SUPREME COURT OF VICTORIA
COURT OF APPEAL
S APCI 2010 0113
| PAUL CARDONA and LAUREN BROWNSCOMBE | Appellants |
| v | |
| ROD BROWN and WENDY BROWN | Respondents |
---
| JUDGES | BONGIORNO, TATE and OSBORN JJA |
| WHERE HELD | MELBOURNE |
| DATE OF HEARING | 27 June 2012 |
| DATE OF JUDGMENT | 13 August 2012 |
| MEDIUM NEUTRAL CITATION | [2012] VSCA 174 1st Revision, 15 August 2012, [30] |
| JUDGMENT APPEALED FROM | Cardona v Brown [2010] VSC 368 (Pagone J) |
---
CONTRACT – Claim for progress payment – Whether claim for completion of lock-up stage depends upon builder having first completed frame stage – Whether open for trial judge to find that lock-up stage had been completed – Whether ‘home’ included garage – Which party repudiated contract – Whether builders’ demand for progress payment for lock-up stage was premature – Whether builders’ notice for suspension of works was premature – Domestic Building Contracts Act 1995 (Vic) ss 3, 5, 40 – Appeal allowed.
---
| Appearances: | Counsel | Solicitors |
| For the Appellants | Mr J Digby QC with Mr B F H Miller | Simon Parsons & Co |
| For the Respondents | Mr R A Edmunds | Littleton Hackford & D’Alessandro |
BONGIORNO JA
I have had the advantage of reading in draft the reasons for judgment of Tate JA. I agree with her Honour that the appeal should be allowed for the reasons she gives.
TATE JA:
Introduction
Paul Cardona and Lauren Brownscombe (‘the owners’) entered into a building contract (‘the contract’) with Rod and Wendy Brown (‘the builders’) for the construction of their new home on land they owned. The contract was in the form of a standard ‘Plain English’ contract for domestic new homes, the Victorian ‘New Homes Contract’.[1] It was for the construction of ‘the Building Works’ comprising a brick veneer dwelling to be built in accordance with the specifications and plans (‘the plans’) prepared by building consultants.[2] The plans indicated that the dwelling included a master suite, a study, lounge, a family and meals area, two additional bedrooms, a verandah for outdoor living, a garage at the right hand side of the house and a covered area at the left hand side. The house and the garage were to be covered by the one roof. The contract price (including the garage) was $245,245.00.
[1]Issued by the Housing Industry Association Limited.
[2]Particulars of Contract.
The owners and the builders agreed that the method of payment they would use was a series of progress payments in accordance with five separate stages: these being the base stage; frame stage; lock-up stage; fixing stage; and completion. These stages reflected those defined under the Domestic Building Contracts Act 1995 (Vic) (‘the Act’).
The builders made a claim for payment for the frame stage. The claim was
paid but later disputed. The builders made a later claim for payment for the lock-up stage. The owners refused to pay on two grounds: (1) the builders were not entitled to a payment for the lock-up stage when the frame stage had not been completed; and (2) in any event, the…
Continue reading Cardona v Brown
Sign in free to access the full text
- AGLC
- Cardona v Brown [2012] VSCA 174
- Case
- [2012] VSCA 174
- Decision Date
CaseChat Overview and Summary
The court found that the trial judge was open to finding that the lock-up stage was completed, and that the ‘home’ included the garage. The court also found that Cardona had not repudiated the contract. The court found that Brown’s demand for progress payment was premature, as the lock-up stage had not yet been completed. The court found that Brown’s notice for suspension of works was also premature, as Brown had not yet completed the lock-up stage. The appeal was allowed, and the matter was remitted to the trial judge.
The final orders of the court were that Cardona’s appeal be allowed, and the matter be remitted to the trial judge. The court found that Brown’s demand for progress payment and notice for suspension of works were premature, and that Cardona was not obliged to pay Brown for the lock-up stage. The court also found that the ‘home’ included the garage, and that the lock-up stage was completed. The matter was remitted to the trial judge for further consideration.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.