QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION:
Partington & Anor v Urquhart (No 2) [2018] QCATA 120
PARTIES:
PHILLIP PARTINGTON
EVELYN PARTINGTON
(applicants/appellants)v JOHN URQUHART T/AS HART RENOVATIONS
(respondent)
APPLICATION NO/S:
APL131-13
ORIGINATING APPLICATION NO/S:
BDL072-10
MATTER TYPE:
Appeals
DELIVERED ON:
10 August 2018
HEARING DATE:
On the papers
HEARD AT:
Brisbane
DECISION OF:
Senior Member Howard, Presiding
Member TravesORDERS:
1. The submissions filed by Phillip Partington and Evelyn Partington in July 2017 are struck out.
2. Leave to appeal is granted.
3. The appeal is allowed.
4. (a) Order 1 of the Tribunal decision dated 19 February 2013 is set aside.
(b) In substitution for order 1 dated 19 February 2013:
(i) The Appeal Tribunal declares that:
a. John Urquhart t/as Hart Renovations is entitled to a quantum meruit in the sum of $160,162.89;
b. Phillip Partington and Evelyn Partington are entitled to damages and interest of $171,938.50;
(ii) The questions of whether interest may be awarded on a quantum meruit, and if so, whether it should be awarded, and if so, in what amount are reserved for further determination on the papers not before 4:00pm on 24 August 2018.
(iii) The Appeal Tribunal directs that the parties may file in the Appeal Tribunal and serve on the other party written submissions limited to two (2) A4 pages in 12 point font about the issues referred to in (ii) above, by 4:00pm on 24 August 2018.
(iv) The Appeal Tribunal directs that the parties must file in the Appeal Tribunal two (2) copies and serve on the other party written submissions limited to two (2) A4 pages in 12 point font about the form of the final orders to be made in substitution of Tribunal order 1 dated 19 February 2013, setting out details of payments made pursuant to the Tribunal order dated 19 February 2013 to be brought into account, by 4:00pm on 24 August 2018.
(v) Further orders will be made in substitution of order 1 dated 19 February 2013 by the Appeal Tribunal not before 4.00pm on 24 August 2018.
5. Order 2 of the Tribunal decision dated 19 February 2013 is confirmed.
CATCHWORDS:
APPEAL AND NEW TRIAL – APPEAL – GENERAL PRINCIPLES – POINTS AND OBJECTIONS NOT TAKEN BELOW – QUESTIONS NOT RAISED ON PLEADINGS OR IN ARGUMENT GENERALLY – where matter remitted from Court of Appeal to Appeal Tribunal – where all issues not considered before the Appeal Tribunal as originally constituted – where newly constituted Appeal Tribunal to conduct rehearing
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – THE CONTRACT – PERFORMANCE OF WORK REMEDIES FOR BREACH OF CONTRACT – DAMAGES – MEASURE OF – whether enclosed stage completed at time progress claim made – whether non-compliant and defective works preclude stage from being complete – enclosed stage invoice not received – effect of variations not in writing – contract not properly terminated under clause 28 – whether contract terminated at law
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS –…
Keep reading for free
Create a free CaseChat account to read Partington & Anor v Urquhart (No 2) and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2018] QCATA 120
- Decision Date
CaseChat Overview and Summary
The legal issues before the Appeal Tribunal included whether the enclosed stage of the renovation was completed as per the contract at the time the progress claim was made, whether non-compliant and defective works precluded the stage from being deemed complete, and whether the contract was properly terminated under the terms of the agreement. Additionally, the tribunal had to consider the appropriate measure of damages, including the cost of rectification by the homeowners and the builder's entitlement to a quantum meruit. The tribunal also needed to address the assessment of interest on the quantum meruit, if any, and the form of final orders considering any payments already made by the parties.
The Appeal Tribunal, after reviewing the evidence and the original tribunal's decision, concluded that the builder was liable for damages for non-completion, the cost to complete the work, and the cost of rectification, along with interest. The tribunal allowed the appeal and set aside the original order, substituting it with a declaration of the amounts owed by the builder to the homeowners and by the homeowners to the builder on a quantum meruit. The tribunal also reserved the question of interest on the quantum meruit for further submissions by the parties. Directions were issued for the parties to file written submissions regarding the quantum meruit interest and the final form of orders by a specified deadline.
The tribunal confirmed some findings of the original tribunal, while allowing the appeal on others, leading to the setting aside of the original order and the substitution of a new one. This decision reflects a comprehensive review of the contractual obligations, the performance of work, and the legal remedies available under the circumstances.
