SUPREME COURT OF SOUTH AUSTRALIA
(Full Court)
TINCKNELL & ANOR v DUTHY HOMES PTY LTD & ANOR; DUTHY HOMES PTY LTD & ANOR v TINCKNELL & ANOR
[2020] SASCFC 24
Judgment of The Full Court
(The Honourable Justice Peek, The Honourable Justice Parker and The Honourable Justice Doyle)
17 April 2020
APPEAL AND NEW TRIAL - APPEAL - GENERAL PRINCIPLES - INTERFERENCE WITH DISCRETION OF COURT BELOW
CONTRACTS - BUILDING, ENGINEERING AND RELATED CONTRACTS - PERFORMANCE OF WORK - REMEDIES FOR BREACH OF CONTRACT - DAMAGES
TRADE AND COMMERCE - COMPETITION, FAIR TRADING AND CONSUMER PROTECTION LEGISLATION - CONSUMER PROTECTION - MISLEADING OR DECEPTIVE CONDUCT OR FALSE REPRESENTATIONS
APPEAL AND NEW TRIAL - APPEAL - GENERAL PRINCIPLES - INTERFERENCE WITH DISCRETION OF COURT BELOW - PARTICULAR CASES - OTHER MATTERS - COSTS
Appeal against a decision of a Judge of the District Court concerning the construction of a residential home at Mannum. The contract price of the house was $2.3 Million.
The Builder commenced proceedings against the Owners seeking payment of the final progress claim. The Owners cross-claimed claiming that the Builder was in breach of contract and statutory warranties. They sought the cost of remedial works, as well as damages for pain and suffering, delay, and breach of the Trade Practices Act. They sought damages against the Builder’s director, in his personal capacity, for negligence and as an accessory to the Builder’s breach of the Trade Practices Act. They asserted that the works were not practically complete.
The Judge found that the house was practically complete on 26 February 2013. The Judge made remedial orders where she found it appropriate and where remedial orders were not appropriate, her Honour awarded the Owners compensation. Her Honour found that certain rectification costs claimed by the Owners were unreasonable and on that basis the Owners were not entitled to damages for breach of contract or breach of statutory warranty. The Judge dismissed the Owners’ claim for delay damages, pain and suffering and breaches of the Trade Practices Act. The Judge awarded the Owners the sum of $32,106.07 in back charges and dismissed the remainder of the Owner’s claims for back charges. The Judge held that the Builder was entitled to the final progress claim, plus the difference between the ‘float’ for variations, less those items where a remedial work order was inappropriate. The Judge awarded the Builder the sum of $173,049.41 plus interest. The Builder was awarded 60 per cent of its costs on a party/party basis.
On appeal, the Owners contend that the Judge erred, inter alia, by:
1. dismissing the claims for defective waterproofing, termite protection and tiling on the external balcony;
2. dismissing the claims for delay damages and damages for breach of the Trade Practices Act;
3. finding that the works had reached practical completion on 26 February 2013;
4. finding that the Builder be permitted to carry out remedial work in respect of the hot water system in accordance with the recommendations of the Builder’s expert rather…
Keep reading for free
Create a free CaseChat account to read Tincknell v Duthy Homes Pty Ltd; Duthy Homes Pty Ltd v Tinck... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2020] SASCFC 24
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the court was whether the trial judge erred in dismissing the owners' claim for damages related to defective waterproofing. Specifically, the court had to determine if the judge was correct in finding a lack of proportionality between the cost of the proposed remedial work and the benefit it would achieve, thereby refusing to award damages based on the estimated cost of rectification. This required the court to consider the principles established in *Bellgrove v Eldridge* regarding the assessment of damages for defective building work.
The court's reasoning focused on the application of the *Bellgrove v Eldridge* principles. These principles establish that the prima facie measure of damages for defective building work is the cost of remedial work necessary to bring the work into conformity with the contract. However, this cost must also represent a reasonable course to adopt. If the remedial work, while necessary to conform with specifications, would not be a reasonable response to the deficiency, the measure of loss may be the diminution in the building's value. The court noted that whether remedial work is necessary and reasonable is a question of fact and degree, and that in certain circumstances, the nature of the defendant's conduct might be relevant to the assessment of reasonableness. The trial judge had found that the proposed remedial work for the waterproofing was disproportionate to the benefit it would achieve, leading to the dismissal of the owners' claim.
The appeal court upheld the trial judge's decision. It found that the judge had correctly applied the principles from *Bellgrove v Eldridge* and that her Honour's conclusion regarding the lack of proportionality between the cost of remedial work and its benefit was a finding of fact open to her on the evidence. Consequently, the owners' appeal on this ground was dismissed. The court also addressed the builder's appeal against the costs orders, finding them to be reasonable and just in the circumstances.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
The Builder asserts that the Owners knew, because they had watched the house being built, the construction methods and the waterproofing. If there is any waterproofing defect it is latent. The work is not defective and no remedial work is necessary. The Builder asserts that the Judge’s application of the principles described is orthodox and well-reasoned. Consideration The key question in relation to the issue of waterproofing is whether the Judge erred by dismissing the claim for damages because of her Honour’s conclusion that there was a lack of proportionality between the cost of the proposed remedial work and the benefit that it would achieve. The decision in Wheeler does not assist the Owners as the case was decided on the particular facts. The question is whether the Judge correctly applied the principles stated by the High Court in Bellgrove v Eldridge.[7] In that case a builder had constructed a house with defective foundations. The issue before the High Court was whether it was appropriate to award damages assessed by reference to the cost of rectification, which would involve the demolition and re‑erection of the house. Alternatively, should damages be assessed in recognition of the cost that would be incurred in rectifying the defective foundations by underpinning. A further alternative was whether damages should be assessed by reference to the diminution in value of the house caused by the defective foundations. [7] (1954) 90 CLR 613. The High Court stated the following principles:·The prima facie position is that where building work is defective and remedial work is required so as to ensure conformity with the specification, the measure of damages will be the cost of the remedial work required to put the plaintiff in the same position as if the contract had been properly performed;·In some cases that may require demolition of the building and its re‑erection;·Not only must the work be necessary to conform with the specifications but the performance of that work must also be a reasonable course to adopt;·Where remedial works are required to conform with the specifications but would not constitute a reasonable response to the deficiency, the true measure of the owner’s loss will be the diminution in value of the building;·Whether remedial work is necessary and reasonable is a question of fact. The High Court found in Bellgrove that because the defective foundations were a serious risk to the stability of the house, the demolition and re‑erection of the building was both necessary and reasonable. The Judge referred to the observation made by the High Court in Tabcorp Holdings Ltd v Bowen Investments Pty Ltd to the effect that the test of “unreasonableness” will only be satisfied by “fairly exceptional circumstances”.[8][8] (2009) 236 CLR 272 at [17]. In Stone v Chappel Doyle J (with Kourakis CJ and Hinton J agreeing) suggested that if the unreasonableness qualification is justified in part by reference to the unfairness of the burden to be imposed upon the defendant, it may be that this permits consideration of the nature or quality of the breach by the defendant.[9] Doyle J suggested if the defendant’s conduct was “intentional, sharp, cynical, profit-driven or opportunistic, then it would be more difficult for the defendant to satisfy a court that the burden sought to be imposed upon it was unreasonable”.[10] Doyle J went on to suggest that while there was merit in this approach to the unreasonableness qualification, this approach had not been expressly adopted in the Australian authorities. The matter had been left to be resolved as a question of fact and degree to be decided in light of the circumstances of the individual case.[9] (2017) 128 SASR 165. [10] Ibid at [253].