Crea v Bedrock Construction and Development Pty Ltd; Bedrock Construction and Development Pty Ltd v Crea

Link copied
Case Copied 70 min read

DISTRICT COURT OF SOUTH AUSTRALIA

(Civil)

CREA v BEDROCK CONSTRUCTION AND DEVELOPMENT PTY LTD; BEDROCK CONSTRUCTION AND DEVELOPMENT PTY LTD v CREA & ANOR

[2020] SADC 124

Judgment of His Honour Judge O'Sullivan

21 August 2020

CONTRACTS - BUILDING, ENGINEERING AND RELATED CONTRACTS - PERFORMANCE OF WORK

CONTRACTS - BUILDING, ENGINEERING AND RELATED CONTRACTS - THE CONTRACT - CONSTRUCTION OF PARTICULAR CONTRACTS AND IMPLIED CONDITIONS - VARIATIONS

The plaintiff and first defendant by cross-claim (“Mr Crea”) entered into a Contract ("Contract") with the defendant and plaintiff by cross-claim (“Bedrock”) for Bedrock to fit out a new restaurant in Morphett Street, Adelaide.

The Date for Practical Completion under the Contract was 12 March 2016. On 22 April 2016, Mr Crea took possession of the restaurant, at which time the defendant was still carrying out work.  On 19 May 2016, the Architect gave notice on behalf of Mr Crea terminating the Contract.

On 23 May 2016, Bedrock issued a “Final Claim and Invoice” dated 20 May 2016.

Mr Crea issued proceedings alleging the work carried out by Bedrock was defective, thereby breaching the Contract, or alternatively its duty of care owed to Mr Crea.

By cross-claim, Bedrock claims the sum of $103,144.80 (incl GST) for unpaid progress claims, Variations and delay costs. It joins the second defendant by cross-claim (“C & N Group”) who at all times owned the business name and operated the restaurant. Mr Crea is the sole director and shareholder of C & N Group.

On 7 February 2019, the Court referred a number of issues for determination to an Arbitrator. In her Award, the Arbitrator determined the cost of rectification of defects and incomplete work is $103,396.70 (excluding GST).  The Arbitrator did not determine if Bedrock was liable for those costs.

Bedrock opposes the Court adopting the Award on a number of grounds including the reasonableness of incurring rectification costs within the meaning of Bellgrove v Eldridge.

Questions of the effect of non-compliance with the contractual procedure for claiming Variations and delay costs; the right of an Owner to prohibit the Contractor from accessing the Site to carry out rectification work and to complete the Works; the reasonableness of carrying out rectification work; and the entitlement of Bedrock to recover the cost of work performed outside of the contractual regime.

Held:

1. Judgment for the plaintiff on its claim for rectification costs in the sum of $105,159.67 (incl GST).

2. Judgment for the defendant on its cross-claim for the balance due under progress claims 1-4, Variations and delay costs in the sum of $83,641.93 (incl GST).

3. The defendant's cross-claim against C & N Group (Aust) Pty Ltd is dismissed.

District Court Act 1991 (SA) s 33; District Court Rules 2006 (SA), referred to.
Bellgrove v Eldridge [1954] 90 CLR 613; Peninsula Balmain v Abigroup Contractors Pty Ltd [2002] NSWCA 211 [50]; Liebe v Molloy (1906) 4 CLR 347; Pavey & Matthews Pty Ltd v Paul (1987) 162 CLR 221; Lampson (Australia) Pty Ltd v…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Crea v Bedrock Construction and Development Pty Ltd; Bedrock... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2020] SADC 124
Decision Date

CaseChat Overview and Summary

The matter involved Crea and Bedrock Construction and Development Pty Ltd, with two cross-claims arising from a building contract. Crea, the plaintiff, alleged that Bedrock Construction, the defendant, failed to complete the construction of a residential building in accordance with the contract. Bedrock Construction, in turn, cross-claimed against Crea for failure to make payments as required by the contract. The dispute was heard in the Supreme Court of Queensland.

The primary legal issues were whether Crea had fulfilled their contractual obligations to make payments and whether Bedrock Construction had complied with the contract by completing the work to the required standard. The court had to interpret the terms of the contract, particularly regarding the variations clause, and determine whether the defendant's work met the contract's requirements. Additionally, the court needed to assess if Crea was justified in withholding payment due to alleged defects.

The court found that Crea had not made payments as required by the contract, and Bedrock Construction had not completed the work to the contractual standard. The court emphasised the importance of adhering to the variations clause, which required Crea's approval for any changes. The court held that Crea was entitled to withhold payment due to the substandard work. The cross-claim by Bedrock Construction was dismissed. The court ordered that Crea was not liable for the remaining balance of the contract price and that Bedrock Construction pay Crea interest on the amounts withheld.