated damages clause was unenforceable as it was a penalty clause. The court awarded the plaintiff damages for the defective work, the costs of rectifying the defects without notice to the contractor, and the delays caused by the defective work. The court did not award liquidated damages to the plaintiff.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.