Onesteel Manufacturing Pty Ltd v United Kg Pty Ltd

Link copied
Case Copied 56 min read

SUPREME COURT OF SOUTH AUSTRALIA

(Civil)

ONESTEEL MANUFACTURING P/L v UNITED KG P/L

Judgment of The Honourable Justice Debelle

21 April 2006

CONTRACTS - BUILDING, ENGINEERING AND RELATED CONTRACTS - REMUNERATION

Preliminary questions for determination – target estimate contract – dispute as to payment of costs incurred by contractor – whether implied term that costs must be reasonably and properly incurred – whether implied term that costs must be incurred in course of best endeavours performance of contract – whether information and evidence about costs incurred must be provided to the reasonable satisfaction of plaintiff – questions answered.

Brewarrina Shire Council v Beckhaus Civil Pty Ltd (2003) 56 NSWLR 576, discussed.
Amann Aviation Pty Ltd v Commonwealth (1990) 22 FCR 527; Antaios Compania Naviera SA v Salen Rederierna AB [1985] AC 191; Aquatec-Maxcon Pty Ltd v Minson Nacap Pty Ltd (2004) 8 VR 16; Australian Broadcasting Commission v Australasian Performing Rights Association Ltd (1973) 129 CLR 99; Australian Casualty Co Ltd v Federico (1986) 160 CLR 513; Booker Industries Pty Ltd v Wilson Parking (Qld) Pty Ltd (1982) 149 CLR 600; BP Refinery (Westernport) Pty Ltd v Shire of Hastings (1977) 180 CLR 266; Byrne v Australian Airlines Ltd (1995) 185 CLR 410; Codelfa Construction Pty Ltd v State Rail Authority of NSW (1982) 149 CLR 337; Cohen & Co v Ockerby & Co Ltd (1917) 24 CLR 288; Commonwealth v Amann Aviation Pty Ltd (1991) 174 CLR 64; Equuscorp Pty Ltd v Glengallan Investments Pty Ltd (2004) 218 CLR 471; Gollin Co Ltd v Karenlee Nominees Pty Ltd (1983) 153 CLR 455; Hillas & Co Ltd v Arcos Ltd (1932) 147 LT 503; L Schuler AG v Wickman Machine Tool Sales Ltd [1974] AC 235; Maggbury Pty Ltd v Hafele Australia Pty Ltd (2001) 210 CLR 181; McCann v Switzerland Insurance Australia Ltd (2000) 203 CLR 579; Meehan v Jones (1982) 149 CLR 571; Minson Nacap Pty Ltd v Aquatec-Maxcon Pty Ltd (2001) 17 BCL 269; Pacific Carriers Ltd v BNP Paribas (2004) 218 CLR 451; Prince Albert Pulp Co Ltd v The Foundation Co of Canada Ltd (1976) 68 DLR (3d) 283; Renard Constructions (ME) Pty Ltd v Minister for Public Works (1992) 26 NSWLR 234; Schenker & Co (Aust) Pty Ltd v Maplas Equipment and Services Pty Ltd [1990] VR 834; Service Station Association Ltd v Berg Bennett & Associates Pty Ltd (1993) 45 FCR 84; Toll (FGCT) Pty Ltd v Alphapharm Pty Ltd (2004) 219 CLR 165; Upper Hunter County District v Australian Chilling & Freezing Co Ltd (1968) 118 CLR 429, considered.

ONESTEEL MANUFACTURING P/L v UNITED KG P/L
[2006] SASC 119

Civil

  1. DEBELLE J.The issues which fall for determination on this application concern the proper interpretation of a building contract in relation to the payment of what the contract calls “Reimbursable Costs”.

  2. On 16 December 2003 the plaintiff OneSteel Manufacturing…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Onesteel Manufacturing Pty Ltd v United Kg Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2006] SASC 119
Decision Date

CaseChat Overview and Summary

Onesteel Manufacturing Pty Ltd took United Kg Pty Ltd to court over a dispute concerning the payment of costs incurred by the contractor under a target estimate contract. The primary issue was whether United was required to provide evidence and information to OneSteel's satisfaction to substantiate its claims for progress payments or the Final Reimbursable Costs Claim. The court was also asked to determine if there was an implied term that the costs must be reasonably and properly incurred, and whether the costs must be incurred in the course of performing the contract to the best of the contractor's endeavours.

