New South Wales |
Case Name: | Rathchime Pty Ltd v Willat; Willat v Rathchime |
Medium Neutral Citation: | [2016] NSWCATCD 74 |
Hearing Date(s): | 18 November and 19 November 2016(Final submissions received 17 February 2016) |
Decision Date: | 9 September 2016 |
Jurisdiction: | Consumer and Commercial Division |
Before: | T Simon, Senior Member |
Decision: | 1. The homeowners are to pay the builder the amount of $26,688.53 immediately. |
Catchwords: | Home Building, abandonment, repudiation, abandonment, variations, defects. |
Legislation Cited: | Home Building Act 1989 (NSW) |
Cases Cited: | Brewarrina Shire Council v Beckhaus Civil Pty Ltd & 1 Or [2005] NSWCA 248. |
Category: | Principal judgment |
Parties: | Parties in HB 14/43750 (homeowners application) |
Representation: | Counsel: |
File Number(s): | HB 14/43750 & HB 15/11593 |
Publication Restriction: | Unrestricted |
REASONS FOR THE DECISION
These reasons relate to two applications. Matter HB 14/43750 is an application made by the homeowner. Application HB 15/11593 was a subsequent application made by the builder.
The Applications
For ease of reference the parties shall be referred to as builder and homeowner.
The initial application was made by the homeowner on 2 September 2014 seeking $300,000.00 for defective works.
The homeowner’s claim was subsequently amended to seeks damages for breach of the contract, breach of statutory warranties, cost savings, costs, interest and interest on costs.
The builder’s application was made on 2 March 2015 seeking an amount of $103,313.02 for outstanding monies due under the contract and unpaid variations.
Both applications were subsequently amended seeking higher amounts and the quantum’s claimed shall be dealt with in greater detail below.
Jurisdiction of the Tribunal
It is not in contest when the parties contracted. However, on 11 July 2011, the parties executed three separate contracts. The first of the three contracts had been previously provided to the homeowners in about April 2011. The contracts were in the following amounts:
(i)Contract 1 was in the amount of $560,758.57.
(ii)Contract 2 was in the amount of $499,661.39.
(iii)Contract 3 was in the amount of $142,503.54.
While the terms…
Continue reading Rathchime Pty Ltd v Willat; Willat v Rathchime
Sign in free to access the full text
- AGLC
- Rathchime Pty Ltd v Willat; Willat v Rathchime [2016] NSWCATCD 74
- Case
- [2016] NSWCATCD 74
- Decision Date
CaseChat Overview and Summary
The central legal issues were whether the homeowners had repudiated the contract and whether the builder had abandoned the project. Additionally, the court had to determine whether the builder was entitled to payment for variations and whether the builder had breached the contract by failing to complete the work to the required standard. The homeowners argued that the builder had abandoned the project due to non-payment and that they were entitled to terminate the contract. The builder, on the other hand, claimed that the homeowners had repudiated the contract and that they were entitled to payment for variations and completion of the work.
The court found that the homeowners had repudiated the contract by refusing to pay the builder for work completed and materials supplied. The court also found that the builder had not abandoned the project, despite the homeowners' claims. The builder was entitled to payment for variations and for the completion of the work to the required standard. The court further found that the builder had breached the contract by failing to complete the work to the required standard, but this breach did not entitle the homeowners to terminate the contract.
The orders made by the court included an immediate payment of $26,688.53 to the builder by the homeowners. The court also set out a schedule for the parties to provide submissions and documents in relation to costs. The court determined that costs would be decided on the papers unless either party sought to be heard in person.
Orders
Orders of the court
1. The homeowners are to pay the builder the amount of $26,688.53 immediately.
2. The parties are to provide to the Tribunal and each other, either in person or by post, submissions and documents in relation to costs by 15 September 2016.
3. The parties are to provide to the Tribunal and each other, either in person or by post, submissions and documents in reply on costs by 30 September 2016.
4. Costs will be determined on the papers. If either party seeks to be heard in person, they should advise the Registry prior to 30 September 2016, setting out the reasons why and the Registry will advise in due course.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.