SUPREME COURT OF THE AUSTRALIAN CAPITAL TERRITORY
| Case Title: | O’Toole & Anor v M Johnson Building Pty Ltd |
| Citation: | [2023] ACTSC 116 |
| Hearing Date: | 27 April 2023 – 5 May 2023 |
| Decision Date: | 19 May 2023 |
| Before: | Balla AJ |
| See [231] | |
| Decision: | |
Catchwords: | CIVIL LAW – BUILDING AND CONSTRUCTION – Breach of Contract – defects in construction of residential building – failure to carry out works in accordance with plans – failure to carry out works with proper care and skill – failure to comply with requirements under the Building Act – Rectification of defects |
| granted | |
| Legislation Cited: | Building Act 2004 (ACT) ss 20, 36, 42, 88, 140 Building (General) Regulation 2008 (ACT) |
| Cases Cited: | Bellgrove v Eldridge [1954] HCA 36; (1954) 90 CLR 613 Brewarrina Shire Council v Beckhaus Civil Pty Ltd & Anor [2006] NSWCA 361 |
| Jones v Dunkel (1959) 101 CLR 298 Kirkby v Coote [2006] QCA 61 Stone v Chappel [2017] SASCFC 72; 128 SASR 165 at 172 | |
| Tabcorp Holdings Ltd v Bowen Investments Pty Ltd [2009] HCA | |
| 8; 236 CLR 272 The Owners Units Plan 1917 v Koundouris [2016] ACTSC 96; | |
| 307 FLR 372 | |
| Documents Cited: | ACT Government, Minimum Documentation Requirements for |
| Building Applications Lodgement Class 1 and 10 - Residential | |
| Construction (2 August 2016) | |
| Parties: | Kate Mary O’Toole (First Plaintiff) |
| Farooq Ahmed (Second Plaintiff) | |
| M Johnson Building Propriety Ltd (First Defendant) Capital Certifiers Pty Ltd (Second Defendant) | |
| Representation: | Counsel |
| M Robens (Plaintiffs) | |
| J Masters (First Defendant) | |
| Solicitors | |
| Harrington Hall Lawyers (Plaintiffs) | |
| O’Connor Harris & Co (First Defendant) | |
| File Number: | SC 386 of 2021 |
| BALLA AJ: | |
| Introduction | |
| 1․ | In 2018 Ms Kate Mary O'Toole and Mr Farooq Ahmed bought a block of vacant land at Latham in the ACT and decided that they wanted to build a house on it. |
| 2․ | They retained the first defendant, M. Johnson Building Pty Ltd (the builder), and the building work commenced in February 2019. The plaintiffs moved in on 7 June 2019. |
| 3․ | The plaintiffs say that there have been a number of breaches of the contract by the builder and claim damages. |
| 4․ | The builder disputes the plaintiffs’ claims. |
Causes of Action
| 5․ | On 6 November 2018 the plaintiffs entered into a written contract with the builder for the construction of a single-story residential dwelling. | |
| 6․ | The plaintiffs rely on the clauses in the contract which say the builder was required to: | |
|
in a proper and skilful manner;[1]
[1] clause 1(a)
(b) Complete the works to the standards of construction required by the Building Act 2004 (ACT) (the Act) and, if inconsistent with the contract, to the higher standard;[2]
[2] clause 1(b)
(c) Provide a warranty as to the accuracy and correctness of the construction plans;[3]
[3] clause 4(a)
(d) Obtain all planning and building approvals;[4]
[4] clause 7(a)
(e) Notify them of any variations in writing;[5] and
[5] clause 17(c)
(f) Rectify any…
Keep reading for free
Create a free CaseChat account to read O'Toole v M Johnson Building Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2023] ACTSC 116
- Decision Date
CaseChat Overview and Summary
The court held that the builder breached the contract by not having the site classification reassessed during excavation and not following the geotechnical engineer's recommendation to use piers to weathered rock. The court found that the builder's design did not comply with the Australian Standards (AS) and the National Construction Code of Australia (NCC) because the engineers did not attend and view the excavated footings and there is no evidence of an engineered design or the application of engineering principles that would satisfy the requirements. The court also found that the builder breached the contract by spacing the ferrules/dowels too far apart in at least one area and using dowels which were too long, by not reinstating the cut reinforcing, by not complying with the Australian Standards (AS) for tiling over a large area, by not building the garage floor with a 100mm set-down as specified in the architectural drawings, by not setting down the internal wet areas and not installing the required falls, by not excavating the site in accordance with the plans, by not installing any drainage to take water away from the edge of the slab, by not constructing the driveway in accordance with the plans, by not changing the access to the porch from the driveway as set out in the plans, by not properly installing the garage door, by not installing expansion joints in the floor tiling, by not installing a termite management system, by not backfilling the stormwater lines to the required depth, by not tiling and sealing the walls adjoining the laundry tub and the ensuite vanity, by not sealing the linen cabinet in the laundry, by not sealing the internal doors at the top and bottom, by not applying the clear seal to the doors as required by the door manufacturer's conditions of sale, by not correctly painting and removing the packing materials around the ensuite and main bathroom vanity mirrors, and by not installing lift-off hinges on the bathroom door.
The court ordered the builder to pay the plaintiffs damages for the rectification of the defects, the cost of obtaining a new development approval and a certificate of occupancy, and loss of amenity. The court also ordered the builder to pay the plaintiffs' costs. The court held that the damages awarded should be reasonable and not out of proportion to the benefit to be obtained. The court considered the likely consequences which flow from the contractual breach and the expert evidence in determining the amount of damages. The court allowed the plaintiffs' claims except for one minor defect and made no award for loss of amenity. The court also apportioned the damages between the builder and the certifier, Capital Certifiers Pty Ltd, based on their respective responsibility for the loss or damage.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.