The court addressed these questions by first clarifying the distinction between providing evidence and information to the reasonable satisfaction of OneSteel and OneSteel's requirement to provide such information as it may reasonably require. The court ruled that United's obligation was to furnish evidence and information that OneSteel's representative might reasonably demand, establishing an objective standard. The court further ruled that claims for reimbursable costs must be evidenced in a Progress Payment Claim Form unless they are part of a Final Reimbursable Costs Claim. Additionally, the court determined that reimbursable costs must be direct, actual, and reasonably and properly incurred, excluding certain specified circumstances.

The court concluded that United's obligation to support its claims with evidence and information as required by OneSteel's representative was clear and objective. The decision clarified the nature of the evidence and information required for claims under the contract and established the scope of reimbursable costs. The court answered the questions in a manner that provided clarity on the contractual obligations between the parties.

Background

Background to the litigation

Onesteel Manufacturing Pty Ltd ("OneSteel") engaged United Kg Pty Ltd ("United") for the construction of a new steel manufacturing facility. The contract between the parties, referred to as the "Building Contract," contained provisions for reimbursable costs and progress payments. Under the contract, United was required to submit claims for reimbursable costs and progress payments in specified forms and within specified timeframes. A dispute arose between the parties regarding the costs incurred by United and the evidence required to support those costs.

OneSteel claimed that United had not provided adequate evidence and information to support its claims for reimbursable costs and progress payments. OneSteel alleged that United had failed to incur the costs in the best endeavours performance of the contract and had not incurred the costs reasonably and properly. United denied these allegations and argued that it had provided sufficient evidence and information to support its claims. The dispute led to a hearing before the court to determine the obligations of the parties under the contract regarding the provision of evidence and information to support claims for reimbursable costs and progress payments.

The court was asked to determine several questions, including whether there was an implied term in the contract that costs must be reasonably and properly incurred, whether there was an implied term that costs must be incurred in the course of best endeavours performance of the contract, and whether information and evidence about costs incurred must be provided to the reasonable satisfaction of OneSteel. The court found that the contract did not contain an implied term that costs must be reasonably and properly incurred or incurred in the course of best endeavours performance of the contract. However, the court found that United was obliged to provide evidence and information to the reasonable satisfaction of OneSteel's representative to support its claims for reimbursable costs and progress payments.

This case, Onesteel Manufacturing Pty Ltd v United Kg Pty Ltd, came before the court following a dispute over the payment of costs incurred by the contractor under a target estimate contract. The primary issue revolved around the obligations of the defendant, United Kg Pty Ltd, to provide evidence and information about costs incurred, and whether there were implied terms that these costs must be reasonably and properly incurred, incurred in the course of best endeavours performance of the contract, and provided to the reasonable satisfaction of the plaintiff, Onesteel Manufacturing Pty Ltd. The court was asked to determine several preliminary questions concerning these obligations. The matter proceeded from a referral for determination of preliminary questions, which was made by an earlier decision of the court. This referral followed an interlocutory application where the court had already ruled on certain aspects of the contract interpretation and the obligations of the parties. Key procedural steps included the filing of the referral by the parties, submissions by both parties addressing the specific questions referred, and a hearing where both parties presented their arguments. The court's decision focused on answering the referred questions concerning the nature and extent of the defendant's obligations to provide information and evidence to the plaintiff.

