Brewarrina Shire Council v Beckhaus Civil Pty Ltd

Link copied
Case Copied 44 min read
CITATION:

Brewarrina Shire Council v Beckhaus Civil Pty Ltd & 1 Or [2005] NSWCA 248

HEARING DATE(S):

12/07/05, 13/07/05, 14/07/05, 15/07/05

 
JUDGMENT DATE: 


4 August 2005

JUDGMENT OF:

Hodgson JA at 1; Ipp JA at 2; McColl JA at 230

DECISION:

(1) The appeal be allowed (2) The orders made by Master Macready following his judgments of 16 September 2004 and 7 December 2004 be set aside (3) Beckhaus pay 70% of the Council's costs of the appeal and cross-appeal, and to have a certificate under the Suitors' Fund Act, if otherwise eligible (4) The following issues be remitted to Macready AsJ to determine in the light of the reasons for judgment (i) The costs of rectifying the work at the culverts (ii) The extent to which the levees constructed by Beckhaus did not comply with the requirement of 12% maximum linear shrinkage, and the costs of rectifying the work that was defective in this respect (iii) The amount the Council would have paid to Beckhaus (including amounts due for variations affecting the cost of the work) if all the work had been duly completed by it in accordance with the Contract (iv) The amount, if any, owing to Beckhaus by the Council for work that advanced the completion of the Contract (as assessed in accordance with the reasons for judgment) (v) The amount, if any, owing to Beckhaus by the Council in respect of the amount claimed under Variation 21 (vi) The amount, if any, owing to the Council by Beckhaus in respect of its cross-claims (as assessed in accordance with the reasons for judgment) (vii) Whether the Council should be given leave to amend its claim so as to be able to claim liquidated damages, and the resolution of such a claim (if it be allowed) (viii) Interest, if any (ix) The costs of the trial and the remitted hearing.

CATCHWORDS:

BUILDING AND CONSTRUCTION - defective or incomplete work - no damage for defective or incomplete work sustained while contract is on foot and contractor is required to complete the work - termination by agreement - can be ab initio or release from future performance only - implied term that the parties' rights are governed by provisions in the contract relating to completion despite the termination of it - failure to meet contractual standard - evidentiary onus on contractor to prove the contractual standard has substantially been complied with - breach by contractor - evidentiary onus on contractor to prove no damage suffered - assessment of damages for rectification costs - costs of new work required to achieve conformity with contractual requirements - undertaking of the new work must be reasonable - intention to rebuild or to rectify the work is generally not relevant - suspension of the work to be carried out under a contract - s 27 of the Building and Contruction Industry Security of Payment Act 1999 (NSW) - no suspension if payment under s 15(1)(b) of the Act is conditional upon the payment of…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Brewarrina Shire Council v Beckhaus Civil Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2005] NSWCA 248
Decision Date

CaseChat Overview and Summary

The New South Wales Court of Appeal considered a dispute between Brewarrina Shire Council and Beckhaus Civil Pty Ltd concerning defective and incomplete building works. The Council alleged that Beckhaus had failed to meet contractual standards in constructing culverts and levees. The primary dispute revolved around the assessment of damages for rectification costs and the application of the Building and Construction Industry Security of Payment Act 1999 (NSW).

The Court was required to determine several key legal issues. These included whether the Council could claim damages for defective work while the contract was still on foot and the contractor was obliged to complete the work, the evidentiary onus on the contractor to prove substantial compliance with contractual standards and the absence of damage, and the principles governing the assessment of rectification costs, including the reasonableness of undertaking new work. The Court also had to consider the application of section 27 of the Security of Payment Act regarding the suspension of work, and the principles for raising new claims on appeal, as established in *Suttor v Gundowda Pty Ltd*. Furthermore, the Court examined the requirement for an adequate causative link between alleged misleading or deceptive conduct and damage suffered.

The Court reasoned that generally, no damages can be claimed for defective or incomplete work while the contract remains on foot and the contractor is still required to complete it, unless the contract has been terminated in a manner that releases parties from future performance. The evidentiary onus rests on the contractor to demonstrate substantial compliance with contractual standards and to prove that no damage was suffered. The assessment of rectification costs requires that the proposed new work be reasonable, and the intention to rebuild or rectify is generally irrelevant to the quantum of damages. Regarding the Security of Payment Act, suspension of work is not permitted if payment is conditional upon a bank guarantee. The Court also affirmed that new claims should not ordinarily be raised for the first time on appeal, adhering to established principles.

The Court allowed the appeal, setting aside the orders made by the Master. Beckhaus was ordered to pay 70% of the Council's costs of the appeal and cross-appeal, with eligibility for a certificate under the Suitors' Fund Act. Several issues were remitted to the Master to determine in light of the Court's reasons, including the costs of rectifying the culverts and levees, the amount the Council would have paid for completed work, amounts owing to Beckhaus for work advanced or under a specific variation, amounts owing to the Council on cross-claims, whether the Council should be granted leave to claim liquidated damages, and questions of interest and trial costs.

Orders

Orders of the court

(1) The appeal be allowed (2) The orders made by Master Macready following his judgments of 16 September 2004 and 7 December 2004 be set aside (3) Beckhaus pay 70% of the Council's costs of the appeal and cross-appeal, and to have a certificate under the Suitors' Fund Act, if otherwise eligible (4) The following issues be remitted to Macready AsJ to determine in the light of the reasons for judgment (i) The costs of rectifying the work at the culverts (ii) The extent to which the levees constructed by Beckhaus did not comply with the requirement of 12% maximum linear shrinkage, and the costs of rectifying the work that was defective in this respect (iii) The amount the Council would have paid to Beckhaus (including amounts due for variations affecting the cost of the work) if all the work had been duly completed by it in accordance with the Contract (iv) The amount, if any, owing to Beckhaus by the Council for work that advanced the completion of the Contract (as assessed in accordance with the reasons for judgment) (v) The amount, if any, owing to Beckhaus by the Council in respect of the amount claimed under Variation 21 (vi) The amount, if any, owing to the Council by Beckhaus in respect of its cross-claims (as assessed in accordance with the reasons for judgment) (vii) Whether the Council should be given leave to amend its claim so as to be able to claim liquidated damages, and the resolution of such a claim (if it be allowed) (viii) Interest, if any (ix) The costs of the trial and the remitted hearing.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established