Lysaght Building Solutions Pty Ltd v Blanalko Pty Ltd [No 3]

Link copied
Case Copied 56 min read
IN THE SUPREME COURT OF VICTORIA Not Restricted

AT MELBOURNE

COMMERCIAL AND EQUITY DIVISION

TECHNOLOGY ENGINEERING AND CONSTRUCTION LIST

No. 05740 of 2012

LYSAGHT BUILDING SOLUTIONS PTY LTD
(T/AS HIGHLINE COMMERCIAL CONSTRUCTION)
(ACN 103 232 444)
Plaintiff
v
BLANALKO PTY LTD
(ACN 005 822 926)
Defendant
BLANALKO PTY LTD
(ACN 005 822 926)
Plaintiff by First Counterclaim
AND
TWENTIETH SUPERPACE NOMINEES PTY LTD
(T/AS SCT LOGISTICS)
Plaintiff by First Counterclaim
v
LYSAGHT BUILDING SOLUTIONS PTY LTD
(T/AS HIGHLINE COMMERCIAL CONSTRUCTION)
(ACN 103 232 444)
Defendant by First Counterclaim

---

JUDGE:

VICKERY J

WHERE HELD:

MELBOURNE

DATE OF HEARING:

4 APRIL 2013

DATE OF JUDGMENT:

21 AUGUST 2013

CASE MAY BE CITED AS:

LYSAGHT BUILDING SOLUTIONS PTY LTD v BLANALKO PTY LTD [No. 3]

MEDIUM NEUTRAL CITATION:

[2013] VSC 435

---

ARBITRATION – Stay application under s 8 of the Commercial Arbitration Act 2011- s 8 considered – Stay granted in part.

BUILDING CONTRACT -  Clause 42 of Australian Standard Contract AS4300–1995 contract considered.

PRACTICE AND PROCEDURE - Summary judgment sought pursuant to s 63 of the Civil Procedure Act 2010 or Order 22 of the Supreme Court (General Civil Procedure) Rules 2005 - Applicable test for summary judgment under the Civil Procedure Act 2010 determined by the Court of Appeal on a reference pursuant to s 17B(1) Supreme Court Act 1986 [2013] VSC 201 and applied.

---

APPEARANCES:

Counsel Solicitors
For the Plaintiff Mr M Dempsey with
Mr A Morrison
Holding Redlich
For the Defendant Mr R Manly with
Mr P Booth
Wisewould Mahony

HIS HONOUR:

Background

  1. These proceedings relate to a design and construct contract for the construction of a rail freight terminal, a container paved area and a locomotive workshop together with associated facilities in Penfield, South Australia (the “Contract”).  The Contract, which incorporates Australian Standard Contract AS4300–1995, is governed by Victorian law.

  1. The plaintiff, Lysaght Building Solutions Pty Ltd (“Lysaght”) is the contractor under the Contract and the defendant, Blanalko Pty Ltd (“Blanalko“) is the principal.

  1. Lysaght as the contractor lodged progress claims for payment relating to works done at a rail freight terminal. These claims were received by the Superintendent, Mr Michael Zerbst (“Zerbst”) as follows:

(a)       claim number 10, dated 29 February 2012 was received on 1 March 2012;

(b)      claim number 12, dated 30 April 2012 was received on 3 May 2012;  and

(c)       claim number 13, dated 30 May 2012 was received on 11 June 2012.

  1. Blanalko failed to make any payment under these payment claims.

  1. By summons dated 7 November 2012, Lysaght sought summary judgment for three progress payments payable under clause 42.1 of the Contract (“clause 42.1”) in the total sum of $3,130,522.97 (or alternatively $3,119,591.24) plus GST.  These progress payments are claimed to have been outstanding from March to July 2012.  The progress payment claims were not made under the Building and Construction Industry Security of Payment Act 2002 (NSW) or its interstate equivalents.

  1. On 27 February 2013, Blanalko filed a defence denying liability, and a counterclaim which:

(a)       sought…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Lysaght Building Solutions Pty Ltd v Blanalko Pty Ltd [No 3] and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2013] VSC 435
Decision Date

CaseChat Overview and Summary

Lysaght Building Solutions Pty Ltd, the subcontractor, sought a stay of the proceedings against Blanalko Pty Ltd, the principal contractor, pursuant to section 8 of the Commercial Arbitration Act 2011. The dispute arose from a building contract governed by the Australian Standard Contract AS4000-1995, which included an arbitration clause. The subcontractor argued that the contractual dispute should be resolved through arbitration rather than litigation. The case was heard in the Supreme Court of Victoria.

The primary legal issue before the court was whether the subcontractor's application for a stay of proceedings should be granted under section 8 of the Commercial Arbitration Act 2011. Additionally, the court had to determine the applicable test for summary judgment under section 63 of the Civil Procedure Act 2010, as referenced by the Court of Appeal in 2013. The subcontractor also sought summary judgment against the principal contractor for the outstanding debt.

In its decision, the court found that the subcontractor's application for a stay of proceedings was warranted in part. The court held that the dispute fell within the scope of the arbitration clause in the contract, thereby requiring the parties to pursue arbitration. The court applied the test for summary judgment as outlined in the referenced decision, concluding that the subcontractor was entitled to summary judgment for the undisputed amount. The court granted the stay of proceedings and ordered the principal contractor to pay the subcontractor the undisputed sum.

The final orders of the court included a partial stay of the proceedings in favour of the subcontractor, requiring the parties to proceed with arbitration for the unresolved issues. The court also granted summary judgment to the subcontractor for the undisputed amount owed by the principal contractor. The subcontractor was ordered to pay the principal contractor's costs of the stay application and the summary judgment application.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.