Thompson Residential Pty Ltd v Hart & Anor

Link copied
Case Copied 71 min read

DISTRICT COURT OF QUEENSLAND

CITATION:

Thompson Residential Pty Ltd v Hart & Anor [2014] QDC 132

PARTIES:

THOMPSON RESIDENTIAL PTY LTD
(plaintiff)

v

MICHAEL CHARLES HART
(first defendant)

and

MARGARET ANN HART
(second defendant)

FILE NO/S:

BD 1011/12

DIVISION:

PROCEEDING:

Trial

ORIGINATING COURT:

District Court at Brisbane

DELIVERED ON:

11 April 2014

DELIVERED AT:

Brisbane

HEARING DATE:

18-22 November 2013

JUDGE:

McGill SC DCJ

ORDER:

Judgment for the defendants with costs.

CATCHWORDS:

BUILDING AND ENGINEERING CONTRACTS – Remuneration – progress payments – “enclosed stage” – not completed – no right to claim – contract validly terminated by owners.

BUILDING AND ENGINEERING CONTRACTS – Remuneration – progress payments – substantial performance doctrine not applicable.

Ankar Pty Ltd v National Westminster Finance (Australia) Ltd (1987) 162 CLR 549 – cited.
Bolton v Mahadeva [1972] 1 WLR 1009 – cited.
Brewarrina Shire Council v Beckhaus Civil Pty Ltd [2005] NSWCA 248 – cited.
Cardona v Brown [2010] VSC 368 – cited.
Connor v Stainton (1924) 27 WALR 72 – considered.
Con-Stan Industries of Australia Pty Ltd v Norwich Winterthur Insurance (Aust) Ltd (1986) 160 CLR 226 – cited.
Cordon Investments Pty Ltd v Lesdor Properties Pty Ltd [2012] NSWCA 184 – applied.
Eshelby v Federated European Bank Ltd [1932] 1 KB 423 – cited.
Highmist Pty Ltd v Tricare Ltd [2005] QCA 357 – applied.
Hoenig v Isaacs [1952] 2 All ER 176 – considered.
Horton Geoscience Consultants Pty Ltd v Energy Minerals Pty Ltd [2005] QCA 169 – cited.
Hospital Products Ltd v United States Surgical Corporation (1984) 156 CLR 421 – cited.
Kevru Industries Pty Ltd v Barnes (unreported, Supreme Court of New South Wales, Cross J, 16 July 1981, BC 8111557) – considered.
Lemura v Coppola [1960] Qd R 308 at 314 – cited.
McGibbo Pty Ltd v Willex Projects Pty Ltd [2013] QDC 313 – followed.
Morgan v S & S Constructions Pty Ltd [1967] VR 149 – cited.
Ownit Homes Pty Limited v Batchelor [1983] 2 Qd R 124 – cited.
Phillips v Ellinson Brothers Pty Ltd (1941) 65 CLR 221 – applied.
Progressive Mailing House Pty Ltd v Tabali Pty Ltd (1985) 157 CLR 17 – cited.
Queensland Alumina Ltd v Alinta DQP Pty Ltd [2006] QSC 391 – cited.
Shevill v Builders Licensing Board (1982) 149 CLR 620 – cited.
Simpson Steel Structures v Spencer [1964] WAR 101 – considered.
Sopov v Kane Constructions Pty Ltd (2008) 20 VR 127 – cited.
Sumpter v Hedges [1898] 1 QB 673 – cited.
Tricontinental Corporation Ltd v HDFI Ltd (1990) 21 NSWLR 689 – applied.
Williamson v Murdoch (1912) 14 WALR 54 – considered.
Zachary Developments Pty Ltd v Turner [2012] QCATA 86 – not followed.
Zamperoni Decorators Pty Ltd v Lo Presti [1983] 1 VR 338 – cited.

COUNSEL:

S McNeil for the plaintiff

G I Thomson for the defendants

SOLICITORS:

Holding Redlich for the plaintiff

CBP Lawyers for the defendants

  1. The parties entered into a contract for the plaintiff to build a residence for the defendants…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Thompson Residential Pty Ltd v Hart & Anor and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2014] QDC 132
Decision Date

CaseChat Overview and Summary

Thompson Residential Pty Ltd sought a declaration that it was entitled to progress payments from Hart and Anor. The defendants argued that the contract had been validly terminated due to the plaintiff’s failure to complete the works to an acceptable standard. The court had to determine whether the plaintiff was entitled to any progress payments despite the contract being terminated and whether the doctrine of substantial performance applied.

The court considered whether the plaintiff had completed the works to a satisfactory standard as required by the contract. It examined the evidence and concluded that the plaintiff had not completed the works to an acceptable standard, leading to the contract's valid termination. The court held that the substantial performance doctrine was not applicable in this case, as it did not consider the works to be substantially complete. The court found that the contract clearly stipulated the standards to be met and that the plaintiff's failure to meet these standards justified the termination.

The court further examined relevant case law and found that the plaintiff's entitlement to progress payments was contingent on the completion of the works to the specified standards. Given that the plaintiff had not achieved this, the court ruled in favour of the defendants. The court determined that the plaintiff was not entitled to any progress payments and that the contract was validly terminated.

The court ordered that judgment be entered for the defendants, with costs awarded to Hart and Anor.

Orders

Orders of the court

Judgment for the defendants with costs.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.