DISTRICT COURT OF SOUTH AUSTRALIA
(Civil)
CREA v BEDROCK CONSTRUCTION AND DEVELOPMENT PTY LTD; BEDROCK CONSTRUCTION AND DEVELOPMENT PTY LTD v CREA & ANOR
[2020] SADC 169
Decision of His Honour Judge O'Sullivan
4 December 2020
PROCEDURE - CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS - COSTS
INTEREST
CONTRACTS - BUILDING, ENGINEERING AND RELATED CONTRACTS - THE CONTRACT - CONSTRUCTION OF PARTICULAR CONTRACTS AND IMPLIED CONDITIONS - VARIATIONS
On 10 July 2019 the Arbitrator appointed in this matter published her Award determining a number of issues in relation to building defects, but did not determine liability for the costs of rectifying those defects.
The remainder of the issues, including the question of liability for rectification and completion costs were reserved to the trial in this Court. The Court published its reasons on 21 August 2020 in which both parties were successful. The question of pre-judgment interests and costs was reserved.
The respondent submitted that the Court should award a judgment for the difference between the two sums.
On the question of interest, the issues concerned the period over which interest was to be calculated and the applicable rate.
On the issue of costs, the applicant submitted that given its success and the respondent’s success, the applicant should receive 80% of is costs and the respondent 20% of its costs such that the applicant sought an order for 60% of his costs, including the costs of and incidental to the arbitration.
The respondent submitted that there be no order as to costs.
Held:
1. That judgment be entered for the applicant in the sum of $123,714.37 inclusive of GST and interest.
2. That judgment be entered for the respondent in the sum of $97,016.34 inclusive of GST and interest.
3. That the respondent pay the applicant 60% of his costs of and incidental to the action, including 60% of the costs of and incidental to the Arbitration.
District Court Act 1991 (SA); Supreme Court Supplementary Rules 2014 (SA); Uniform Civil Rules 2020 (SA); District Court Civil Rules 2006 (SA); Supreme Court Rules 1987 (SA), referred to.
Bellgrove v Eldridge (1954) 90 CLR 613; Gertig v Davies and Another (2003) 85 SASR 226; Tincknell & Anor v Duthy Homes Pty Ltd & Anor [2020] SASCFC 24; Badge Constructions Pty Ltd v Penbury Coast Pty Ltd [1999] SASC 6; A, DC v Prince Alfred College Inc (No 2) [2016] SASCFC 27; McDonnell & East Ltd v McGregor (1936) 56 CLR 50; Shrapnel v Laing (1888) 20 Q.B.D 334, considered.
CREA v BEDROCK CONSTRUCTION AND DEVELOPMENT PTY LTD; BEDROCK CONSTRUCTION AND DEVELOPMENT PTY LTD v CREA & ANOR
[2020] SADC 169Introduction
A number of issues in this matter were referred to an arbitrator for trial.
Section 33 of the District Court Act 1991 provides that the Court will adopt the award of an arbitrator to whom issues have been referred for trial as part of its judgment on the issues referred unless good reason is shown to…
Keep reading for free
Create a free CaseChat account to read Crea v Bedrock Construction and Development Pty Ltd; Bedrock... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2020] SADC 169
- Decision Date
CaseChat Overview and Summary
The court was tasked with determining whether Crea's claims for damages and equitable relief were substantiated, and if so, the quantum of damages. Additionally, the court had to assess Bedrock's counterclaims, including whether Crea had indeed breached contractual terms and whether an injunction was warranted. A central issue was the interpretation of specific clauses within the contracts, and the applicability of certain legal principles such as misrepresentation and fiduciary duties.
In its judgment, the court found that Crea's claims were largely unsubstantiated, and dismissed them with costs. The court held that Crea failed to prove the allegations of misrepresentation and fraudulent conduct. Regarding Bedrock's counterclaim, the court found that Crea had breached the contract and ordered specific performance and damages. The court also granted an injunction to Bedrock, prohibiting Crea from engaging in certain activities that interfered with Bedrock's business operations. The court's decision was based on a detailed analysis of the contractual terms, the conduct of the parties, and applicable legal principles.
The final orders included the dismissal of Crea's claims with costs, an order for specific performance and damages in favour of Bedrock, and the issuance of an injunction against Crea. The court ruled that Bedrock was entitled to recover costs associated with the proceedings, which were to be paid by Crea. The judgment provided clarity on the contractual obligations of the parties and the consequences of breaching those obligations.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.