SUPREME COURT OF SOUTH AUSTRALIA
(Court of Appeal: Civil)
BEDROCK CONSTRUCTION AND DEVELOPMENT PTY LTD v CREA
[2021] SASCA 66
Judgment of the Court of Appeal
(The Honourable Justice Doyle, the Honourable Justice Livesey and the Honourable Justice Bleby)
25 June 2021
APPEAL AND NEW TRIAL - APPEAL - GENERAL PRINCIPLES
CONTRACTS - BUILDING, ENGINEERING AND RELATED CONTRACTS - PERFORMANCE OF WORK
PROCEDURE - CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS - JUDGMENTS AND ORDERS - INTEREST ON JUDGMENTS
PROCEDURE - CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS - JUDGMENTS AND ORDERS - SATISFACTION AND SET-OFF OF JUDGMENTS
PROCEDURE - CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS - COSTS
In late December 2015 or early January 2016, the appellant building company (Bedrock Construction and Development Pty Ltd) (Bedrock)) and the respondent restaurateur (Mr Crea) entered into a contract (the Contract) for Bedrock to undertake a renovation and fitout of a restaurant in the Adelaide CBD (the Site).
The Contract provided for Bedrock to carry out the relevant works in accordance with, and to the standard set out in, construction drawings provided by Mr Crea. The Contract contained a clause which provided that the contractor was required to correct any defects, or finalise any incomplete work, within 10 days after receiving a written instruction to do so.
Mr Crea, through the contractually-appointed superintendent (the Architect), issued three defects lists to Bedrock, dated 12 April 2016 (Revision A), 20 April 2016 (Revision B) and 13 May 2016 (Revision C). By 3 May 2016, Bedrock had rectified a number of the defects on the Revision A and B defects lists. However, from 11 May 2016, Mr Crea effectively refused Bedrock further access to the Site, and on 19 May 2016, the Architect purported to issue a notice of termination pursuant to the Contract. Bedrock did not undertake any further work.
Mr Crea issued proceedings in the District Court, seeking damages in contract and tort for the allegedly defective work. Bedrock subsequently filed a cross-claim, seeking damages on account of the balance due to it on progress claims, and in respect of variations and delay costs. The trial of the claim and cross-claim occurred over several days commencing in December 2019.
In August 2020, the trial judge published his reasons. Mr Crea was largely successful in his defects claim, and Bedrock enjoyed partial success on its cross-claim. In relation to the defects claim, the trial judge accepted that Mr Crea had refused Bedrock access to the Site from about 11 May 2016, but found that this prohibition was reasonable and declined to disallow or reduce the claim on this basis. His Honour also found that the notice issued on 19 May 2016 did not effect a valid termination pursuant to the Contract, but that the Contract had been validly terminated at common law on this date.
After hearing submissions from both parties, the trial judge awarded interest on the claim and cross-claim, and ordered that Bedrock pay 60 per cent of Mr Crea’s costs.…
Continue reading Bedrock Construction and Development Pty Ltd v Crea
Sign in free to access the full text
- AGLC
- Bedrock Construction and Development Pty Ltd v Crea [2021] SASCA 66
- Case
- [2021] SASCA 66
- Decision Date
CaseChat Overview and Summary
The appeal required the court to determine several legal issues. Firstly, whether the trial judge erred in awarding damages to Mr Crea for defects without adequately considering Bedrock's contractual right to a period of at least 10 working days to rectify any identified defects. Secondly, the court needed to consider the appropriateness of awarding interest on Bedrock's cross-claim, particularly in light of the timing of the claim and the nature of the debt. Finally, the court was asked to reconsider the order for costs, given the potential alteration of the parties' respective success at trial.
The Full Court of the Supreme Court of South Australia, allowing the appeal, held that the trial judge's award of damages for Mr Crea's defects claim should be reduced. This was because the contract provided Bedrock with a contractual opportunity of at least 10 working days to rectify defects, and the evidence did not establish that this entitlement had been afforded to Bedrock. The court found it unnecessary to determine the validity of the contract's termination, as it held no practical significance for the parties. Regarding interest, the court determined it was appropriate to award Bedrock interest on its entire cross-claim from the same date Mr Crea was awarded interest on his defects claim, as a significant portion of the cross-claim was an agreed liquidated sum due before the claim was instituted.
Consequently, the court ordered a reduction in the damages awarded to Mr Crea for defects. The court also ordered that Bedrock be awarded interest on its cross-claim from the same date as Mr Crea's interest award. The court further directed that a balance judgment be entered, reflecting the net entitlement between the parties, and that the issue of costs be reconsidered due to the altered assessment of the parties' respective success on appeal.
Orders
Orders of the court
Held, per Doyle JA (Livesey and Bleby JJA agreeing), allowing the appeal:
1. In circumstances where the Contract provided Bedrock with a contractual opportunity of at least 10 working days to rectify any defects, and the evidence did not permit a finding that this entitlement had been given, the trial Judge’s award of damages for Mr Crea’s defects claim should be reduced.
2. It is unnecessary to reach a final view on the issue of whether the Contract was validly terminated, as neither party suggested that the trial judge’s conclusion in this regard was of any practical significance.
3. As a significant proportion of the cross-claim was an agreed liquidated sum that fell due before the date the cross-claim was instituted, it is appropriate to award Bedrock interest on the entirety of its cross-claim from the same date Mr Crea was awarded interest on his defects claim.
4. There was no good reason to depart from the usual approach of entering a balance judgment.
5. As the grounds on which the appeal has been allowed will both alter the assessment of the parties’ respective degrees of success below, and result in the substitution of a judgment with a net entitlement in favour of Bedrock, it is appropriate that the Court reconsider the issue of costs.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established