Orders
Orders of the court
1. The submissions filed by Phillip Partington and Evelyn Partington in July 2017 are struck out.
2. Leave to appeal is granted.
3. The appeal is allowed.
4. (a) Order 1 of the Tribunal decision dated 19 February 2013 is set aside.
(b) In substitution for order 1 dated 19 February 2013:
(i) The Appeal Tribunal declares that:
a. John Urquhart t/as Hart Renovations is entitled to a quantum meruit in the sum of $160,162.89;
b. Phillip Partington and Evelyn Partington are entitled to damages and interest of $171,938.50;
(ii) The questions of whether interest may be awarded on a quantum meruit, and if so, whether it should be awarded, and if so, in what amount are reserved for further determination on the papers not before 4:00pm on 24 August 2018.
(iii) The Appeal Tribunal directs that the parties may file in the Appeal Tribunal and serve on the other party written submissions limited to two (2) A4 pages in 12 point font about the issues referred to in (ii) above, by 4:00pm on 24 August 2018.
(iv) The Appeal Tribunal directs that the parties must file in the Appeal Tribunal two (2) copies and serve on the other party written submissions limited to two (2) A4 pages in 12 point font about the form of the final orders to be made in substitution of Tribunal order 1 dated 19 February 2013, setting out details of payments made pursuant to the Tribunal order dated 19 February 2013 to be brought into account, by 4:00pm on 24 August 2018.
(v) Further orders will be made in substitution of order 1 dated 19 February 2013 by the Appeal Tribunal not before 4.00pm on 24 August 2018.
5. Order 2 of the Tribunal decision dated 19 February 2013 is confirmed.
Background
Background to the litigation
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
In the Specification under Timber Weatherboard Cladding it provides:PreparationPrime all faces of boards prior to installation.Nails:Hot dip galvanised to non-corrosive timbersSilica bronze or stainless steel to corrosive timbers Nailheads: Treat visible nailheads as follows:In stained or clear finishes: Drive flush.In opaque finishes: Punch below the surface and fill flush with putty after the surface has been primed.JointsOverlapping joints: Lap boards at least 30mmEnd grain joints: Install boards so that butt joints are in compression.[87][87]Specification, 35, [3.3]. Drawings WD201, 202, 301, 302, 303 and 304 show where the hardwood is to be applied (indicated by WB). The only section to use pine (WB1) was the upper floor blade wall on the eastern side of the house.[88] We find that the contract provided for the use of hardwood chamfer boards in the areas identified, but that pine was used. Was there an effective oral variation to use pine chamfer boards instead of hard wood chamfer boards?[88]Statement of Evelyn Partington, 26 November 2010, [107]-[108]. The Tribunal at first instance found that the builder used the incorrect chamfer board. The Tribunal preferred Mrs Partington’s evidence on this issue to that of the builder.[89] However, in context, having regard to the overall evidence and the Tribunal’s reasons for decision, we are satisfied that the Tribunal’s finding was limited to the requirements of the contract. The Tribunal did not make findings about whether or not, having regard to a conversation between the builder and Mr Partington on 5 February 2009, there was an oral agreement to vary the contract by permitting pine chamfer boards rather than hardwood boards. (If we are wrong about the scope of the Tribunal’s finding, in any event, we would find that no reasonable arbiter of fact could have reached a different conclusion based on the evidence, discussed below, to the effect that it was common ground that the homeowners had agreed to the use of pine instead of hardwood chamfer boards).[89][2013] QCAT 133, [71](o). Any reliance on the Barac and Michelsen quotes as evidence was abandoned by the Partingtons.[162] Mr Barac and Mr Michelsen were not witnesses and the basis for the quotes they provided was untested by cross-examination. It is not now appropriate or permissible to consider their quotes on appeal as the homeowners are bound by the case they presented.[162]Reasons, [85] regarding the Barac quote; and Transcript of Proceedings, John Urquhart trading as Hart Renovations v Partington (QCAT, BDL072-10, Senior Member Oliver, 27 August 2012) 282-284, regarding the Barac and Michelsen quotes. Mr Bowman, the civil engineer engaged by the homeowners, considered that the slab could be replaced, ‘scrabbled back’ or just left alone.[163][163]Transcript of Proceedings, John Urquhart trading as Hart Renovations v Partington (QCAT, BDL072-10, Senior Member Oliver, 27 August 2012) 137-138. The principal reason for the Senior Member accepting the evidence of Mr Ray over Mr Groom in a number of respects is the fact that Mr Ray provided greater detail in respect of the costs and the work to been done to undertake rectification.