NEW SOUTH WALES COURT OF APPEAL
CITATION: Brewarrina Shire Council v Beckhaus Civil Pty Ltd & Anor [2006] NSWCA 361
FILE NUMBER(S):
40957/05
HEARING DATE(S): 28 November 2006
DECISION DATE: 15/12/2006
PARTIES:
Brewarrina Shire Council
Beckhaus Civil Pty Ltd
Dennis Fredrick Beckhaus
JUDGMENT OF: Giles JA Tobias JA McColl JA
LOWER COURT JURISDICTION: Supreme Court - Equity Division
LOWER COURT FILE NUMBER(S): SC 055025/02
LOWER COURT JUDICIAL OFFICER: Associate Justice Macready
COUNSEL:
A: B Walker SC / M Christie / V Culkoff
R: Mr Rudge SC / D Robertson
SOLICITORS:
A: Paul Ward-Harvey & Co, Sydney
R: Dutton Lawyers, Newcastle
CATCHWORDS:
CONTRACTS – building, engineering and related contracts – alleged non-compliance with contract specifications – payment claimed under s 8 of the Building and Construction Industry Security of Payment Act 1999 – whether breach of contract – measure of damages – assessment of expert evidence
LEGISLATION CITED:
Building and Construction Industry Security of Payment Act 1999
DECISION:
Appeal dismissed with costs
JUDGMENT:
IN THE SUPREME COURT
OF NEW SOUTH WALES
COURT OF APPEAL
CA 40957/05
SC 55025/02GILES JA
TOBIAS JA
McCOLL JAFriday 15 December 2006
BREWARRINA SHIRE COUNCIL v BECKHAUS CIVIL PTY LTD & ANOR
Judgment
GILES JA: I agree with Tobias JA.
TOBIAS JA: The town of Brewarrina in northwestern New South Wales has in the past been subject from time to time to inundation by floodwaters from the Barwon River. To prevent these occurrences earthen levee banks were constructed around the town. After a flood in 2000 when the town’s population was heavily engaged in saving the existing levees, the appellant (the Council) commissioned a redesign of the levees with a view to upgrading them to improve their effectiveness. The upgrade works were the subject of a tender process. The first respondent (Beckhaus Civil), whose principal is the second respondent (Mr Beckhaus), was the successful tenderer.
A contract in the form of General Conditions of Contract AS2124-1992 (the contract) with annexed related documents including Technical Specifications (the Specifications) was entered into between the Council and Beckhaus Civil on 13 October 2001. Work commenced the following day and continued until March 2002 when it became apparent to the Council that having nearly completed the works, Beckhaus Civil was about to apply for a Certificate of Practical Completion.
The contract provided for the Council to appoint one of its employees to the position of Superintendent of Works. On 16 December 2001 a Mr Komp was so appointed. However, on 21 March 2002 Mr Komp was removed as superintendent and a Mr Corven was appointed in his place. Mr Corven, after carrying out various investigations, sent a series of letters to Beckhaus Civil alleging non-compliance with a number of the requirements of the Specifications. On 26 April 2002 Beckhaus Civil lodged Progress Claim No.7 in the amount of $702,678.45 in respect of which it claimed payment pursuant to s.8 of the Building and Construction Industry Security of Payment Act 1999 (the 1999 Act). It appears that Beckhaus…
Keep reading for free
Create a free CaseChat account to read Brewarrina Shire Council v Beckhaus Civil Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2006] NSWCA 361
- Decision Date
CaseChat Overview and Summary
The Court of Appeal was required to determine whether the primary judge had erred in finding that Brewarrina Shire Council had not established a breach of contract by Beckhaus Civil. Specifically, the appeal challenged the primary judge's findings regarding the alleged non-compliance with contract specifications and the subsequent assessment of damages. The court also considered the weight given to the expert evidence presented at trial.
The Court of Appeal, in dismissing the appeal, found that the challenges raised by Brewarrina Shire Council to the primary judge's findings had failed. The court concluded that no errors of the nature alleged in the grounds of appeal had been established. The reasoning, as articulated by Tobias JA and agreed to by McColl JA, indicated that the Council's submissions on appeal were not successfully maintained, leading to the dismissal of the appeal.
The appeal was dismissed with costs.