SUPREME COURT OF THE AUSTRALIAN CAPITAL TERRITORY
Case Title: | Maples Winterview Pty Ltd v Liu & Anor |
Citation: | [2015] ACTSC 58 |
Hearing Dates: | 23-24, 26-27 February 2015 |
DecisionDate: | 16 July 2015 |
Before: | Mossop AsJ |
Decision: | See [160] |
Category: | Principal Judgment |
Catchwords: | CONTRACT – standard form building contract – floor slab stage of construction not completed – claim for progress payment from owners dependent on completion of the relevant and any preceding stages of construction – test for completion of stage – failure by owners to make payment found not in breach of contract – termination of contract by builder found wrongful – no alternative basis for liability of owners pleaded by builder CONTRACT – implied duty to cooperate – failure to obtain bank loan – no breach of duty where no obligation under contract to obtain the loan |
Legislation Cited: | Building Act 2004 (ACT) Construction Occupations (Licensing) Act 2004 (ACT) Court Procedures Rules 2006 (ACT) |
Cases Cited: | Adrija Pty Ltd v Mohamed [2013] ACTSC 120 Australis Media Holdings Pty Ltd v Telstra Corporation Ltd (1998) 43 NSWLR 104 Tabcorp Holdings Ltd v Bowen Investments Pty Ltd (2009) 236 CLR 272 |
Texts Cited: | Hudson’s Building and Engineering Contracts (12th edition, Sweet & Maxwell) |
Parties: | Maples Winterview Pty Ltd (Plaintiff) Bin Liu (First Defendant) Chen Huan Li (Second Defendant) |
Representation: | Counsel Mr R Thomas (Plaintiff) Self-represented (First Defendant) Self-represented (Second Defendant) |
| Solicitors Fitzgerald Naylor Lawyers (Plaintiff) Self-represented (First Defendant) Self-represented (Second Defendant) | |
File Number: | SC 418 of 2013 |
Introduction
The plaintiff is a building company. It has brought proceedings against the first and second defendants, the joint owners of a property which is located in Roy Marika Street in Bonner in the Australian Capital Territory (the premises).
The claim arises out of a relatively simple standard form building contract. It seeks payment of an amount said to be owed by the defendants following termination of the building contract by the plaintiff.
The determination of the claim is complicated by four factors. The first is the fact that during the construction project that has led to the claim the person responsible for the plaintiff’s construction of the dwelling died and the record keeping by the plaintiff was not as good as it might have been. The second is the fact that the defendants, for whom English is a second language, were unrepresented during the course of the proceedings. The third is that because of the scope…
Keep reading for free
Create a free CaseChat account to read Maples Winterview Pty Ltd v Liu & Anor and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2015] ACTSC 58
- Decision Date
CaseChat Overview and Summary
The primary legal issues before the court involved the interpretation of the contract regarding the completion of construction stages and the builder's right to terminate the contract. Additionally, the court had to determine whether the owners' failure to obtain a bank loan constituted a breach of the implied duty to cooperate. The builder argued that the owners' actions warranted termination of the contract, while the owners maintained that the builder's termination was wrongful and unjustified. The court had to examine the terms of the contract, the obligations of both parties, and the circumstances under which the builder could lawfully terminate the agreement.
The court found that the floor slab stage had not been completed as required by the contract, thereby negating the builder's claim for the progress payment. The builder's termination of the contract was deemed wrongful as no valid grounds for termination were established. Furthermore, the court held that the owners' failure to obtain the bank loan did not amount to a breach of the implied duty to cooperate, as there was no contractual obligation to secure such a loan. Consequently, the builder's claim against the owners was dismissed in its entirety.
The court ordered that Maples Winterview Pty Ltd pay the costs of the proceeding, as determined by the Registrar. The owners were not held liable for any payment to the builder, and the builder's wrongful termination did not entitle them to any additional damages or costs.
Orders
Orders of the court
See [160]
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.