QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION:
Purnell & Anor v Manson [2023] QCATA 77
PARTIES:
SARAH PURNELL
STEWART BRETT
(applicants/appellants)
v
LEE MANSON T/AS MANSON HOMES (respondent)
APPLICATION NO/S:
APL346-19
ORIGINATING APPLICATION NO/S:
BDL117-14
MATTER TYPE:
Appeals
DELIVERED ON:
27 June 2023
HEARING DATE:
On the papers
HEARD AT:
Brisbane
DECISION OF:
Senior Member Brown, Presiding
Senior Member Traves
ORDERS:
1. Leave to appeal granted.
2. Appeal allowed.
3. Order 1 of the decision dated 18 November 2019 is set aside and in lieu thereof it is ordered that Lee Manson t/as Manson Homes must pay Sarah Purnell and Stewart Brett the amount of $20,103.00.
4. The parties must file in the Tribunal two (2) copies and exchange one (1) copy of any submissions on costs within fourteen (14) days and any submissions in reply within seven (7) days thereafter.
5. The submissions on costs must not exceed five (5) pages in length.
6. The Appeal Tribunal will determine the costs of the appeal, on the papers, upon the expiration of the time for compliance with order 4.
CATCHWORDS:
APPEAL AND NEW TRIAL – APPEAL – GENERAL PRINCIPLES – RIGHT OF APPEAL – WHEN APPEAL LIES – OTHER CASES – error of fact or mixed law and fact – where the appellant homeowners were found to have terminated the contract with the respondent builder – where the tribunal below awarded the homeowners damages for the cost of completing the works and rental expenses – where homeowners’ damages reduced by builder’s entitlement to quantum meruit – whether the tribunal erred in assessing the homeowners’ entitlement to damages – whether the tribunal erred in allowing the builder to recover on a quantum meruit basis in respect of incomplete building stages – whether the homeowners failed to mitigate their loss
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION – RECOVERY ON QUANTUM MERUIT – IN GENERAL – where the contract price was payable by progress payments for each stage – where the tribunal below found that the builder was entitled on a quantum meruit to reimbursement for work performed under the relevant stage of the contract where the stage was incomplete – whether the appellant homeowners freely accepted the benefits flowing from the builder’s part performance – whether basis exists for claim of quantum meruit
Queensland Civil and Administrative Tribunal Act 2009 (Qld), s 142(1), s 142(3)(b), s 147(2), s 147(3)
Amundsen v Queensland College of Teachers [2011] QCATA 2
Bellgrove v Eldridge (1954) 90 CLR 613
Burns v MAN Automotive (Aust) Pty Ltd (1986) 161 CLR 653
Earthworks and Quarries Ltd v FT Eastman & Sons Pty Ltd [1966] VR 24
GDLA v GMG [2017] QCATA 18
Harrison & Anor v Meehan [2017] QCA 315
Hasell v Bagot, Shakes & Lewis Ltd (1911) 13 CLR 374
Knott Investments Pty Ltd v Fulcher [2014] 1 Qd R 21
Lee Manson t/as Manson Homes v Brett & Anor [2017] QCATA 124
Lee Manson t/as Manson Homes v Brett & Purnell [2016] QCAT 282
Continue reading Purnell v Manson
Sign in free to access the full text
- AGLC
- Purnell v Manson [2023] QCATA 77
- Case
- [2023] QCATA 77
- Decision Date
CaseChat Overview and Summary
The court found that the tribunal erred in allowing the builder to recover on a quantum meruit basis. The court held that the builder was not entitled to recover on a quantum meruit basis for the work done under the relevant stage of the contract, where the work performed was not to the standard necessary under the contract. The court noted that there is no basis for a claim for quantum meruit in such circumstances, and that the application of quantum meruit does not depend on who treated the contract as discharged. The court found that the homeowners had not freely accepted the benefits flowing from the builder's part performance, and that it was difficult to demonstrate that the homeowners had a proper opportunity to reject, or accept, the work.
