Medium Neutral Citation: The Owners - Strata Plan No 76674 v Di Blasio Constructions Pty Ltd [2014] NSWSC 1067 Hearing dates: 28 and 29 July 2014 Decision date: 11 August 2014 Before: Ball J Decision: Judgment for the plaintiff in the sum of $481,405.61
Catchwords: BUILDING AND CONSTRUCTION - breach of statutory warranties in the Home Building Act 1989 (NSW), s 18B - reasonableness of owner's conduct after breach by builder - duty to mitigate - where builder refused to rectify defects - where owner lost confidence in builder - whether owner reasonable in rejecting later offer by builder to rectify defects - availability of damages for cost of rectification work Legislation Cited: Building Code of Australia
Home Building Act 1989 (NSW), s 18BCases Cited: Bellgrove v Eldridge [1954] HCA 36; (1954) 90 CLR 613
Bitannia Pty Ltd v Parkline Constructions Pty Ltd [2009] NSWSC 1302; (2010) 26 BCL 335
Burns v MAN Automotive (Aust) Pty Ltd [1986] HCA 81; (1986) 161 CLR 653
Cassidy v Engwirda Construction Co (No 2) [1968] Qd R 159
Cassidy v Engwirda Construction Co (No 2) [1968] QWN 47 (HC); (1968) 42 ALJR 168
Eribo v Odinaiya [2010] EWHC 301 (TCC)
Hasell v Bagot, Shakes & Lewis Ltd [1911] HCA 62(1911) 13 CLR 374
Karacominakis v Big Country Developments Pty Ltd [2000] NSWCA 313
Radford v de Froberville [1978] 1 All ER 33; [1977] 1 WLR 1262
TC Industrial Plant Pty Ltd v Robert's Queensland Pty Ltd [1963] HCA 57; (1963) 180 CLR 130
TCN Channel 9 Pty Ltd v Hayden Enterprises Pty Ltd (1989) 16 NSWLR 130Texts Cited: A Chambers, Hudson's Building and Engineering Contracts, (12th ed, 2010, Sweet & Maxwell)
J Bailey, Construction Law, (Vol II, 2011, Informa Law)
J Carter, E Peden and GJ Tolhurst, Contract Law in Australia, (5th ed, 2007, LexisNexis)Category: Principal judgment Parties: The Owners - Strata Plan No 76674 (Plaintiff)
Di Blasio Constructions Pty Ltd (ACN 082 737 559) (Defendant)Representation: Counsel:
D Hand (Plaintiff)
M Pesman SC (Defendant)
Solicitors:
Makinson D'Apice (Plaintiff)
Jane Crittenden (Defendant)
File Number(s): 2012/119976 Publication restriction: Nil
Judgment
Introduction
In these proceedings, the plaintiff (the Owners Corporation), which is the owners corporation in respect of a strata development consisting of a three storey building comprising 9 residential units and an underground carpark and storage area in Dalley Street, Queenscliff, sues the builder of the building, Di Blasio Constructions Pty Ltd (the Builder), for breaches of the warranties implied by s 18B of the Home Building Act 1989 (NSW) (the Act).
The Builder filed a cross-claim against a subcontractor who was responsible for installing the roof of the building. However, that cross-claim was settled on the first day of the hearing.
It is not disputed that the construction of the building involved "residential building work" within the meaning of the Act and that there were defects in that work with the result that the Builder was…
Keep reading for free
Create a free CaseChat account to read The Owners - Strata Plan No 76674 v Di Blasio Constructions... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2014] NSWSC 1067
- Decision Date
CaseChat Overview and Summary
The key issues for the court to decide were whether the Owners Corporation was reasonable in rejecting the Builder's offer to rectify the defects, and if so, whether the Owners Corporation was entitled to damages for the cost of rectifying the defects. The Builder submitted that the Owners Corporation had failed to mitigate its loss by engaging the Builder to perform the necessary rectification work. It said that it offered to enter into a building contract to perform that work for $1, the Owners Corporation had acted unreasonably by refusing that offer and that, in circumstances where the Builder was ready, willing and able to enter into that contract, the proceedings should be dismissed. Alternatively, the Builder submitted that the Owners Corporation should recover no more than the amount it would have cost the Builder to perform the rectification work.
The court held that the Owners Corporation was not unreasonable in rejecting the Builder's offer to rectify the defects. The court noted that the Owners Corporation had lost confidence in the Builder and was entitled to do so. The court held that the Owners Corporation was entitled to damages for the cost of rectifying the defects. The court rejected the Builder's submission that the Owners Corporation was required to engage the Builder to perform the necessary rectification work because the Owner's Corporation was not obliged to engage the Builder to perform the necessary rectification work. The court found that the Owner's Corporation was entitled to damages for the cost of rectifying the defects.
The court ordered that the Builder pay the Owners Corporation $151,375 for the cost of rectifying the defects, $116,108.65 for the cost of rectifying defects with the roof and guttering, and $12,144 for the cost of rectifying the fire safety defect. The court further ordered that the Builder pay interest on those amounts.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
In these proceedings, the plaintiff (the Owners Corporation), which is the owners corporation in respect of a strata development consisting of a three storey building comprising 9 residential units and an underground carpark and storage area in Dalley Street, Queenscliff, sues the builder of the building, Di Blasio Constructions Pty Ltd (the Builder), for breaches of the warranties implied by s 18B of the Home Building Act 1989 (NSW) (the Act). The Builder filed a cross-claim against a subcontractor who was responsible for installing the roof of the building. However, that cross-claim was settled on the first day of the hearing. It is not disputed that the construction of the building involved "residential building work" within the meaning of the Act and that there were defects in that work with the result that the Builder was in breach of the statutory warranties implied by s 18B. The defects fall into three categories. First, there are defects in the roof and guttering. Second, there is a particular fire safety defect. Third, there are a number of other defects, the most significant of which concern waterproofing of bathrooms and exterior planter boxes. It is now agreed that the trade costs of rectifying the fire safety defect is $12,144. The Owners Corporation and the Builder each obtained expert reports concerning the scope of the work required to rectify the other defects (apart from the roof), and they appointed an expert quantity surveyor, Mr Madden, to cost that work. Although the experts agreed on much of the work that needed to be done, there were some differences. According to Mr Madden, the trade costs associated with the work that the Owners Corporation's expert said needed to be done are $179,343, and the trade costs of the work that the Builder's expert said needed to be done are $123,406. On the first day of the hearing, the Owners Corporation and the Builder sensibly agreed to split the difference between the two estimates and agreed that the trade costs of the work are $151,375. The Owners Corporation's expert, Mr Mo'ane of Integrated Building Consultancy Norwest, also estimated that the costs of rectifying defects with the roof and guttering were $116,108.65. Two issues remain. First, the Builder takes issue with some of the preliminaries and on costs allowed for by Mr Madden, and it submits that there has been some duplication between preliminaries allowed for in respect of the roofing work and preliminaries allowed for in respect of other work. It also claims that other components allowed for in the estimate of the costs of rectifying defects with the roof are excessive. Secondly, and more significantly, the Builder says that the Owners Corporation has failed to mitigate its loss by engaging the Builder to perform the necessary rectification work. It says that it offered to enter into a building contract to perform that work for $1, that the Owners Corporation has acted unreasonably by refusing that offer and that, in circumstances where the Builder was ready, willing and able to enter into that contract, the proceedings should be dismissed. Alternatively, the Builder submits that the Owners Corporation should recover no more than the amount it would have cost the Builder to perform the rectification work.