Civil and Administrative Tribunal
New South Wales
Medium Neutral Citation: Sharma v Manhattan Custom Homes Pty Ltd [2025] NSWCATCD 89 Hearing dates: 23 August 2024 Date of orders: 2 June 2025 (Amended 26 June 2025) Decision date: 02 June 2025 Jurisdiction: Consumer and Commercial Division Before: D Goldstein, Senior Member Decision: The Tribunal makes the following amended orders under section 63 of the Civil Administrative Tribunal Act 2013:
(1) Manhattan Custom Homes Pty Ltd must carry out all work required by and perform all of its obligations, including the obligation to do the work with due diligence, under the NSW Government home building contract for work over $20,000 which it signed with Ashish Sharma on 2 April 2022 in accordance with all terms conditions and covenants contained in the contract.
(2) Manhattan Custom Homes Pty Ltd must also carry out and complete all defect rectification work referred to at pages 14, 15 and 16 of the expert report of Mr Craig Nisbett dated 5 April 2024, except items 2, 3, 4 and 6.
(3) In the event that a party is minded to make an application for costs, such application must be lodged in the Tribunal and served on/given to the costs respondent within 14 days of the date of the orders in these proceedings either attaching or referring to the documents relied upon in support of the application.
(4) The costs respondent will have 14 days after the date it receives the application to lodge in the Tribunal and serve on/give to the costs applicant its submissions, if any, in response to the costs application, such submissions either attaching or referring to the documents relied upon.
(5) The parties must state in their submissions whether or not they consent to the costs application being determined on the basis of the parties written submissions and attached documents, if any, without the need for a hearing.
(6) Subject to the parties’ submissions, the Tribunal will determine any costs application made on the basis of the submissions and papers filed in the Tribunal.
Catchwords: BUILDING and CONSTUCTION – NSW Government home building contract for work over $20,000 – Contract not terminated at the time of the hearing – Notice of suspension – Meaning of ‘prevents the contractor from carrying on the work’ – Clause 24
Legislation Cited: Home Building Act 1989
Cases Cited: Brewarrina Shire Council v Beckhaus Civil Pty Ltd [2005] NSWCA 248
Little v J & K Homes Pty Ltd [2017] NSWCATAP 84
Stevens v Kabushiki Kaisha Sony Computer Entertainment [2005] HCA 58; (2005) 221 ALR 448
Verma v Udhay Pty Ltd (Unreported, Consumer and Commercial Division, 7 February 2024)
Texts Cited: None cited
Category: Principal judgment Parties: Ashish Sharma (Applicant)
Manhattan Custom Homes Pty Ltd (Respondent)Representation: Counsel:
Solicitors:
J Pearson (Respondent)
Roberts Crosbie Mortensen Lawyers (Applicant)
Onelaw (Respondent)
File Number(s): 2023/00368991 Publication restriction: Nil
REASONS FOR DECISION
-
The parties entered into a NSW Government home building contract for work over $20,000…
Keep reading for free
Create a free CaseChat account to read Sharma v Manhattan Custom Homes Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2025] NSWCATCD 89
- Decision Date
CaseChat Overview and Summary
The Tribunal examined the meaning of clause 24 and whether the actions of Manhattan Custom Homes Pty Ltd amounted to preventing the contractor from carrying on the work. The Tribunal concluded that the phrase in question was intended to cover situations where the contractor was entirely unable to proceed with the work, rather than temporary interruptions or delays. Based on the evidence presented, the Tribunal determined that Manhattan Custom Homes Pty Ltd had not sufficiently demonstrated that it was entirely unable to carry on the work.
Consequently, the Tribunal ordered that Manhattan Custom Homes Pty Ltd must complete all required work under the contract and defect rectification work, with certain exceptions. The Tribunal also set out a process for any party seeking to apply for costs, including a requirement for the parties to indicate whether they consented to the application being determined on written submissions. The Tribunal retained the discretion to determine any costs application based on the submissions and papers filed.
Orders
Orders of the court
The Tribunal makes the following amended orders under section 63 of the Civil Administrative Tribunal Act 2013:
(1) Manhattan Custom Homes Pty Ltd must carry out all work required by and perform all of its obligations, including the obligation to do the work with due diligence, under the NSW Government home building contract for work over $20,000 which it signed with Ashish Sharma on 2 April 2022 in accordance with all terms conditions and covenants contained in the contract.
(2) Manhattan Custom Homes Pty Ltd must also carry out and complete all defect rectification work referred to at pages 14, 15 and 16 of the expert report of Mr Craig Nisbett dated 5 April 2024, except items 2, 3, 4 and 6.
(3) In the event that a party is minded to make an application for costs, such application must be lodged in the Tribunal and served on/given to the costs respondent within 14 days of the date of the orders in these proceedings either attaching or referring to the documents relied upon in support of the application.
(4) The costs respondent will have 14 days after the date it receives the application to lodge in the Tribunal and serve on/give to the costs applicant its submissions, if any, in response to the costs application, such submissions either attaching or referring to the documents relied upon.
(5) The parties must state in their submissions whether or not they consent to the costs application being determined on the basis of the parties written submissions and attached documents, if any, without the need for a hearing.
(6) Subject to the parties’ submissions, the Tribunal will determine any costs application made on the basis of the submissions and papers filed in the Tribunal.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.