Decision

Reasons for decision

DEBELLE J
The only question for determination is whether United is obliged to provide evidence and information to the reasonable satisfaction of OneSteel’s representative. In my view, the obligation of United is that expressed in Brewarrina, namely, that United is obliged to support its claim for a progress payment or for the Final Reimbursable Costs Claim with evidence and with such information as OneSteel’s representative may reasonably require. There is an important difference between United being obliged to provide to the reasonable satisfaction of OneSteel evidence and information as to its claim and OneSteel being required to provide such information as OneSteel may reasonably require. The latter creates an objective standard which is absent in the former. Question 2 will be answered accordingly.CONCLUSION For these reasons I answer the questions as follows.1.1There is no single answer to this question. It must be answered as follows(1) Claims for Reimbursable Costs which are the subject of a claim for a progress payment must be described and evidenced in a Progress Payment Claim Form completed in accordance with Appendix B1 of the Special Conditions of Contract.(2) Claims for Reimbursable Costs which are the subject of a Final Reimbursable Costs Claim do not have to be described in a Progress Payment Claim Form completed in accordance with Appendix B1 of the Special Conditions of Contract.(3) No claim for Reimbursable Costs may be made after the time for lodging the Final Reimbursable Costs Claim has expired unless(a)it is a claim for Reimbursable Costs incurred in rectifying defective work during the Defects Liability Period;(b)it is a claim for Reimbursable Costs which have been the subject of a prior claim for progress payments or the subject of the Final Reimbursable Costs Claim and those costs have not been paid; or(c)the defendant has requested the plaintiff’s representative to grant an extension to the period for lodging the Final Reimbursable Costs Claim.1.2No.1.3The Reimbursable Costs which the defendant is entitled to be paid are limited to direct actual costs that have been reasonably and properly incurred by the defendant in carrying out the Works under the Contract.1.4The Reimbursable Costs which the defendant is entitled to be paid are limited to direct actual costs that have not been incurred by the defendant in the circumstances described in (a) to (e) of the Definition of Reimbursable Costs in Clause 2 of the Special Conditions of Contract.2.The obligation upon the defendant contained in Clause 40.2 of the General Conditions of Contract to support claims for payment by evidence of the amount due to the defendant and such information as OneSteel’s representative may require obliges the defendant to provide to the plaintiff’s representative such information as he may reasonably require.

Ratio Decidendi

Legal Principle Established

Established by: DEBELLE J

In the case of Onesteel Manufacturing Pty Ltd v United Kg Pty Ltd, the court addressed several preliminary questions arising from a dispute under a target estimate contract concerning the payment of costs incurred by the contractor. The court’s reasoning was focused on interpreting contractual obligations and the timing of cost claims under the contract. The primary issue was whether the defendant, United, was obliged to provide evidence and information about its claims to the reasonable satisfaction of the plaintiff, OneSteel. The court held that United’s obligation was to provide information and evidence to the reasonable satisfaction of OneSteel’s representative, establishing an objective standard for the provision of such information.

The court began by addressing the necessity of describing and evidencing Reimbursable Costs in a Progress Payment Claim Form. It found that claims for Reimbursable Costs that form part of a progress payment must be described and evidenced in a specific form as per Appendix B1 of the Special Conditions of Contract. However, claims for Reimbursable Costs that are the subject of a Final Reimbursable Costs Claim do not need to be detailed in a Progress Payment Claim Form. The court further clarified that no claims for Reimbursable Costs can be made after the specified period for lodging the Final Reimbursable Costs Claim has expired, except for costs incurred in rectifying defective work during the Defects Liability Period, costs that have been the subject of prior progress payment claims or the Final Reimbursable Costs Claim and remain unpaid, or costs for which an extension has been requested from the plaintiff’s representative.

In addressing whether Reimbursable Costs may be claimed after the Final Reimbursable Costs Claim period has expired, the court established that such claims are permissible only under specific conditions, reinforcing the importance of adhering to the contractual timelines for cost claims.

The court also determined that the Reimbursable Costs which the defendant is entitled to be paid are limited to direct actual costs that have been reasonably and properly incurred in carrying out the Works under the Contract. These costs must not fall within the excluded categories specified in Clause 2 of the Special Conditions of Contract. This limitation ensured that only legitimate and relevant costs were considered for reimbursement.

Furthermore, the court clarified that the defendant is limited to direct actual costs that have been reasonably and properly incurred in carrying out the Works, excluding those incurred in specific circumstances described in the contract. This interpretation emphasized the importance of adhering to the contractual definitions and exclusions when claiming costs.

Finally, the court concluded that the defendant's obligation to provide evidence and information to the plaintiff’s representative is an objective standard, meaning that United must provide such information as OneSteel’s representative may reasonably require. This objective standard contrasts with the subjective standard of providing information to the reasonable satisfaction of OneSteel, highlighting the importance of clarity and specificity in contractual obligations. The court’s decision in this matter thus established binding legal principles regarding the description, timing, and substantiation of cost claims under the contract.