The court allowed the appeal and set aside the decision of the tribunal below. The court ordered that Lee Manson t/as Manson Homes must pay Sarah Purnell and Stewart Brett the amount of $20,103.00. The parties were required to file and exchange submissions on costs within a specified timeframe. The Appeal Tribunal would determine the costs of the appeal on the papers.
Orders
Orders of the court
1. Leave to appeal granted.
2. Appeal allowed.
3. Order 1 of the decision dated 18 November 2019 is set aside and in lieu thereof it is ordered that Lee Manson t/as Manson Homes must pay Sarah Purnell and Stewart Brett the amount of $20,103.00.
4. The parties must file in the Tribunal two (2) copies and exchange one (1) copy of any submissions on costs within fourteen (14) days and any submissions in reply within seven (7) days thereafter.
5. The submissions on costs must not exceed five (5) pages in length.
6. The Appeal Tribunal will determine the costs of the appeal, on the papers, upon the expiration of the time for compliance with order 4.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
The application to rely upon fresh evidence is refused. Consideration For reasons that will become apparent, we will first consider appeal ground 4. Did the tribunal err in allowing the builder to recover on a quantum meruit for the enclosed stage works, and further works, which were completed by the builder? – ground of appeal 4 The contract price was payable by seven progress payments: deposit, demolition and excavation, base, frame, enclosed, fixing and final. The appellants paid the first four stage payments. The respondent submitted a claim for the enclosed stage which the appellants disputed. It was at this stage that the appellants terminated the contract. The respondent claimed that he was entitled to be paid for the work performed until the termination of the contract. The learned member found that, notwithstanding the builder was in breach, the builder was entitled to recover from the homeowners $77,232.30 on a quantum meruit for works completed up to, and beyond, the enclosed stage. The learned member did not consider the building contract to be entire.[34] The parties approached the dispute both below and in the appeal on the basis that the contract was not entire, but rather a series of entire obligations which were defined by the stages of payment contemplated by the contract. [34]Second decision, at [132] - [135]. It is clear that, in respect of the enclosed stage the subject of dispute and the work undertaken beyond the enclosed stage, the work performed by the respondent was not to the standard necessary under the contract to give rise to an obligation under the contract to pay for it.[35] [35]Thompson Residential Pty Ltd v Hart & Anor [2014] QDC 132 (McGill SC DCJ). The question becomes, therefore, whether the builder was entitled to a payment on the basis of a quantum meruit for work done under the relevant stage of the contract, but not to the standard required by the contract to permit payment pursuant to it. That is, may the builder in default in the present circumstances recover on the basis of quantum meruit, where no claim under the contract may be made? In our view, there is no basis for a claim for quantum meruit in the present circumstances. There is support for the proposition that in some circumstances a builder in default of completion of a stage may recover a reasonable sum for work done within that stage. In Steele v Tardiani,[36] Latham CJ adopted as correct the following rule:Where work is done by one party under a special contract, but not according to its terms, the other may refuse to accept it; but if he does accept it and takes the benefit of it, he may be sued for the value on this [common indebitatus] count [for work done].[37][36](1946) 72 CLR 386.[37]Ibid, 393; see also at 402; Phillips v Ellinson Brothers Pty Ltd (1941) 65 CLR 221, 234, 246; Earthworks and Quarries Ltd v FT Eastman & Sons Pty Ltd [1966] VR 24. It follows that the application of quantum meruit does not depend on who treated the contract as discharged. The learned authors of Mason & Carter’s Restitution Law in Australia express the view that, in principle, there is no reason why the fact that the plaintiff breached the contract should be conclusive.[38] However, for a builder in breach to recover under a quantum meruit it must be demonstrated that the innocent party accepted the benefit of the work, within the meaning of the authorities.[39] These circumstances will be rare and will ordinarily not be established where the owner has done no more than build upon work which was incomplete under the contract.[40] In such circumstances, it will be difficult for a builder to demonstrate that the owner had a proper opportunity to reject, or accept, the work.[38]K Mason, J W Carter and G J Tolhurst, Mason & Carter’s Restitution Law in Australia (LexisNexis, 3rd ed, 2016) [1155].[39]Sumpter v Hedges [1898] 1 QB 673; Steele v Tardiani (1946) 72 CLR 386, 403.[40]Ibid.